Kenitra-Marrakech high-speed line

Location
Kenitra (Sidi Ichou) to Marrakech, Rabat-Salé-Kénitra / Casablanca-Settat / Marrakech-Safi, Morocco. See it on the map, in 3D
Stage
Under construction, as of November 11, 2026 (Le360). The Minister of Transport put the line at 30% complete on 25 May 2026; Le360 reported about 35% in November 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerONCF (Office National des Chemins de Fer)
TypeRail
Headline amountMAD 4 billion (MAD), as of April 27, 2025Médias24 (interview of Khalid Khairane, ONCF high-speed project director)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length430 kmprojectMaroc Hebdo (ONCF communiqué of 24 April 2026)
Design speed350 km/hprojectLe360 (MAP release)
Operating speed320 km/hprojectMédias24
Land takeAbout 3,500 haprojectMédias24 (interview of Khalid Khairane, ONCF high-speed project director)
Earthworks doneNearly 20,000,000 m3project, at 2026-04-24Maroc Hebdo (ONCF communiqué of 24 April 2026)
Viaducts under construction15project, at 2026-04-24Maroc Hebdo (ONCF communiqué of 24 April 2026)
Rail and road bridges under way92project, at 2026-04-24Maroc Hebdo (ONCF communiqué of 24 April 2026)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 53 bnBudgetproject (infrastructure and equipment, excluding rolling stock)April 24, 2025Le360 (MAP release)
MAD 96 bnInvestment programmeONCF programme: LGV 53bn, 168 trains 29bn, network performance 14bnApril 24, 2026Maroc Hebdo (ONCF communiqué of 24 April 2026)
MAD 4 bnBudgetland acquisition (included in the 53bn)April 27, 2025Médias24 (interview of Khalid Khairane, ONCF high-speed project director)
MAD 40 bnLoanshare of a MAD 48bn regional financing protocol (regions Casablanca-Settat, Rabat-Salé-Kénitra, Marrakech-Safi, MAD 16bn each, via 25-year bank loans) allocated to the LGVJuly 7, 2025La Vie éco
€205 MLoanAfDB, railway infrastructure development support project (PADIF) for the Kenitra-Marrakech corridorNovember 20, 2026African Development Bank
MAD 3.4 bnContract valuecivil works lot 1, Sidi Ichou-Rabat, 62 kmOctober 22, 2024Challenge.ma
MAD 4.5 bnContract valuecivil works lot 2, Rabat-Agdal-Zenata, 64 kmOctober 22, 2024Challenge.ma
MAD 2.15 bnContract valuecivil works lot 3, Casablanca bypass-Berrechid, 36 kmOctober 22, 2024Challenge.ma
MAD 2.4 bnContract valuecivil works lot 3-bisNovember 20, 2024La Vie éco
MAD 2.83 bnContract valuecivil works lot 4, Berrechid-Settat, 51 kmOctober 22, 2024Challenge.ma
MAD 2.83 bnContract valuecivil works lot 5, Settat-Benguerir, 36 kmOctober 22, 2024Challenge.ma
MAD 2.1 bnContract valuecivil works lot 6, Benguerir-Marrakech Palmeraie, 60 kmNovember 21, 2024Le Nouvelliste
MAD 2 bnContract valuecivil works lot 7, Marrakech Palmeraie-Marrakech centreOctober 22, 2024Challenge.ma
MAD 1.4 bnContract valueRabat tunnel (3.3 km)June 28, 2024Médias24
€200 MContract valuetrack, catenary and substations, north section, 346 km single trackMarch 2, 2025Railway Gazette International
€50 MContract valuesuperstructure and civil works on lines in operation, 112 track-kmMarch 2, 2025Railway Gazette International
€29 MContract valuetrack and catenary, Roches-Noires station to Nouaceur technicentreNovember 12, 2026Yabiladi
MAD 444 MContract valuestructures and road reinstatement, Kenitra-Aïn Attiq sectionMarch 18, 2026La Vie éco
MAD 563 MContract valuestations lot 3: Marrakech-Guéliz station and Marrakech technicentreJuly 27, 2026La Vie éco
MAD 438 MContract valueBenguerir Ville Verte LGV station and four RER stationsOctober 15, 2026La Vie éco
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONCF (Office National des Chemins de Fer)Ownerproject owner and future operatorLe360 (MAP release)
China Railway No.4 Engineering Group (CREC 4)Contractor, one lotcivil works lot 1, Sidi Ichou-Rabat, 62 km, MAD 3.4bnChallenge.ma
Shandong Hi-Speed Engineering Construction GroupContractor, one lotcivil works lot 2, Rabat-Agdal-Zenata, 64 km, MAD 4.5bn (4.05bn per Le Nouvelliste)Challenge.ma
GTR (Les Grands Travaux Routiers, Colas subsidiary)Contractor, one lotcivil works lot 3, Casablanca bypass-Berrechid, MAD 2.15bn / nearly EUR 180m, earthworks and 5 bridges over 40 km, completion end 2027Railway PRO (relaying Colas)
STAM (Société de Travaux Agricoles Marocains)Contractor, one lotcivil works lot 3-bis, MAD 2.4bn (estimate MAD 3bn); competitors were CCECC, China Gezhouba Group and SNCE/CAPEP/SEPROBLa Vie éco
TGCCContractor, one lotcivil works lot 4, Berrechid-Settat, 51 km, MAD 2.83bn; also stations lot 3 (Marrakech-Guéliz station and technicentre, MAD 562.7M)Challenge.ma
CRCC 20 (China Railway 20th Bureau Group)Contractor, one lotcivil works lot 5, Settat-Benguerir, 36 km (MAD 2.83bn per Challenge, 1.8bn per Le Nouvelliste)Challenge.ma
China Railway Construction Corporation (CRCC)Contractor, one lotOum Er-Rbia bridge, described by Barlamane as the main structure of 'lot 9' (6.23 km, six major bridges)Barlamane
Jet ContractorsContractor, one lotcivil works lot 6, Benguerir-Marrakech Palmeraie, 60 km, MAD 2.098bn; Grand Stade Hassan II LGV station (MAD 415.5M); Benguerir Ville Verte LGV station and four RER stations (MAD 437.5M)La Vie éco
MojazineContractor, one lotcivil works lot 7, Marrakech Palmeraie-Marrakech centre, MAD 2bnChallenge.ma
SGTM with Sinohydro Bureau 5Contractor, one lotRabat tunnel, 3,300 m, MAD 1.4bn, 42 monthsMédias24
Colas Rail with SETECContractor, one lottrack, catenary and substations north section (EUR 200m) and works on lines in operation (EUR 50m); Colas Rail alone: Roches-Noires to Nouaceur technicentre (about EUR 29m, Nov 2026)Railway Gazette International
Generale Costruzioni Ferroviarie (GCF)Contractor, one lottrack construction lot 2 (GCF project page), bases at Sidi El Aidi and BenguerirGenerale Costruzioni Ferroviarie
NGE ContractingContractor, one lotstructures and road reinstatement Kenitra-Aïn Attiq, MAD 443.5MLa Vie éco
Urbagec-SeparatorContractor, one lotstations lot 4: Mohammed V airport LGV station, MAD 394.4M excl. VATLa Vie éco
Sogea MarocContractor, one lotCasa-Sud LGV station, about MAD 945MLa Vie éco
Cogifer France (Vossloh Cogifer)Supplierturnouts (appareils de voie)Médias24
Egis, Systra and NovecEngineerproject management assistance (AMO)Médias24
AlstomSupplier18 Avelia Horizon high-speed trainsets (12 firm, 6 optional)LesEco.ma
Regions of Casablanca-Settat, Rabat-Salé-Kénitra and Marrakech-SafiLenderMAD 16bn each through long-term loans (Attijariwafa bank 24bn, BCP 8bn, CDG 8bn, Bank of Africa 6bn, Bank Al-Maghrib 2bn per the region's president)La Vie éco
African Development Bank (AfDB)LenderEUR 205m PADIF loan for the Kenitra-Marrakech corridorAfrican Development Bank
China Gezhouba GroupContractor, one lotcivil works lot 9, viaducts over the Ikkem, Cherrat, Nfifikh, Dir and Maleh north and south wadis, MAD 2.32bnLe360
COVECContractor, one lotcivil works lot 10: earthworks, structures, restoration of communications and fencing on the conventional line in operation at Casablanca, MAD 1.34bnLe360
SGTMContractor, one lotcivil works lot 8, earthworks and structures in the Bouregreg valley, MAD 2bn (separate from the Rabat tunnel SGTM builds with Sinohydro Bureau 5)H24info
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
November 2023Declaration of public utility publishedMédias24 (interview of Khalid Khairane, ONCF high-speed project director)
June 28, 2024Rabat tunnel awarded to SGTM and Sinohydro Bureau 5 (MAD 1.4bn)Médias24
July 2024Environmental authorisation obtainedMédias24 (interview of Khalid Khairane, ONCF high-speed project director)
October 22, 2024Seventh and last main civil works lot awarded (Mojazine)Challenge.ma
November 20, 2024Civil works lot 3-bis awarded to STAMLa Vie éco
January 2025Colas Rail-SETEC track, catenary and substation contracts (EUR 250m) and GTR lot 3Railway PRO (relaying Colas)
April 24, 2025King Mohammed VI launches the works at Rabat-Agdal stationLe360 (MAP release)
September 24, 2025Works on the Casa-Sud, Stade Hassan II and Mohammed V airport stations launched by the KingLa Vie éco
April 24, 2026ONCF: land acquisition complete, 15 viaducts and three covered trenches under construction, 92 bridges under wayMaroc Hebdo (ONCF communiqué of 24 April 2026)
May 25, 202630% complete (Minister of Transport)La Vie éco
November 11, 2026About 35% complete (Le360)Le360
January 2029 (planned)Start of technical testsLesEco.ma
December 2029 (planned)Start of commercial service (ONCF project director); other sources give November or September 2029Médias24 (interview of Khalid Khairane, ONCF high-speed project director)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A 430 km high-speed line that extends the Tangier-Kenitra LGV south to Rabat, Casablanca and Marrakech, built by ONCF for 350 km/h and operation at 320 km/h. It serves the Rabat-Salé and Mohammed V airports and the Grand Stade Hassan II, with a hub at Nouaceur where a Casablanca branch and a direct bypass meet. Works were launched on 24 April 2025 and were about 35% complete in November 2026, with commercial service planned for late 2029. Civil works are split into lots held by Chinese, French and Moroccan contractors, among them CREC 4, Shandong Hi-Speed, GTR, STAM, TGCC, CRCC 20, Jet Contractors, Mojazine and the SGTM-Sinohydro group for the Rabat tunnel.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources