Agadir Grand Stadium upgrade (World Cup phase 2)
- Location
- Agadir, Souss-Massa, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of September 2026 (LesEco.ma). TGCC's lot 1 was awarded on 1 July 2026 and works had started by 23 July 2026; the roof and facade lot (Inter Tridim) and the electrical lot (Encom-Protelec) were awarded by September 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | SONARGES | |
| Type | Stadiums | |
| Headline amount | MAD 2.419 billion (MAD), as of August 2026 | LesEco.ma |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 1.08 bn | Contract value | lot 1: demolition, structure, waterproofing, finishes (TGCC) | July 2026 | LesEco.ma |
| MAD 996 M | Contract value | roof and facades (Inter Tridim) | September 2026 | Infomédiaire |
| MAD 1.23 bn | Contract value | electrical systems, high and low current (Encom-Protelec) | September 2026 | Infomédiaire |
| MAD 2.42 bn | Budget | three lots launched in August 2026 (roof and facades, fluids, electrical) | August 2026 | LesEco.ma |
| MAD 3.5 bn | Budget | all lots launched so far | August 2026 | LesEco.ma |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| SONARGES | Owner | manages the stadium; co-leads the operation | LesEco.ma |
| ANEP (Agence Nationale des Équipements Publics) | Other role | delegated contracting authority, runs the tenders | LesEco.ma |
| TGCC | Contractor, one lot | lot 1 demolition, structure, waterproofing, finishes; about MAD 1.08bn; 15 months | Infomédiaire |
| Inter Tridim | Contractor, one lot | roof and facades, about MAD 996M (September 2026) | Infomédiaire |
| Encom-Protelec | Contractor, one lot | electrical, lighting, IT and security systems, about MAD 1.23bn | Infomédiaire |
Milestones
| Date | Milestone | Source |
|---|---|---|
| 2013 | Stadium opened | SONARGES |
| July 1, 2026 | Lot 1 awarded to TGCC | LesEco.ma |
| July 23, 2026 | Works under way at the north entrance | LesEco.ma |
| August 3, 2026 | Three further lots launched (MAD 2.419bn) | LesEco.ma |
| September 2026 | Roof and facades to Inter Tridim; electrical to Encom-Protelec | Infomédiaire |
| 2028 (planned) | Phase 2 to end in 2028 (bid book) | SNRT News |
About the project
The second-phase upgrade of Agadir's Adrar stadium for the 2030 World Cup adds a 360-degree roof, removes the athletics track for lower stands, upgrades VIP areas and brings capacity to about 46,000 seats. TGCC holds lot 1 (structure and finishes, about MAD 1.08 billion, 15 months), Inter Tridim the roof and facades (about MAD 996 million) and Encom-Protelec the electrical systems (about MAD 1.23 billion). Works started in July 2026 under SONARGES and ANEP.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Mondial 2030 : TGCC décroche un chantier à plus d'un milliard de DH au Grand Stade d'Agadir, Médias24 (press), 30 Jun 2026. Consulted 20 Nov 2026.
- Mondial 2030 : le Stade Adrar d'Agadir entame sa mue, LesEco.ma (press), 23 Jul 2026. Consulted 20 Nov 2026.
- Stade Adrar d'Agadir : le chantier accélère sa transformation pour 2030, Infomédiaire (press), 23 Sep 2026. Consulted 20 Nov 2026.
- Grand stade d'Agadir : trois nouveaux marchés de 2,4 MMDH pour accélérer les travaux, LesEco.ma (press), 3 Aug 2026. Consulted 20 Nov 2026.
- Grand Stade d'Agadir, SONARGES (owner). Consulted 20 Nov 2026.
- Mondial 2030: le point sur les 6 stades marocains, SNRT News (state news agency (map)), 11 Dec 2024. Consulted 20 Nov 2026.