Research record, fact-checked

Agadir Al Massira airport: terminal extension

Location
Agadir (Agadir-Al Massira airport, Inezgane-Aït Melloul prefecture), Souss-Massa, Morocco. See it on the map, in 3D
Stage
Under construction, as of September 2026 (Le Desk). ONDA awarded the works to SGTM in August 2025. Le Desk reported the works at 16% complete at the end of September 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerONDA (Office National des Aéroports)
TypeAirports
AmountNot found in the sources consulted
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Terminal floor area, after the worksAbout 75,000 m2terminal after worksLa Vie Eco
Refitted area23,800 m2existing terminalLa Vie Eco
Extension areaAbout 51,200 m2new buildingLa Vie Eco
Passengers a year7,000,000 passengers a yearafter works (ONDA)La Vie Eco
Capacity passengers per year afdb5,000,000 passengers a yearAfDB 2030 figureAfrican Development Bank
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 2.23 bnContract valueterminal refit and extension, roads and exterior works (SGTM), incl. taxAugust 2025LesEco.ma
€270 MLoanAfDB PEMIA loan to ONDA, shared by Marrakech, Agadir, Tangier and FezDecember 2025African Development Bank
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONDA (Office National des Aéroports)OwnerLa Vie Eco
SGTMGeneral contractorterminal refit and extension, roads and exterior works; beat TGCC-Inter Tridim (MAD 2.263bn)LesEco.ma
African Development BankLenderPEMIA loan of EUR 270M across four airportsAfrican Development Bank
TGCC-Inter TridimBiddersole other bidder past the technical review, MAD 2.263bn incl. taxes, not retainedLesEco.ma
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
August 19, 2025Contract awarded to SGTM (MAD 2.231bn incl. tax)La Vie Eco
December 12, 2025AfDB board approves EUR 270M PEMIA loanAfrican Development Bank
September 30, 2026Works about 16% complete (Le Desk)Le Desk
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

ONDA is refitting and extending the passenger terminal of Agadir Al Massira airport to about 75,000 m2: 23,800 m2 refitted and 51,200 m2 of new building. SGTM won the contract in August 2025 with a bid of MAD 2.231 billion including tax, which also covers access roads, the car park and landscaping. Capacity is to rise from about 3 to 7 million passengers a year. Works were about 16% complete at the end of September 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.