Research record, fact-checked
Al Wahda open-cycle gas turbine power plant
- Location
- Lamjaara, Ouazzane province, Tanger-Tétouan-Al Hoceïma, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of January 2026 (ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital). ONEE's progress report put the whole project at 54.86% and construction at 18% at the end of January 2026. The first turbine and its generator reached Casablanca port in June 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | ONEE | |
| Type | Energy | |
| Headline amount | MAD 5.6 billion (MAD), as of June 2026 | La Vie éco |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Capacity | 990 MW | project | Mitsubishi Power |
| Units | 2 gas turbines of 495 MW | project | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
| Turbine model | Mitsubishi M701JAC | each unit | Mitsubishi Power |
| Fuel | natural gas and diesel (dual fuel) | project | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
| Substation | 400 kV | on-site substation | MEED |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 5.9 bn | Contract value | EPC contract including five years of O&M | February 2025 | MEED |
| MAD 5.6 bn | Total project cost | project | June 2026 | La Vie éco |
| MAD 4.2 bn | Loan | project financing (Attijariwafa bank, Bank of Africa, Flexenergy and Nord Energy funds) | February 2025 | L'Observateur |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ONEE | Owner | owner and operator; contract SP 98852 P4 | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
| China Energy Engineering Co., Ltd. (CEEC) | General contractor | consortium with Mitsubishi Power | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
| Mitsubishi Power | General contractor | consortium member; supplies the two M701JAC gas turbines and a long-term service agreement | Mitsubishi Power |
| Attijariwafa bank | Lender | MAD 4.2bn financing with Bank of Africa and two funds | L'Observateur |
| Bank of Africa | Lender | MAD 4.2bn financing | L'Observateur |
Milestones
| Date | Milestone | Source |
|---|---|---|
| October 2024 | EPC contract awarded to CEEC and Mitsubishi Power (press) | MEED |
| February 12, 2025 | Mitsubishi Power announces the turbine and service order | Mitsubishi Power |
| January 31, 2026 | 54.86% overall, 18% construction; both turbine foundation rafts poured | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
| June 18, 2026 | First turbine and generator arrive at Casablanca port | La Vie éco |
| 2027 (planned) | Planned commissioning | ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital |
About the project
A 990 MW open-cycle gas power plant with two Mitsubishi Power M701JAC turbines of 495 MW each, built for ONEE near the Al Wahda dam in Ouazzane province. The consortium of China Energy Engineering Corporation and Mitsubishi Power builds it. It burns natural gas from the Maghreb-Europe pipeline, with diesel as backup. ONEE expects it in service in 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Projet de construction de la centrale turbines à gaz en cycle ouvert Al Wahda 2*495MW, rapport d'avancement des travaux, ONEE (Direction Ingénierie et Réalisation Projets Production), published by BMCE Capital (owner), 13 Feb 2026. Consulted 20 Nov 2026.
- Mitsubishi Power wins Morocco gas turbines order, MEED (press), Feb 2025. Consulted 20 Nov 2026.
- Mitsubishi Power Secures Major Gas Turbine and Services Order for Al Wahda Open Cycle Gas Turbine Power Plant in Morocco, Mitsubishi Power (company), 12 Feb 2025. Consulted 20 Nov 2026.
- Centrale à gaz d'Al Wahda : la première des deux turbines est arrivée, La Vie éco (press), 18 Jun 2026. Consulted 20 Nov 2026.
- ONEE. Le financement de la centrale Al Wahda bouclé, L'Observateur (press), 7 Feb 2025. Consulted 20 Nov 2026.