Research record, fact-checked

Casablanca Mohammed V airport: new hub terminal

Location
Nouaceur (Mohammed V International Airport, Casablanca), Casablanca-Settat, Morocco. See it on the map, in 3D
Stage
Under construction, as of March 2026 (RSHP). ONDA awarded the main construction contract to SGTM and TGCC in January 2026. RSHP said in March 2026 that site preparation, started in July 2025, was complete.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerONDA (Office National des Aéroports)
TypeAirports
Headline amountAbout MAD 15 billion (MAD), as of September 2026La Vérité
What it coversTotal project cost, approx.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Floor area600,000 m2terminalFNH (quoting ONDA communiqué)
Passengers a year20,000,000 passengers a yearfirst phaseFNH (quoting ONDA communiqué)
Capacity passengers per year expandable30,000,000 passengers a yearexpansionFNH (quoting ONDA communiqué)
Contact stands45 aircraftterminalFNH (quoting ONDA communiqué)
Levels3 levelsterminalRSHP
Piers2 piersterminalTelQuel (quoting ONDA communiqué)
New runway length3,700 mnew parallel runwayRSHP
New runway width45 mnew parallel runwayRSHP
Control tower height42 mnew control towerH24info (quoting ONDA communiqué)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 12.8 bnContract valueterminal construction contract (SGTM/TGCC)January 2026FNH (quoting ONDA communiqué)
MAD 10 bnBudgetestimate at tender launch (ONDA communiqué)November 2025TelQuel (quoting ONDA communiqué)
MAD 12 bnInvestment programmeproject (as stated by the architect)March 2026RSHP
About MAD 15 bnTotal project costproject (press)September 2026La Vérité
MAD 144 MContract valueengineering and project management mission (re-tendered)September 2026La Vérité
MAD 15 bnTotal project costnew terminal zone (ONDA communiqué, March 2025)March 2025H24info (quoting ONDA communiqué)
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONDA (Office National des Aéroports)OwnerFNH (quoting ONDA communiqué)
SGTMGeneral contractorjoint venture with TGCC, construction contract MAD 12.8bn, awarded January 2026FNH (quoting ONDA communiqué)
TGCCGeneral contractorjoint venture with SGTMFNH (quoting ONDA communiqué)
STAMContractor, one lotgeneral earthworks, 40% done in November 2025TelQuel (quoting ONDA communiqué)
Ala ConceptArchitectdesign group with RSHP and Egis Bâtiment International, competition winnerConsonews
RSHPArchitectdesign group with Ala Concept and EgisRSHP
Egis Bâtiment InternationalEngineermember of the design groupConsonews
Royal Air MarocOther rolemain airline the hub is built forTelQuel (quoting ONDA communiqué)
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
March 20, 2025ONDA announces the hub terminal (MAD 15bn); earthworks tender already launchedH24info (quoting ONDA communiqué)
April 2025Call for expressions of interest for a design-and-build contractorFNH (quoting ONDA communiqué)
July 2025Site preparation (levelling and excavation) startsRSHP
November 4, 2025Tender for the terminal launched, nine sub-lots; earthworks by STAM 40% doneTelQuel (quoting ONDA communiqué)
January 7, 2026Construction contract awarded to SGTM/TGCC, MAD 12.8bnFNH (quoting ONDA communiqué)
March 20, 2026Design by Ala Concept, RSHP and Egis made public; site preparation completeRSHP
June 2029 (planned)Completion of works planned mid-2029FNH (quoting ONDA communiqué)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A new hub terminal at Casablanca Mohammed V airport, built by ONDA for 20 million passengers a year in a first phase, expandable to 30 million. The H-shaped building of about 600,000 m2 has a central processor, two piers and up to 45 contact stands, and will connect to the high-speed rail line. A joint venture of SGTM and TGCC holds the MAD 12.8 billion construction contract awarded in January 2026; completion is planned for mid-2029. The architects are Ala Concept, RSHP and Egis.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.