Casablanca Mohammed V airport: new hub terminal
- Location
- Nouaceur (Mohammed V International Airport, Casablanca), Casablanca-Settat, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of March 2026 (RSHP). ONDA awarded the main construction contract to SGTM and TGCC in January 2026. RSHP said in March 2026 that site preparation, started in July 2025, was complete.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | ONDA (Office National des Aéroports) | |
| Type | Airports | |
| Headline amount | About MAD 15 billion (MAD), as of September 2026 | La Vérité |
| What it covers | Total project cost, approx. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Floor area | 600,000 m2 | terminal | FNH (quoting ONDA communiqué) |
| Passengers a year | 20,000,000 passengers a year | first phase | FNH (quoting ONDA communiqué) |
| Capacity passengers per year expandable | 30,000,000 passengers a year | expansion | FNH (quoting ONDA communiqué) |
| Contact stands | 45 aircraft | terminal | FNH (quoting ONDA communiqué) |
| Levels | 3 levels | terminal | RSHP |
| Piers | 2 piers | terminal | TelQuel (quoting ONDA communiqué) |
| New runway length | 3,700 m | new parallel runway | RSHP |
| New runway width | 45 m | new parallel runway | RSHP |
| Control tower height | 42 m | new control tower | H24info (quoting ONDA communiqué) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 12.8 bn | Contract value | terminal construction contract (SGTM/TGCC) | January 2026 | FNH (quoting ONDA communiqué) |
| MAD 10 bn | Budget | estimate at tender launch (ONDA communiqué) | November 2025 | TelQuel (quoting ONDA communiqué) |
| MAD 12 bn | Investment programme | project (as stated by the architect) | March 2026 | RSHP |
| About MAD 15 bn | Total project cost | project (press) | September 2026 | La Vérité |
| MAD 144 M | Contract value | engineering and project management mission (re-tendered) | September 2026 | La Vérité |
| MAD 15 bn | Total project cost | new terminal zone (ONDA communiqué, March 2025) | March 2025 | H24info (quoting ONDA communiqué) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ONDA (Office National des Aéroports) | Owner | FNH (quoting ONDA communiqué) | |
| SGTM | General contractor | joint venture with TGCC, construction contract MAD 12.8bn, awarded January 2026 | FNH (quoting ONDA communiqué) |
| TGCC | General contractor | joint venture with SGTM | FNH (quoting ONDA communiqué) |
| STAM | Contractor, one lot | general earthworks, 40% done in November 2025 | TelQuel (quoting ONDA communiqué) |
| Ala Concept | Architect | design group with RSHP and Egis Bâtiment International, competition winner | Consonews |
| RSHP | Architect | design group with Ala Concept and Egis | RSHP |
| Egis Bâtiment International | Engineer | member of the design group | Consonews |
| Royal Air Maroc | Other role | main airline the hub is built for | TelQuel (quoting ONDA communiqué) |
Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 20, 2025 | ONDA announces the hub terminal (MAD 15bn); earthworks tender already launched | H24info (quoting ONDA communiqué) |
| April 2025 | Call for expressions of interest for a design-and-build contractor | FNH (quoting ONDA communiqué) |
| July 2025 | Site preparation (levelling and excavation) starts | RSHP |
| November 4, 2025 | Tender for the terminal launched, nine sub-lots; earthworks by STAM 40% done | TelQuel (quoting ONDA communiqué) |
| January 7, 2026 | Construction contract awarded to SGTM/TGCC, MAD 12.8bn | FNH (quoting ONDA communiqué) |
| March 20, 2026 | Design by Ala Concept, RSHP and Egis made public; site preparation complete | RSHP |
| June 2029 (planned) | Completion of works planned mid-2029 | FNH (quoting ONDA communiqué) |
About the project
A new hub terminal at Casablanca Mohammed V airport, built by ONDA for 20 million passengers a year in a first phase, expandable to 30 million. The H-shaped building of about 600,000 m2 has a central processor, two piers and up to 45 contact stands, and will connect to the high-speed rail line. A joint venture of SGTM and TGCC holds the MAD 12.8 billion construction contract awarded in January 2026; completion is planned for mid-2029. The architects are Ala Concept, RSHP and Egis.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Nouveau terminal de l'aéroport Mohammed V : le duo SGTM-TGCC décroche le marché à 12,8 milliards de DH, FNH (quoting ONDA communiqué) (press), 7 Jan 2026. Consulted 20 Nov 2026.
- Aéroport Mohammed V: le tandem SGTM-TGCC décroche le contrat du nouveau terminal à 12,8 milliards de DH, Le360 (press), 7 Jan 2026. Consulted 20 Nov 2026.
- L'ONDA lance l'appel d'offres pour le nouveau terminal de l'aéroport Casablanca Mohammed V, TelQuel (quoting ONDA communiqué) (press), 4 Nov 2025. Consulted 20 Nov 2026.
- Casablanca Mohammed V : l'ONDA lance un appel d'offres pour la construction de son futur terminal HUB, Consonews (press), 5 Nov 2025. Consulted 20 Nov 2026.
- RSHP and ALA Concept to design new terminal at Mohammed V Airport in Casablanca, RSHP (company), Mar 2026. Consulted 20 Nov 2026.
- Nouveau terminal Mohammed V : l'ONDA relance la mission de pilotage du chantier, La Vérité (press), 23 Sep 2026. Consulted 20 Nov 2026.
- Images | Architects reveal designs for $1.3bn Casablanca airport terminal, Construction Briefing (KHL) (press), 20 Mar 2026. Consulted 20 Nov 2026.
- Aéroport Mohammed V: 15 MMDH pour un nouveau terminal unique en son genre (images), H24info (quoting ONDA communiqué) (press), 20 Mar 2025. Consulted 20 Nov 2026.
- Nouaceur : la gare LGV reliée au nouveau terminal de l'aéroport Mohammed V, LeBrief (press), 5 Jun 2025. Consulted 20 Nov 2026.