Research record, fact-checked

Casablanca seawater desalination plant

Location
Lamharza Essahel, El Jadida province (south of Casablanca, near Sidi Rahal Chatai), Casablanca-Settat, Morocco. See it on the map, in 3D
Stage
Under construction, as of July 2026 (Le360). Works were launched in June 2024. ONEE connected the plant to the grid on 19 July 2026, and the minister said in July 2026 that it would be operational in February 2027.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnersONEE (Office National de l'Electricité et de l'Eau Potable), Al Baidaa Desalination Company, Green of Africa, Afriquia Gaz
TypeWater
Headline amountEUR 613 million (EUR), as of May 2025Smart Water Magazine
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Capacity, first phase548,000 m3/dayphase 1Yabiladi (reporting the official launch, MAP)
Capacity phase2 total822,000 m3/dayphase 2 (total)Yabiladi (reporting the official launch, MAP)
Annual capacity total300 million m3 a yearprojectYabiladi (reporting the official launch, MAP)
Annual capacity irrigation50 million m3 a yearphase 2Smart Water Magazine
Site area50 haprojectYabiladi (reporting the official launch, MAP)
Intake pipes2 pipes of 1,850 mprojectYabiladi (reporting the official launch, MAP)
Outfall length2,500 mprojectYabiladi (reporting the official launch, MAP)
Distribution network lengthNearly 130 kmprojectYabiladi (reporting the official launch, MAP)
Pumping stations3projectYabiladi (reporting the official launch, MAP)
Storage tanks3projectYabiladi (reporting the official launch, MAP)
Population served7.5 million inhabitantsprojectYabiladi (reporting the official launch, MAP)
Water tariff4.48 MAD/m3projectYabiladi (reporting the official launch, MAP)
Dedicated wind power360 MW (Bir Anzarane wind farm, 47% of output dedicated)projectSmart Water Magazine
Grid connection400 kVprojectLe360
Capacity, first phase559,000 m3/dayphase 1Acciona
Capacity phase2 addition279,500 m3/dayphase 2 (addition)Acciona
Capacity total838,000 m3/dayprojectAcciona
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 6.5 bnTotal project costprojectJune 2024Yabiladi (reporting the official launch, MAP)
€613 MTotal project costprojectMay 2025Smart Water Magazine
MAD 486 MContract valueONEE grid connection (400 kV substation and line)July 2026Le360
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONEE (Office National de l'Electricité et de l'Eau Potable)OwnerPublic partner and offtaker; built the 400 kV grid connectionLe360
Al Baidaa Desalination CompanyConcessionaireProject company: Acciona 50%, Green of Africa 45%, Afriquia Gaz 5%Smart Water Magazine
Acciona (Acciona Agua)General contractorConstruction, operation and maintenance for 27 years; 50% shareholderSmart Water Magazine
Green of AfricaConcessionaire45% shareholderSmart Water Magazine
Afriquia GazConcessionaire5% shareholderSmart Water Magazine
FIEM / ICO, Société Générale, Attijariwafa Bank, Banque Centrale Populaire, Bank of Africa, Caixa, COFIDESLenderFinancing 80% debt, 20% equitySmart Water Magazine
CAPEPContractor, one lotONEE lots 1 and 2, treated-water transfer (adduction) from the plant, nearly MAD 744MChallenge
STAMBidderbid for the first three ONEE adduction lots, not retainedChallenge
SNCEBidderSociété nouvelle des conduites d'eau, bid for the first three ONEE adduction lots, not retainedChallenge
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
June 10, 2024Crown Prince Moulay El Hassan launches construction at Lamharza EssahelYabiladi (reporting the official launch, MAP)
May 2025Financing signed (80% debt, 20% equity)Smart Water Magazine
July 19, 2026ONEE commissions the 400 kV grid connectionLe360
February 2027 (planned)Operational (phase 1), per the ministerLe360
June 2028 (planned)Phase 2 (822,000 m3/day), mid-2028Yabiladi (reporting the official launch, MAP)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A seawater reverse osmosis plant on the Atlantic coast at Lamharza Essahel, south of Casablanca, built in two phases on a 50 ha site. It is developed under a public-private partnership by Al Baidaa Desalination Company (Acciona, Green of Africa, Afriquia Gaz) for ONEE, with Acciona building and operating it. Phase 1 is 548,000 m3 a day; phase 2 takes it to 822,000 m3 a day (300 million m3 a year). Works started in June 2024 and the minister expects it to be operational in February 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.