Chtouka-Aït Baha (Agadir) desalination plant extension
- Location
- Chtouka-Aït Baha province, south of Agadir, Souss-Massa, Morocco. See it on the map, in 3D
- Stage
- Contract awarded, works not confirmed, as of July 2025 (La Vie éco). In July 2025 the Spanish company Cox formalised an agreement with the Ministry of Agriculture to enlarge the plant to 400,000 m³ a day. No start of works was found.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Ministry of Agriculture, ONEE, Cox | |
| Type | Water | |
| Headline amount | MAD 4.41 billion (MAD), as of August 2024 | L'Economiste |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Capacity | 400,000 m3/day | after extension | La Vie éco |
| Capacity before | 275,000 m3/day | existing plant | La Vie éco |
| Capacity drinking | 150,000 m3/day | after extension | La Vie éco |
| Capacity irrigation | 250,000 m3/day | after extension | La Vie éco |
| Irrigated area | 13,600 ha | after extension | La Vie éco |
| Irrigated area | 15,000 ha | existing plant, Chtouka plain | L'Economiste |
| Wind farm capacity | 150 MW | associated wind farm | La Vie éco |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| €250 M | Announced investment | extension and wind farm | July 2025 | La Vie éco |
| MAD 4.41 bn | Total project cost | existing plant (2.35bn irrigation, 2.06bn drinking water) | August 2024 | L'Economiste |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Agriculture | Owner | signed the extension agreement with Cox (irrigation component) | La Vie éco |
| ONEE | Owner | in charge of the capacity increase for drinking water (2024) | L'Economiste |
| Cox | Concessionaire | Spanish company, extension agreement July 2025 | La Vie éco |
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 29, 2025 | Cox formalises the extension agreement with the Ministry of Agriculture | La Vie éco |
| 2027 (planned) | Extension expected to operate in 2026-2027, wind farm in 2027 | La Vie éco |
About the project
The enlargement of the seawater desalination plant in Chtouka-Aït Baha, south of Agadir, from 275,000 to 400,000 m³ a day: 150,000 m³ for drinking water and 250,000 m³ for irrigation. The Spanish company Cox signed the agreement with the Ministry of Agriculture in July 2025, for a planned EUR 250 million with a wind farm of more than 150 MW. The extension was expected to operate in 2026 or 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Agadir: L'extension de la station de dessalement actée, La Vie éco (press), 29 Jul 2025. Consulted 23 Nov 2026.
- Chtouka-Aït Baha : La capacité de la station de dessalement portée à 400.000 m3/j à l'horizon 2026, L'Economiste (press), 31 Aug 2024. Consulted 23 Nov 2026.