Research record, fact-checked
Dakhla Atlantique port
- Location
- N'Tireft (N'Tirift), north of Dakhla, Oued Eddahab province, Dakhla-Oued Eddahab, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of September 30, 2026 (Finances News Hebdo). SGTM reported progress above 74% at the end of September 2026; Le360 reported 76% in mid-November 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water (Direction des Ports et du Domaine Public Maritime) | |
| Type | Ports | |
| Headline amount | MAD 12.6 billion (MAD), as of June 20, 2026 | Le360 |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Protection works length | 7.5 km | project | Finances News Hebdo |
| Quays, total length | 2,300 m | project | Finances News Hebdo |
| Access bridge | 1,330 m | maritime access bridge | Finances News Hebdo |
| Industrial logistics zone | 1,650 ha | industrial and logistics zones | Le360 |
| Land reclaimed | 80 ha | fill completed by mid-November 2026 | Le360 |
| Capacity | 35 Mt/year | target, extensible | LesEco.ma |
| Max depth | 18 m | quays | Bourse News |
| Basins | 3 basins | commercial, deep-sea fishing, ship repair | Bourse News |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 12.6 bn | Total project cost | project | June 20, 2026 | Le360 |
| MAD 12.4 bn | Contract value | works entrusted to the SGTM–Somagec Sud grouping (search summary of Médias24 / ministry, not read verbatim) | June 2026 | Ministère de l'Equipement et de l'Eau |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water (Direction des Ports et du Domaine Public Maritime) | Owner | project management director Nisrine Iouzzi quoted in the press | Le360 |
| SGTM | General contractor | member of the works grouping; reports progress in its financial communication | Finances News Hebdo |
| SGTM-Somagec Sud | General contractor | works grouping for the construction of the new port, contract of MAD 12,401,195,656.8 accepted by the Directorate of Ports in August 2021; the Somagec member is named Somagec Sud in the admission minutes quoted by LesEco (c1: 'seul le groupement SGTM-Somagec-Sud a été retenu comme concurrent admissible sans réserves'). Adds Somagec Sud | Afrimag |
Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.
Milestones
| Date | Milestone | Source |
|---|---|---|
| October 2025 | About 45% overall (87% of the bridge, about 25% of the port works) | LesEco.ma |
| June 20, 2026 | 62% overall, maritime bridge 85% | Le360 |
| July 31, 2026 | 65% at the end of July 2026 | Bourse News |
| September 30, 2026 | Above 74% (SGTM) | Finances News Hebdo |
| November 15, 2026 | 76% (Le360) | Le360 |
| December 2028 (planned) | End of works planned for late 2028, operations in 2029 | LesEco.ma |
About the project
Dakhla Atlantique is a deepwater port being built on an artificial island in the Atlantic north of Dakhla, linked to the shore by a 1,330 m maritime bridge. The works comprise 7.5 km of protection works and more than 2,300 m of quays, with a commercial basin and a fishing basin. The Ministry of Equipment and Water is the owner and the works are carried out by a grouping that includes SGTM. Progress passed 74% at the end of September 2026; the works are due to end in late 2028, with operations in 2029.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Port Dakhla Atlantique : les travaux dépassent 74% d'avancement, Finances News Hebdo (press), 20 Oct 2026. Consulted 20 Nov 2026.
- Port de Dakhla Atlantique : le chantier franchit un cap décisif avec la mise en place des quais, Le360 (press), 20 Jun 2026. Consulted 20 Nov 2026.
- Dakhla Atlantique : le futur port, pivot de la prospérité des provinces du Sud, Le360 (press), 15 Nov 2026. Consulted 20 Nov 2026.
- Dakhla Atlantique : un port appelé à transformer la façade atlantique, LesEco.ma (press), Oct 2025. Consulted 20 Nov 2026.
- Nouveau Port de Dakhla Atlantique (project page), Ministère de l'Equipement et de l'Eau (owner). Consulted 20 Nov 2026.
- Port Dakhla Atlantique : le taux d'avancement atteint 65%, Bourse News (press), 6 Oct 2026. Consulted 20 Nov 2026.
- Maroc/Port de Dakhla Atlantique : le consortium marocain SGTM-SOMAGEC remporte le marché pour 12,4 milliards de dirhams, Afrimag (press), 9 Aug 2021. Consulted 23 Nov 2026.