Fès-Taounate expressway (RN8 dualling)

Location
Fès to Taounate, Fès-Meknès, Morocco. See it on the map, in 3D
Stage
Under construction, as of September 2026 (Fès News Media). In September 2026 the first section was complete, the second was over 90% complete, the third about 25%, and the fourth had been awarded.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Equipment and Water (provincial directorate of Taounate)
TypeHighways
Headline amountAbout MAD 1.56 billion (MAD), as of July 2026Fès News Media
What it coversTotal project cost, approx.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length73 kmprojectFès News Media
Length16 kmsection 1Challenge
Length19 kmsection 2 (Ouled Daoud to Bouarous road)Fès News Media
Length19 kmsection 3 (Bouarous road to Aïn Kansra)Fès News Media
Length17 kmsection 4 (Aïn Kansra to Fès)Fès News Media
Structures11projectFès News Media
TrafficAbout 7,500 vehicles/dayexisting roadChallenge
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
About MAD 1.56 bnTotal project costprojectJuly 2026Fès News Media
MAD 238 MContract valuesection 1 (PK805 to PK789)November 2023Challenge
MAD 285 MContract valuesection 2 (PK788 to PK769)November 2023Challenge
About MAD 260 MBudgetsection 1September 2026Fès News Media
MAD 303 MBudgetsection 2September 2026Fès News Media
MAD 324 MBudgetsection 3September 2026Fès News Media
MAD 137 MContract valuesection 4 (Aïn Kansra to Fès entrance)September 2026Fès News Media
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and Water (provincial directorate of Taounate)Ownercontracting authority for sections 1 and 2Challenge
SSMT-TaroudantContractor, one lotsection 1, PK805 to PK789, MAD 238M (2023)Challenge
Univers BatContractor, one lotsection 2, PK788 to PK769, MAD 285M, 18 months (2023)Challenge
Les Grands Chantiers RoutiersContractor, one lotsection 4, from the Fès city entrance, MAD 137.273M (2026)Fès News Media
Fès-Meknès Regional CouncilOther roleits vice-president announced the start of section 4Fès News Media
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
November 2023Sections 1 and 2 awarded to SSMT-Taroudant and Univers BatChallenge
July 9, 2026Section 1 nearly 100% complete, section 2 at 85%Fès News Media
September 2026Section 2 over 90%, section 3 about 25%, structures over 45%; section 4 awarded and starting at the Fès entranceFès News Media
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The dualling of the RN8 national road over 73 km between Fès and Taounate, for the Ministry of Equipment and Water, in four sections. The section from Ouled Daoud to Taounate is complete. In September 2026 the second section was over 90% complete, the third about 25%, and the fourth, from Aïn Kansra to the entrance of Fès, had been awarded to Les Grands Chantiers Routiers.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.