Fès-Taounate expressway (RN8 dualling)
- Location
- Fès to Taounate, Fès-Meknès, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of September 2026 (Fès News Media). In September 2026 the first section was complete, the second was over 90% complete, the third about 25%, and the fourth had been awarded.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water (provincial directorate of Taounate) | |
| Type | Highways | |
| Headline amount | About MAD 1.56 billion (MAD), as of July 2026 | Fès News Media |
| What it covers | Total project cost, approx. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 73 km | project | Fès News Media |
| Length | 16 km | section 1 | Challenge |
| Length | 19 km | section 2 (Ouled Daoud to Bouarous road) | Fès News Media |
| Length | 19 km | section 3 (Bouarous road to Aïn Kansra) | Fès News Media |
| Length | 17 km | section 4 (Aïn Kansra to Fès) | Fès News Media |
| Structures | 11 | project | Fès News Media |
| Traffic | About 7,500 vehicles/day | existing road | Challenge |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| About MAD 1.56 bn | Total project cost | project | July 2026 | Fès News Media |
| MAD 238 M | Contract value | section 1 (PK805 to PK789) | November 2023 | Challenge |
| MAD 285 M | Contract value | section 2 (PK788 to PK769) | November 2023 | Challenge |
| About MAD 260 M | Budget | section 1 | September 2026 | Fès News Media |
| MAD 303 M | Budget | section 2 | September 2026 | Fès News Media |
| MAD 324 M | Budget | section 3 | September 2026 | Fès News Media |
| MAD 137 M | Contract value | section 4 (Aïn Kansra to Fès entrance) | September 2026 | Fès News Media |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water (provincial directorate of Taounate) | Owner | contracting authority for sections 1 and 2 | Challenge |
| SSMT-Taroudant | Contractor, one lot | section 1, PK805 to PK789, MAD 238M (2023) | Challenge |
| Univers Bat | Contractor, one lot | section 2, PK788 to PK769, MAD 285M, 18 months (2023) | Challenge |
| Les Grands Chantiers Routiers | Contractor, one lot | section 4, from the Fès city entrance, MAD 137.273M (2026) | Fès News Media |
| Fès-Meknès Regional Council | Other role | its vice-president announced the start of section 4 | Fès News Media |
Milestones
| Date | Milestone | Source |
|---|---|---|
| November 2023 | Sections 1 and 2 awarded to SSMT-Taroudant and Univers Bat | Challenge |
| July 9, 2026 | Section 1 nearly 100% complete, section 2 at 85% | Fès News Media |
| September 2026 | Section 2 over 90%, section 3 about 25%, structures over 45%; section 4 awarded and starting at the Fès entrance | Fès News Media |
About the project
The dualling of the RN8 national road over 73 km between Fès and Taounate, for the Ministry of Equipment and Water, in four sections. The section from Ouled Daoud to Taounate is complete. In September 2026 the second section was over 90% complete, the third about 25%, and the fourth, from Aïn Kansra to the entrance of Fès, had been awarded to Les Grands Chantiers Routiers.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Taounate : Le projet de dédoublement de la Route Nationale n°8 entre dans sa phase décisive… un tronçon achevé et un second presque terminé, Fès News Media (press), 15 Jul 2026. Consulted 23 Nov 2026.
- Fes-Taounate.. Work begins on the fourth section of the National Road No. 8 duplication project, Fès News Media (press), 17 Sep 2026. Consulted 23 Nov 2026.
- Dédoublement de la voie express Fès-Taounate. Le marocain Univers Bat, attributaire de la 2ème tranche, Challenge (press), 19 Nov 2023. Consulted 23 Nov 2026.