Research record, fact-checked

Gotion battery gigafactory, Kenitra

Location
Kenitra Atlantic Free Zone, Rabat-Salé-Kénitra, Morocco. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of October 2026 (WINS Solutions). Gotion Power Morocco began commissioning and starting up its production equipment in the week of 20 October 2026, after building the cell plant in 13 months from September 2025.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnersGotion Power Morocco, CDG Invest
TypeIndustry
Headline amountUS$1.3 billion (US dollars), as of October 2026WINS Solutions
What it coversAnnounced investment. Not to be read as a construction cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Capacity20 GWh/yearphase 1: cells, packs and storage systems (company, press)WINS Solutions
Capacity10 GWhphase 1 cells and packs for EVs (AfDB)African Development Bank (via Zawya)
Cathode materials100,000 t/yearphase 1WINS Solutions
Capacity target100 GWhfull build-outAfrican Development Bank (via Zawya)
Direct jobs600 jobsphase 1 (AfDB)African Development Bank (via Zawya)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
US$1.3 bnAnnounced investmentphase 1October 2026WINS Solutions
€100 MLoanAfDB loan, with up to EUR 141m more to be mobilised from partnersJuly 2026African Development Bank (via Zawya)
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Gotion Power MoroccoOwnersubsidiary of Gotion High-Tech (Hefei)African Development Bank (via Zawya)
African Development BankLenderEUR 100mAfrican Development Bank (via Zawya)
CDG InvestOwnerequity stake in Gotion Power Morocco through its NAMA fund, MAD 3.16bnLe360
ACWA PowerSupplier500 MW wind plant with 2,000 MWh storage to power the gigafactory, USD 800 millionBatteries International
PowerCoOther role49% of a joint venture with Gotion (51%) producing LFP cathode materials at KenitraLe360
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
September 2025Construction starts after earthworksWINS Solutions
July 2026AfDB approves EUR 100m loanAfrican Development Bank (via Zawya)
October 20, 2026Commissioning and start-up of production equipmentWINS Solutions
November 2026 (planned)Second production lineWINS Solutions
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A lithium iron phosphate battery factory of Gotion High-Tech in the Kenitra Atlantic Free Zone, making cathode materials, cells, battery packs and storage systems. Construction started in September 2025 and production equipment started up in October 2026. The first phase drew about USD 1.3 billion of investment; the African Development Bank lent EUR 100 million.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.