Guercif-Nador motorway
- Location
- Guercif, Saka, Driouch, Nador West Med, Oriental, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of April 4, 2026 (Le360). ADM's representative said in April 2026 that section 3 (27 km) was more than 80% complete and that section 2 had been under construction since January 2026. Section 1 was awarded to CRBC on 27 July 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Ministry of Equipment and Water (Direction régionale de l'Oriental), ADM (Société Nationale des Autoroutes du Maroc) | |
| Type | Highways | |
| Headline amount | MAD 7.9 billion (MAD), as of July 29, 2026 | Barlamane |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 104 km | project | Barlamane |
| Lanes | 4 lanes (2x2) | project | African Development Bank |
| Length | 36.475 km | section 1 Guercif-Saka | Bladi.net (relaying the AfDB award notice) |
| Length | 40.5 km | section 2 Saka-Driouch | Le360 (press review of L'Economiste) |
| Length | 27 km | section 3 Driouch-Nador West Med | Le360 |
| Land take | 1,099 ha | project (618 Guercif + 89 Driouch + 392 Nador) | African Development Bank |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 7.9 bn | Total project cost | project | July 29, 2026 | Barlamane |
| MAD 7.65 bn | Total project cost | project, excluding taxes, with contingencies (AfDB appraisal, 2023) | November 2023 | African Development Bank |
| €229 M | Loan | AfDB financing of the Guercif-Nador motorway as stated in November 2026 | November 20, 2026 | African Development Bank |
| €200 M | Loan | AfDB loan (section 1) | November 2023 | African Development Bank |
| €46 M | Loan | Africa Growing Together Fund (AGTF) loan (USD 50 million) | November 2023 | African Development Bank |
| €200 M | Loan | IsDB (section 2), as planned in the AfDB appraisal | November 2023 | African Development Bank |
| €248 M | Budget | Moroccan government counterpart | November 2023 | African Development Bank |
| MAD 632 M | Contract value | section 1, lot 1 (first 10.6 km) | July 27, 2026 | Bladi.net (relaying the AfDB award notice) |
| MAD 564 M | Contract value | section 1, lot 2 (13.8 km) | July 27, 2026 | Bladi.net (relaying the AfDB award notice) |
| MAD 625 M | Contract value | section 1, lot 3 (just over 12 km) | July 27, 2026 | Bladi.net (relaying the AfDB award notice) |
| MAD 587 M | Contract value | section 2, one lot (Mojazine) | November 14, 2025 | Barlamane |
| MAD 1.1 bn | Contract value | section 2, two lots (Bioui Travaux) | November 14, 2025 | Barlamane |
| Nearly MAD 2 bn | Budget | section 3, Driouch-Nador West Med | April 4, 2026 | Le360 |
| MAD 5.5 bn | Budget | project, initial ADM estimate (2021) | 2021 | Bladi.net |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water (Direction régionale de l'Oriental) | Owner | owner of section 1 (and of the project) | Barlamane |
| ADM (Société Nationale des Autoroutes du Maroc) | Owner | delegated owner; leads section 3 | Le360 |
| China Road and Bridge Corporation (CRBC) | Contractor, one lot | section 1, all three lots, MAD 1.821bn excl. taxes, 30 months each | Bladi.net (relaying the AfDB award notice) |
| Bioui Travaux | Contractor, one lot | section 2, two lots, more than MAD 1.1bn | Barlamane |
| Mojazine | Contractor, one lot | section 2, one lot, MAD 586.78M | Barlamane |
| African Development Bank (AfDB) | Lender | EUR 200m for section 1 | African Development Bank |
| Africa Growing Together Fund (AGTF) | Lender | EUR 46m (USD 50m), managed by the AfDB | African Development Bank |
| Islamic Development Bank (IsDB) | Lender | finances section 2 (EUR 200m planned; EUR 187.84m reported) | Bladi.net |
Milestones
| Date | Milestone | Source |
|---|---|---|
| November 24, 2023 | AfDB board presentation planned for the EUR 246m financing (approved December 2023 per press) | African Development Bank |
| November 14, 2025 | Section 2 (Saka-Driouch) awarded to Bioui Travaux and Mojazine | Barlamane |
| January 2026 | Section 2 enters construction | Le360 |
| April 4, 2026 | Section 3 more than 80% complete | Le360 |
| May 3, 2026 | AfDB announces the start of works on section 1 | Le360 (press review of L'Economiste) |
| July 27, 2026 | AfDB award notice: section 1, three lots, to CRBC | Bladi.net (relaying the AfDB award notice) |
| January 17, 2028 (planned) | Latest delivery date for section 1 | Bladi.net (relaying the AfDB award notice) |
| June 2029 (planned) | Completion of the whole motorway (governor of Driouch, August 2026) | Bladi.net |
About the project
A 104 km motorway in the Oriental region that will connect the Nador West Med port to the Fès-Oujda motorway near Guercif, via Saka and Driouch. It is built in three sections: Driouch to the port, led by ADM, was more than 80% complete in April 2026; Saka to Driouch, financed by the Islamic Development Bank and built by Bioui Travaux and Mojazine, started in January 2026; Guercif to Saka, financed by the African Development Bank, was awarded to China Road and Bridge Corporation in July 2026. The total cost is put at about MAD 7.9 billion and full completion is now expected in June 2029.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Autoroute Nador-Guercif: le troisième tronçon réalisé à plus de 80%, Le360 (press), 4 Apr 2026. Consulted 20 Nov 2026.
- Le chinois CRBC décroche un contrat de 170 millions de dollars pour le premier tronçon de l'autoroute Guercif-Nador, Barlamane (press), 29 Jul 2026. Consulted 20 Nov 2026.
- Maroc - Projet autoroutier Guercif-Nador - Rapport d'évaluation de projet, African Development Bank (lender), 2023. Consulted 20 Nov 2026.
- Maroc : la Chine prend toute l'autoroute vers Nador West Med, Bladi.net (relaying the AfDB award notice) (press), 29 Jul 2026. Consulted 20 Nov 2026.
- Nador West Med ouvre fin 2026, mais son autoroute jusqu'à Guercif ne sera terminée qu'en 2029, Bladi.net (press), 19 Aug 2026. Consulted 20 Nov 2026.
- Autoroute Guercif-Nador: la BAD lance les travaux du tronçon n°1, Le360 (press review of L'Economiste) (press), 3 May 2026. Consulted 20 Nov 2026.
- Attribution de marchés - Maroc - Travaux de construction de l'autoroute Guercif-Nador, section 1 Guercif-Saka, African Development Bank (lender), 27 Jul 2026. Consulted 20 Nov 2026.
- Autoroutes au Maroc : les prochains grands chantiers se précisent, Bladi.net (press), 10 May 2026. Consulted 20 Nov 2026.
- Maroc : plus de 2 milliards d'euros pour bâtir le réseau de transport de demain, African Development Bank (lender), 20 Nov 2026. Consulted 20 Nov 2026.