Guercif-Nador motorway

Location
Guercif, Saka, Driouch, Nador West Med, Oriental, Morocco. See it on the map, in 3D
Stage
Under construction, as of April 4, 2026 (Le360). ADM's representative said in April 2026 that section 3 (27 km) was more than 80% complete and that section 2 had been under construction since January 2026. Section 1 was awarded to CRBC on 27 July 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnersMinistry of Equipment and Water (Direction régionale de l'Oriental), ADM (Société Nationale des Autoroutes du Maroc)
TypeHighways
Headline amountMAD 7.9 billion (MAD), as of July 29, 2026Barlamane
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length104 kmprojectBarlamane
Lanes4 lanes (2x2)projectAfrican Development Bank
Length36.475 kmsection 1 Guercif-SakaBladi.net (relaying the AfDB award notice)
Length40.5 kmsection 2 Saka-DriouchLe360 (press review of L'Economiste)
Length27 kmsection 3 Driouch-Nador West MedLe360
Land take1,099 haproject (618 Guercif + 89 Driouch + 392 Nador)African Development Bank
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 7.9 bnTotal project costprojectJuly 29, 2026Barlamane
MAD 7.65 bnTotal project costproject, excluding taxes, with contingencies (AfDB appraisal, 2023)November 2023African Development Bank
€229 MLoanAfDB financing of the Guercif-Nador motorway as stated in November 2026November 20, 2026African Development Bank
€200 MLoanAfDB loan (section 1)November 2023African Development Bank
€46 MLoanAfrica Growing Together Fund (AGTF) loan (USD 50 million)November 2023African Development Bank
€200 MLoanIsDB (section 2), as planned in the AfDB appraisalNovember 2023African Development Bank
€248 MBudgetMoroccan government counterpartNovember 2023African Development Bank
MAD 632 MContract valuesection 1, lot 1 (first 10.6 km)July 27, 2026Bladi.net (relaying the AfDB award notice)
MAD 564 MContract valuesection 1, lot 2 (13.8 km)July 27, 2026Bladi.net (relaying the AfDB award notice)
MAD 625 MContract valuesection 1, lot 3 (just over 12 km)July 27, 2026Bladi.net (relaying the AfDB award notice)
MAD 587 MContract valuesection 2, one lot (Mojazine)November 14, 2025Barlamane
MAD 1.1 bnContract valuesection 2, two lots (Bioui Travaux)November 14, 2025Barlamane
Nearly MAD 2 bnBudgetsection 3, Driouch-Nador West MedApril 4, 2026Le360
MAD 5.5 bnBudgetproject, initial ADM estimate (2021)2021Bladi.net
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and Water (Direction régionale de l'Oriental)Ownerowner of section 1 (and of the project)Barlamane
ADM (Société Nationale des Autoroutes du Maroc)Ownerdelegated owner; leads section 3Le360
China Road and Bridge Corporation (CRBC)Contractor, one lotsection 1, all three lots, MAD 1.821bn excl. taxes, 30 months eachBladi.net (relaying the AfDB award notice)
Bioui TravauxContractor, one lotsection 2, two lots, more than MAD 1.1bnBarlamane
MojazineContractor, one lotsection 2, one lot, MAD 586.78MBarlamane
African Development Bank (AfDB)LenderEUR 200m for section 1African Development Bank
Africa Growing Together Fund (AGTF)LenderEUR 46m (USD 50m), managed by the AfDBAfrican Development Bank
Islamic Development Bank (IsDB)Lenderfinances section 2 (EUR 200m planned; EUR 187.84m reported)Bladi.net
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
November 24, 2023AfDB board presentation planned for the EUR 246m financing (approved December 2023 per press)African Development Bank
November 14, 2025Section 2 (Saka-Driouch) awarded to Bioui Travaux and MojazineBarlamane
January 2026Section 2 enters constructionLe360
April 4, 2026Section 3 more than 80% completeLe360
May 3, 2026AfDB announces the start of works on section 1Le360 (press review of L'Economiste)
July 27, 2026AfDB award notice: section 1, three lots, to CRBCBladi.net (relaying the AfDB award notice)
January 17, 2028 (planned)Latest delivery date for section 1Bladi.net (relaying the AfDB award notice)
June 2029 (planned)Completion of the whole motorway (governor of Driouch, August 2026)Bladi.net
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A 104 km motorway in the Oriental region that will connect the Nador West Med port to the Fès-Oujda motorway near Guercif, via Saka and Driouch. It is built in three sections: Driouch to the port, led by ADM, was more than 80% complete in April 2026; Saka to Driouch, financed by the Islamic Development Bank and built by Bioui Travaux and Mojazine, started in January 2026; Guercif to Saka, financed by the African Development Bank, was awarded to China Road and Bridge Corporation in July 2026. The total cost is put at about MAD 7.9 billion and full completion is now expected in June 2029.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources