Oued Sakia El Hamra viaduct, Laayoune bypass

Location
Laâyoune, Laâyoune-Sakia El Hamra, Morocco. See it on the map, in 3D
Stage
Under construction, as of November 2026 (TelQuel (MAP dispatch)). The director of the Tiznit-Dakhla expressway told MAP in early November 2026 that the works were 57% complete, with about 900 people on site in three shifts.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Equipment and Water
TypeHighways
Headline amountMAD 9 billion (MAD), as of November 2026TelQuel (MAP dispatch)
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length1,648 mprojectTelQuel (MAP dispatch)
Deck width21.4 mprojectTelQuel (MAP dispatch)
Piers14 piersprojectTelQuel (MAP dispatch)
Max pier height46.5 mprojectTelQuel (MAP dispatch)
Foundation depth24 to 46 mprojectTelQuel (MAP dispatch)
Concrete volumeAbout 70,000 m3projectTelQuel (MAP dispatch)
SteelAbout 12,000 tprojectTelQuel (MAP dispatch)
Lanes4 lanes (2 each way)projectBladi.net
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 1.38 bnBudgetproject (the viaduct)November 2026TelQuel (MAP dispatch)
MAD 1.2 bnContract valueworks contract awarded to SGTMNovember 2023Le Desk
MAD 9 bnTotal project costTiznit-Dakhla expressway (1,055 km), not the viaduct aloneNovember 2026TelQuel (MAP dispatch)
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and WaterOwnermaître d'ouvrageNeogenesis
SGTM (Société Générale des Travaux du Maroc)General contractorworks contract won in November 2023Le Desk
Novec (CDG group)Engineerowner's assistant (assistance à maîtrise d'ouvrage)Neogenesis
NeogenesisEngineercheck of the first-category temporary works (cofferdams, climbing forms, pier segment forms, form travellers), 2025-2026Neogenesis
Arab Fund for Economic and Social DevelopmentLenderloan agreement to finance the Laâyoune western ring road, per pressBladi.net
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
November 2, 2023Works contract awarded to SGTMLe Desk
July 28, 2024Start of works on the viaduct reported (MAD 1.38 billion)Le Desk
November 3, 2026Works 57% completeTelQuel (MAP dispatch)
July 2027 (planned)Commissioning plannedNeogenesis
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A 1,648 m road viaduct is being built over the Oued Sakia El Hamra on the Laâyoune bypass, part of the 1,055 km Tiznit-Dakhla expressway. The Ministry of Equipment and Water is the owner and SGTM the contractor. The prestressed concrete box girder is built by the balanced cantilever method on 14 piers, some 46.5 m high. Works were 57% complete in November 2026, with commissioning planned for July 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.