Research record, fact-checked
Laâyoune phosphate port (Phosboucraa)
- Location
- Laâyoune coast (El Marsa area), Laâyoune-Sakia El Hamra, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of March 30, 2026 (Le360). Le360 reported in March 2026 that the works on OCP's new phosphate port at Laâyoune had reached 95%.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Phosboucraa (OCP Group) | |
| Type | Ports | |
| Headline amount | MAD 5.2 billion (MAD), as of July 29, 2024 | Medi1News (with MAP) |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Access bridge | 3.5 km | access bridge to the berths | Medi1News (with MAP) |
| Access bridge width | 25 m | access bridge | Medi1News (with MAP) |
| Caisson breakwater length | 920 m | protection works | Medi1News (with MAP) |
| Design ship | 100,000 t | Post-Panamax | Medi1News (with MAP) |
| Capacity | 5.2 Mt/year | first phase, expandable to 8.2 Mt with a third berth | Medi1News (with MAP) |
| Seawater intake | 30,000 m3/h | water intake | Medi1News (with MAP) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 5.2 bn | Total project cost | project | July 29, 2024 | Medi1News (with MAP) |
| MAD 4.2 bn | Budget | new wharf, 2016 announcement | February 18, 2016 | La Vie éco |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Phosboucraa (OCP Group) | Owner | OCP subsidiary | Medi1News (with MAP) |
| Archirodon | EPC contractor | EPC contract since 2019: caisson breakwater, 3.2 km trestle, four post-Panamax berths, 30,000 m3/h seawater intake; USD 460,000,000 | Archirodon |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 18, 2016 | OCP announces a new wharf at Laâyoune within its Phosboucraa programme | La Vie éco |
| July 29, 2024 | Works at 85% (MAP) | Medi1News (with MAP) |
| March 30, 2026 | Works at 95% | Le360 |
About the project
Phosboucraa, the OCP subsidiary, is building a new phosphate port at Laâyoune to import raw materials for its fertiliser complex and export phosphate, fertilisers and phosphoric acid. A 3.5 km access bridge leads to berths sheltered by a 920 m caisson breakwater, for ships of up to 100,000 tonnes. The total amount is MAD 5.2 billion, and the works were 95% complete in early 2026.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Construction, extension et modernisation : comment les ports ont enchaîné les chantiers, Le360 (press), 30 Mar 2026. Consulted 20 Nov 2026.
- Le nouveau port phosphatier de Laâyoune a atteint 85% de taux d'avancement, Medi1News (with MAP) (state news agency (map)), 29 Jul 2024. Consulted 20 Nov 2026.
- Le Groupe OCP investit 19 milliards de DH à Laâyoune, La Vie éco (press), 18 Feb 2016. Consulted 20 Nov 2026.
- Phosphate port, Laayoune, Morocco, Archirodon (company). Consulted 23 Nov 2026.