Grand Stade de Marrakech upgrade for the 2030 World Cup
- Location
- Marrakech, Marrakech-Safi, Morocco. See it on the map, in 3D
- Stage
- Contract awarded, works not confirmed, as of June 2026 (La Vie éco). ANEP awarded lot 1 (demolition, structure and finishes) to TGCC in June 2026. Lot 2 (roof and façade) was put out to international tender in July 2026, with bids due on 7 September 2026; no award was found.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | ANEP (Agence nationale des équipements publics) | |
| Type | Stadiums | |
| Headline amount | MAD 1.265 billion (MAD), as of August 2026 | La Tribune de Marrakech |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Capacity | 45,860 seats | after works | La Vie éco |
| Capacity before | 40,500 seats | before works | La Vie éco |
| Capacity | About 46,000 seats | after works | La Tribune de Marrakech |
| Pitch lowering | 6 m | pitch | La Tribune de Marrakech |
| Roof columns | 4 | new roof | La Vie éco |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 903 M | Contract value | lot 1: demolition, structure, waterproofing, finishes | June 2026 | La Vie éco |
| MAD 883 M | Budget | lot 1 estimate | April 2026 | La Vie éco |
| MAD 767 M | Budget | lot 2: roof and façade, tender estimate | July 2026 | appeldoffres.ma (tender notice 04/GSM/2026/ANEP) |
| MAD 1.26 bn | Budget | electrical works tender estimate | August 2026 | La Tribune de Marrakech |
| MAD 212 M | Budget | plumbing, water and air conditioning tender estimate | August 2026 | La Tribune de Marrakech |
| MAD 3.1 bn | Budget | contracts identified to date (lot 1 award plus three tenders) | August 2026 | La Tribune de Marrakech |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ANEP (Agence nationale des équipements publics) | Owner | contracting authority for the works (tender 04/GSM/2026/ANEP) | La Vie éco |
| Sonarges | Other role | national stadium management company; states the capacity target | La Vie éco |
| TGCC | Contractor, one lot | lot 1, demolition, structure, waterproofing and finishes, MAD 902.86M, sole admissible bid (June 2026) | La Vie éco |
| Saâd Benkirane Architecte | Architect | architectural design of the upgrade | La Vie éco |
| Gregotti Associati International | Architect | named with Saad Benkirane as designer in April 2026 (Gregotti designed the original stadium) | La Vie éco |
| EGIS Bâtiments International | Engineer | technical studies, with LUSEO | La Vie éco |
| LUSEO | Engineer | technical studies, with EGIS | La Vie éco |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 28, 2026 | ANEP tender for lot 1, estimated at MAD 883.2M, 15 months | La Vie éco |
| June 25, 2026 | Lot 1 awarded to TGCC for MAD 902.86M | Médias24 |
| July 2026 | International tender for lot 2, roof and façade, estimated at MAD 767.2M, 12 months | La Vie éco |
| September 7, 2026 | Lot 2 bids due | appeldoffres.ma (tender notice 04/GSM/2026/ANEP) |
| December 2028 (planned) | Delivery announced for the end of 2028 | La Tribune de Marrakech |
About the project
The rebuilding of the Grand Stade de Marrakech for the 2030 World Cup, procured by the national public facilities agency ANEP. The athletics track goes, the pitch is lowered, the stands move closer and capacity rises to about 46,000, under a new roof on four corner columns. TGCC won lot 1 in June 2026 for MAD 902.86 million; the roof and façade lot was in tender in September 2026. Delivery is announced for the end of 2028.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Mondial 2030 : TGCC remporte un lot du marché de mise à niveau du stade de Marrakech pour près de 903 MDH, Médias24 (press), 25 Jun 2026. Consulted 23 Nov 2026.
- Grand Stade de Marrakech : 767 MDH pour la couverture et la façade, La Vie éco (press), 23 Jul 2026. Consulted 23 Nov 2026.
- Mondial 2030 : 883 MDH pour la mise à niveau du Grand Stade de Marrakech, La Vie éco (press), 28 Apr 2026. Consulted 23 Nov 2026.
- Travaux de mise à niveau du Grand Stade de Marrakech, lot n°2 : couverture et façade, appeldoffres.ma (tender notice 04/GSM/2026/ANEP) (government), Jul 2026. Consulted 23 Nov 2026.
- Grand Stade de Marrakech : les travaux avant le Mondial 2030, La Tribune de Marrakech (press), 23 Aug 2026. Consulted 23 Nov 2026.
- Le Maroc accélère la modernisation du Stade de Marrakech, Hespress FR (press), 26 Jul 2026. Consulted 23 Nov 2026.