Research record, fact-checked

Marrakech Menara airport: terminal extension

Location
Marrakech (commune of Ménara), Marrakech-Safi, Morocco. See it on the map, in 3D
Stage
Under construction, as of September 2026 (Le Desk). ONDA awarded the contract to Jet Contractors on 18 August 2025. Le Desk reported the extension at 15% complete at the end of September 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerONDA (Office National des Aéroports)
TypeAirports
Headline amountMAD 3 billion (MAD), as of October 2025ONDA / African Development Bank
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Terminal floor area, after the worksAbout 142,000 m2terminals 1 and 2 after extensionLa Vie Eco
Terminal floor area before65,700 m2existing terminals, excluding basement (since 2017)ONDA / African Development Bank
Passengers a year16,000,000 passengers a yearairport after worksLa Vie Eco
Capacity passengers per year afdb14,000,000 passengers a yearAfDB 2030 figureAfrican Development Bank
Runway length3,100 mexisting runwayONDA / African Development Bank
Runway width45 mexisting runwayONDA / African Development Bank
Contact stands existing6 standsbefore worksONDA / African Development Bank
Remote stands existing30 standsbefore worksONDA / African Development Bank
Airport areaAbout 510 haairportONDA / African Development Bank
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 2.2 bnContract valueterminal extension and refit (Jet Contractors), incl. taxAugust 2025LesEco.ma
MAD 1.8 bnContract valueterminal extension (Jet Contractors), excl. taxJune 2026La Tribune de Marrakech
MAD 3 bnBudgetextension and refit of the terminal facilities (ESIA)October 2025ONDA / African Development Bank
€270 MLoanAfDB PEMIA loan to ONDA, shared by Marrakech, Agadir, Tangier and FezDecember 2025African Development Bank
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONDA (Office National des Aéroports)OwnerLesEco.ma
Jet ContractorsGeneral contractorterminal extension and refit, awarded 18 August 2025La Vie Eco
Abdou LahlouArchitectarchitectural studies awarded before February 2024 (press, via Le360)Bladi.net (citing Le360)
African Development BankLenderPEMIA loan of EUR 270M; at Marrakech it finances the apron extension, taxiways, apron lighting, security and mobility equipmentONDA / African Development Bank
TGCC-Inter TridimBidderbid MAD 2.532bn incl. taxes, not retainedLesEco.ma
SGTMBidderbid MAD 2.705bn incl. taxes, not retainedLesEco.ma
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
February 2024Architectural studies awarded to Abdou Lahlou (press)Bladi.net (citing Le360)
July 10, 2025Bids opened: Jet Contractors MAD 2.2bn, TGCC MAD 2.5bn, SGTM MAD 2.6bnBoursenews
August 18, 2025Contract awarded to Jet ContractorsLa Vie Eco
December 12, 2025AfDB board approves EUR 270M PEMIA loan (Marrakech, Agadir, Tangier, Fez)African Development Bank
September 30, 2026Extension about 15% complete (Le Desk)Le Desk
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

ONDA is extending and refitting the passenger terminals of Marrakech Menara airport to about 142,000 m2, to raise capacity from 9 to 16 million passengers a year. Jet Contractors won the works contract in August 2025 with a bid of MAD 2.204 billion including tax. The wider programme adds aircraft stands, taxiways and a new control tower, partly financed by an African Development Bank loan. Works were about 15% complete at the end of September 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.