Mokhtar Soussi dam raising

Location
On the Oued Aouzioua, about 100 km east of Taroudant, Souss-Massa, Morocco. See it on the map, in 3D
Stage
Under construction, as of September 2026 (Le360). Le360 reports 83.5% progress on 19 Sept 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Equipment and Water
TypeDams and hydro
Headline amountMAD 1.3 billion (MAD), as of May 2021BTP News
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Height before62.5 m above foundationexisting damBTP News
Height after101 m above foundationraised damBTP News
Crest length after768 mraised damBTP News
Fill volume6 million m3raisingBTP News
Reservoir, before raising50 million m3existing dam (2002)BTP News
Reservoir, after raising281 million m3raised damBTP News
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 1.3 bnTotal project costprojectMay 2021BTP News
Nearly MAD 1.3 bnBudgetprojectOctober 2026Le360
MAD 1.64 bnBudgetprojectSeptember 2026Le360
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and WaterOwnerWorks launched by the minister in May 2021BTP News
AlsinaSupplierFormwork systemsAlsina
SomagecGeneral contractordam raising works, due to finish by end 2026La Vie éco
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
2002Original dam in serviceBTP News
May 26, 2021Minister launches the raising works (66-month schedule)BTP News
September 19, 202683.5% (ministry figures)Le360
October 15, 2026Past 85%Le360
January 2027 (planned)Commissioning expected in early 2027Le360
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The raising of the Mokhtar Soussi dam on the Oued Aouzioua, about 100 km east of Taroudant, from 62.5 m to 101 m above foundation with a 768 m crest. It takes the reservoir from 50 million m3 to about 281 million m3, for water supply, irrigation, aquifer recharge and flood protection in Souss-Massa. Works began in May 2021 and passed 85% in October 2026; commissioning is expected in early 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.