Research record, fact-checked
Mokhtar Soussi dam raising
- Location
- On the Oued Aouzioua, about 100 km east of Taroudant, Souss-Massa, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of September 2026 (Le360). Le360 reports 83.5% progress on 19 Sept 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water | |
| Type | Dams and hydro | |
| Headline amount | MAD 1.3 billion (MAD), as of May 2021 | BTP News |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Height before | 62.5 m above foundation | existing dam | BTP News |
| Height after | 101 m above foundation | raised dam | BTP News |
| Crest length after | 768 m | raised dam | BTP News |
| Fill volume | 6 million m3 | raising | BTP News |
| Reservoir, before raising | 50 million m3 | existing dam (2002) | BTP News |
| Reservoir, after raising | 281 million m3 | raised dam | BTP News |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water | Owner | Works launched by the minister in May 2021 | BTP News |
| Alsina | Supplier | Formwork systems | Alsina |
| Somagec | General contractor | dam raising works, due to finish by end 2026 | La Vie éco |
Milestones
| Date | Milestone | Source |
|---|---|---|
| 2002 | Original dam in service | BTP News |
| May 26, 2021 | Minister launches the raising works (66-month schedule) | BTP News |
| September 19, 2026 | 83.5% (ministry figures) | Le360 |
| October 15, 2026 | Past 85% | Le360 |
| January 2027 (planned) | Commissioning expected in early 2027 | Le360 |
About the project
The raising of the Mokhtar Soussi dam on the Oued Aouzioua, about 100 km east of Taroudant, from 62.5 m to 101 m above foundation with a 768 m crest. It takes the reservoir from 50 million m3 to about 281 million m3, for water supply, irrigation, aquifer recharge and flood protection in Souss-Massa. Works began in May 2021 and passed 85% in October 2026; commissioning is expected in early 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Sept barrages dépassent 80% de réalisation: le point sur les grands réservoirs en chantier, Le360 (press), 19 Sep 2026. Consulted 20 Nov 2026.
- Taroudant: les travaux de surélévation du barrage Mokhtar Soussi dépassent 85% d'avancement, Le360 (press), 15 Oct 2026. Consulted 20 Nov 2026.
- Taroudant.. M. Amara lance les travaux de surélévation du barrage Mokhtar Soussi, BTP News (press), 26 May 2021. Consulted 20 Nov 2026.
- Modernisation du barrage Mokhtar Soussi, Alsina (company). Consulted 20 Nov 2026.
- Dragage portuaire : Comment Somagec est devenue le maître des fonds marins, La Vie éco (press), 1 Apr 2026. Consulted 23 Nov 2026.
- Sept barrages dépassent 80% de réalisation: le point sur les grands réservoirs en chantier, Le360 (press), 19 Sep 2026. Consulted 23 Nov 2026.