Research record, fact-checked

Nador West Med port and industrial complex

Location
Iaazzanene (Iâazanene), Nador province, Oriental, Morocco. See it on the map, in 3D
Stage
Partly in service, partly under construction, as of October 31, 2026 (Le360 (with MAP)). The Crown Prince launched operations of the East container terminal on 31 October 2026. The West container terminal is due in April 2027 and other terminals in 2027 and 2028.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnersNador West Med SA, West Med Container Terminal (Marsa Maroc and Terminal Investment Limited, MSC), Marsa Maroc and CMA CGM, Marsa Maroc-Boluda Towage France
TypePorts
Headline amountMAD 10.12 billion (MAD), as of March 2015African Development Bank
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Platform areaAbout 1,500 haport, commercial, industrial, logistics and services platform (free zone)African Development Bank
Industrial zone area700 haindustrial and logistics platformLe360 (with MAP)
Main breakwater4,200 mfirst moduleAfrican Development Bank
Secondary breakwater1,200 mfirst moduleAfrican Development Bank
Protected water areaAbout 250 hafirst moduleAfrican Development Bank
East container quay length1,520 mEast container terminalLe360 (with MAP)
East container depth18 mEast container terminalLe360 (with MAP)
East container yard70 haEast container terminalLe360 (with MAP)
East container capacity3,500,000 containers/yearEast container terminal, by 2030Le360 (with MAP)
West container quay length900 mWest container terminalLe360 (with MAP)
West container yard38 haWest container terminalLe360 (with MAP)
West container capacity1,800,000 TEU/yearWest container terminalConstruction Review Online
Roro capacity400,000 units/yearro-ro terminalLe360 (with MAP)
Roro quay length380 mro-ro terminalLe360 (with MAP)
General cargo terminal area22 hageneral cargo terminalLe360 (with MAP)
Bulk terminal capacity7 Mt/yearbulk (coal) terminalLe360 (with MAP)
Lng terminal quay length360 mplanned LNG terminalLe360 (with MAP)
Hydrocarbon terminal25 Mt/yearhydrocarbon terminal, three 125 m berthsLe360 (with MAP)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 54 bnInvestment programmeproject (public and private, port and industrial complex)October 31, 2026Le360 (with MAP)
MAD 31 bnInvestment programmepublic shareNovember 3, 2026Construction Review Online
MAD 23 bnInvestment programmeprivate shareNovember 3, 2026Construction Review Online
MAD 10.1 bnTotal project costfirst port module (civil works, land, supervision), 2015 estimateMarch 2015African Development Bank
MAD 5 bnInvestment programmeEast container terminal (concessionaire)October 31, 2026Le360 (with MAP)
MAD 3 bnInvestment programmeWest container terminal (concessionaire)October 31, 2026Le360 (with MAP)
MAD 12 bnInvestment programmeindustrial and logistics platform (private)October 31, 2026Le360 (with MAP)
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Nador West Med SAOwnerdeveloper of the port and free zone (Tanger Med group)Construction Review Online
West Med Container Terminal (Marsa Maroc and Terminal Investment Limited, MSC)ConcessionaireEast container terminal, 25-year concession; Marsa Maroc 50% plus one shareLe360 (with MAP)
Marsa Maroc and CMA CGMConcessionaireWest container terminalLe360 (with MAP)
STFA-SGTM joint ventureGeneral contractormarine works; named by Artelia as its client for the physical model tests of the breakwatersArtelia (laboratory)
ArteliaEngineer2D and 3D physical model tests of the protection works, for the STFA-SGTM joint ventureArtelia (laboratory)
African Development BankLenderESIA summary of the first port module published by the AfDB (2015)African Development Bank
SBTXContractor, one lotactivity zone phase I, industrial zone: earthworks, roads, networks and a turnkey treatment plant, MAD 367,697,133.75 excl. taxes, started 24 March 2025, 18 months (AfDB-financed PAZAP project)Nador West Med
NGE ContractingContractor, one lotactivity zone phase I, energy zone: earthworks, roads and networks, MAD 379,313,168.00 excl. taxes, started 24 March 2025, 18 monthsNador West Med
China Road and Bridge CorporationContractor, one lotactivity zone phase I, logistics zone: earthworks, roads and networks, MAD 414,666,666.28 excl. taxes, started 21 April 2025, 18 monthsNador West Med
Marsa Maroc-Boluda Towage FranceConcessionairetowage and assistance services for 20 years from the last quarter of 2026, through a joint subsidiary held 51% by Boluda Towage France and 49% by Marsa Maroc; Boluda Towage France is a subsidiary of Boluda Corporación MarítimaLesEco.ma
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
March 2015AfDB publishes the ESIA summary of the first port moduleAfrican Development Bank
September 2026 (planned)Ro-ro terminal (380 m quay) dueLe360 (with MAP)
October 31, 2026Crown Prince Moulay El Hassan launches operations of the East container terminalLe360 (with MAP)
April 2027 (planned)West container terminal and hydrocarbon terminal dueLe360 (with MAP)
June 2027 (planned)Bulk terminal (7 Mt) dueLe360 (with MAP)
December 2028 (planned)General cargo terminal (22 ha, 3 Mt) dueLe360 (with MAP)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

Nador West Med is a new deepwater port and free zone on the Bay of Betoya, west of Nador, on Morocco's Mediterranean coast. Its first module has a 4.2 km main breakwater, a 1.2 km secondary breakwater and container, bulk, hydrocarbon, ro-ro and general cargo terminals. The East container terminal, run by Marsa Maroc and MSC's Terminal Investment Limited, started operations on 31 October 2026. The West container terminal, conceded to Marsa Maroc and CMA CGM, is due in April 2027.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.