Nador West Med port and industrial complex
- Location
- Iaazzanene (Iâazanene), Nador province, Oriental, Morocco. See it on the map, in 3D
- Stage
- Partly in service, partly under construction, as of October 31, 2026 (Le360 (with MAP)). The Crown Prince launched operations of the East container terminal on 31 October 2026. The West container terminal is due in April 2027 and other terminals in 2027 and 2028.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owners | Nador West Med SA, West Med Container Terminal (Marsa Maroc and Terminal Investment Limited, MSC), Marsa Maroc and CMA CGM, Marsa Maroc-Boluda Towage France | |
| Type | Ports | |
| Headline amount | MAD 10.12 billion (MAD), as of March 2015 | African Development Bank |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Platform area | About 1,500 ha | port, commercial, industrial, logistics and services platform (free zone) | African Development Bank |
| Industrial zone area | 700 ha | industrial and logistics platform | Le360 (with MAP) |
| Main breakwater | 4,200 m | first module | African Development Bank |
| Secondary breakwater | 1,200 m | first module | African Development Bank |
| Protected water area | About 250 ha | first module | African Development Bank |
| East container quay length | 1,520 m | East container terminal | Le360 (with MAP) |
| East container depth | 18 m | East container terminal | Le360 (with MAP) |
| East container yard | 70 ha | East container terminal | Le360 (with MAP) |
| East container capacity | 3,500,000 containers/year | East container terminal, by 2030 | Le360 (with MAP) |
| West container quay length | 900 m | West container terminal | Le360 (with MAP) |
| West container yard | 38 ha | West container terminal | Le360 (with MAP) |
| West container capacity | 1,800,000 TEU/year | West container terminal | Construction Review Online |
| Roro capacity | 400,000 units/year | ro-ro terminal | Le360 (with MAP) |
| Roro quay length | 380 m | ro-ro terminal | Le360 (with MAP) |
| General cargo terminal area | 22 ha | general cargo terminal | Le360 (with MAP) |
| Bulk terminal capacity | 7 Mt/year | bulk (coal) terminal | Le360 (with MAP) |
| Lng terminal quay length | 360 m | planned LNG terminal | Le360 (with MAP) |
| Hydrocarbon terminal | 25 Mt/year | hydrocarbon terminal, three 125 m berths | Le360 (with MAP) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 54 bn | Investment programme | project (public and private, port and industrial complex) | October 31, 2026 | Le360 (with MAP) |
| MAD 31 bn | Investment programme | public share | November 3, 2026 | Construction Review Online |
| MAD 23 bn | Investment programme | private share | November 3, 2026 | Construction Review Online |
| MAD 10.1 bn | Total project cost | first port module (civil works, land, supervision), 2015 estimate | March 2015 | African Development Bank |
| MAD 5 bn | Investment programme | East container terminal (concessionaire) | October 31, 2026 | Le360 (with MAP) |
| MAD 3 bn | Investment programme | West container terminal (concessionaire) | October 31, 2026 | Le360 (with MAP) |
| MAD 12 bn | Investment programme | industrial and logistics platform (private) | October 31, 2026 | Le360 (with MAP) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Nador West Med SA | Owner | developer of the port and free zone (Tanger Med group) | Construction Review Online |
| West Med Container Terminal (Marsa Maroc and Terminal Investment Limited, MSC) | Concessionaire | East container terminal, 25-year concession; Marsa Maroc 50% plus one share | Le360 (with MAP) |
| Marsa Maroc and CMA CGM | Concessionaire | West container terminal | Le360 (with MAP) |
| STFA-SGTM joint venture | General contractor | marine works; named by Artelia as its client for the physical model tests of the breakwaters | Artelia (laboratory) |
| Artelia | Engineer | 2D and 3D physical model tests of the protection works, for the STFA-SGTM joint venture | Artelia (laboratory) |
| African Development Bank | Lender | ESIA summary of the first port module published by the AfDB (2015) | African Development Bank |
| SBTX | Contractor, one lot | activity zone phase I, industrial zone: earthworks, roads, networks and a turnkey treatment plant, MAD 367,697,133.75 excl. taxes, started 24 March 2025, 18 months (AfDB-financed PAZAP project) | Nador West Med |
| NGE Contracting | Contractor, one lot | activity zone phase I, energy zone: earthworks, roads and networks, MAD 379,313,168.00 excl. taxes, started 24 March 2025, 18 months | Nador West Med |
| China Road and Bridge Corporation | Contractor, one lot | activity zone phase I, logistics zone: earthworks, roads and networks, MAD 414,666,666.28 excl. taxes, started 21 April 2025, 18 months | Nador West Med |
| Marsa Maroc-Boluda Towage France | Concessionaire | towage and assistance services for 20 years from the last quarter of 2026, through a joint subsidiary held 51% by Boluda Towage France and 49% by Marsa Maroc; Boluda Towage France is a subsidiary of Boluda Corporación Marítima | LesEco.ma |
Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 2015 | AfDB publishes the ESIA summary of the first port module | African Development Bank |
| September 2026 (planned) | Ro-ro terminal (380 m quay) due | Le360 (with MAP) |
| October 31, 2026 | Crown Prince Moulay El Hassan launches operations of the East container terminal | Le360 (with MAP) |
| April 2027 (planned) | West container terminal and hydrocarbon terminal due | Le360 (with MAP) |
| June 2027 (planned) | Bulk terminal (7 Mt) due | Le360 (with MAP) |
| December 2028 (planned) | General cargo terminal (22 ha, 3 Mt) due | Le360 (with MAP) |
About the project
Nador West Med is a new deepwater port and free zone on the Bay of Betoya, west of Nador, on Morocco's Mediterranean coast. Its first module has a 4.2 km main breakwater, a 1.2 km secondary breakwater and container, bulk, hydrocarbon, ro-ro and general cargo terminals. The East container terminal, run by Marsa Maroc and MSC's Terminal Investment Limited, started operations on 31 October 2026. The West container terminal, conceded to Marsa Maroc and CMA CGM, is due in April 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Sur instructions du Roi, Moulay El Hassan lance les opérations du premier terminal à conteneurs du port Nador West Med, Le360 (with MAP) (state news agency (map)), 31 Oct 2026. Consulted 20 Nov 2026.
- Maroc, Complexe portuaire Nador West Med, Résumé EIES (OITC, 03/2015), African Development Bank (lender), Mar 2015. Consulted 20 Nov 2026.
- First container terminal officially launched at $5.5bn Nador West Med port in Morocco, Construction Review Online (press), 3 Nov 2026. Consulted 20 Nov 2026.
- Port de Nador West Med (Maroc), ouvrages maritimes et portuaires, Artelia (laboratory) (company). Consulted 20 Nov 2026.
- Publication de l'attribution du marché de travaux, note d'information: Phase I, Zone Industrielle (AOIO NWM/DG/15/2024), Nador West Med (owner), 11 Dec 2024. Consulted 23 Nov 2026.
- Publication de l'attribution du marché de travaux, note d'information: Phase I, Zone Énergie (AOIO NWM/DG/11/2024), Nador West Med (owner), 4 Nov 2024. Consulted 23 Nov 2026.
- Publication de l'attribution du marché de travaux, note d'information: Phase I, Zone Logistique (AOIO NWM/DG/16/2024), Nador West Med (owner), 20 Dec 2024. Consulted 23 Nov 2026.
- Nador West Med : Marsa Maroc-Boluda Towage France en charge du remorquage, LesEco.ma (press), 3 Apr 2025. Consulted 23 Nov 2026.