Nador West Med rail link
- Location
- Nador province, Selouane to Nador West Med port, Oriental, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of October 2025 (Hespress FR). The minister of Equipment and Water told the House of Representatives in October 2025 that the technical studies were complete and 65% of the priority infrastructure was built, with tenders for four further lots being launched.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | ONCF (Office National des Chemins de Fer) | |
| Type | Rail | |
| Amount | Not found in the sources consulted |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 53 km | project | Hespress FR |
| Length | About 40 km | Selouane to port section | Ports Europe |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 606 M | Contract value | Selouane to port section (tender estimate) | July 2025 | Ports Europe |
| MAD 504 M | Contract value | Selouane to Nador West Med tender of January 2025 (estimate) | January 2025 | L'Opinion |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ONCF (Office National des Chemins de Fer) | Owner | procuring authority | Ports Europe |
| Ministry of Equipment and Water | Government | progress reported to Parliament by minister Abdessamad Kayouh | Hespress FR |
Milestones
| Date | Milestone | Source |
|---|---|---|
| January 9, 2025 | ONCF tender for a Selouane-Nador West Med rail section, estimated at MAD 504 million | L'Opinion |
| July 2025 | ONCF tender for the Selouane to port section, MAD 606 million, 20 months | Ports Europe |
| October 31, 2025 | Studies 100% complete, 65% of priority infrastructure built, four lots being tendered | Hespress FR |
About the project
ONCF is building a 53 km line for freight and passengers to connect the Nador West Med port to the national rail network. The section from Selouane to the port, about 40 km, was tendered in July 2025 for MAD 606 million with a 20-month completion time. In October 2025 the minister said 65% of the priority infrastructure was built and four more lots were being tendered.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Rail : de grands projets à venir pour renforcer le réseau national, Hespress FR (press), 31 Oct 2025. Consulted 23 Nov 2026.
- Tender for key rail link to Morocco's future Nador West Med port, Ports Europe (press), Jul 2025. Consulted 23 Nov 2026.
- L'ONCF lance un projet ferroviaire de 504 millions de dirhams entre Selouane et Nador, L'Opinion (press), 9 Jan 2025. Consulted 23 Nov 2026.
- Liaison ferroviaire Selouane-Nador West Med : l'ONCF lance le chantier d'un important tronçon pour 606 MDH, Médias24 (press), 7 Jul 2025. Consulted 23 Nov 2026.