OCP Mzinda Phosphate Hub

Location
Mzinda, near Youssoufia, Marrakech-Safi, Morocco. See it on the map, in 3D
Stage
Under construction, as of April 2025 (EcoActu). Civil works started in June 2024; in April 2025 progress ranged from 15 to 24% across the components and workshops.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerOCP Nutricrops
TypeIndustry
AmountNot found in the sources consulted
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Phosphate rock processed6 Mt/yearby end 2027Le Nouvelliste
Chemical complex capacity3 MtMzinda chemical complexEcoActu
Unitsphosphoric acid (PAP), sulphuric acid (SAP), autonomous power plantprojectLe Nouvelliste
Physical figures, as their sources describe them

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
OCP NutricropsOwnerAPA News
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
June 2024Civil works launchedEcoActu
April 202515 to 24% across componentsEcoActu
December 2027 (planned)6 Mt of phosphate rock processed a yearLe Nouvelliste
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A new OCP chemical and mining complex at Mzinda, near Youssoufia, to process 6 million tonnes of phosphate rock a year by the end of 2027, from the Benguerir and Youssoufia mines and the future Louta mine. It includes phosphoric and sulphuric acid units and its own power plant, and runs on solar power and desalinated water from Safi. Civil works started in June 2024 and were 15 to 24% complete in April 2025.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.