Rabat-Casablanca continental motorway
- Location
- Tamesna (Rabat bypass) to Tit Mellil (Casablanca), Rabat-Salé-Kénitra / Casablanca-Settat, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of April 29, 2026 (L'Economiste). Eight of nine lots were awarded in May 2025; La Vie éco reported in December 2025 that works had started, and L'Economiste reported on 29 April 2026 that they were continuing.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | ADM (Société Nationale des Autoroutes du Maroc) | |
| Type | Highways | |
| Headline amount | MAD 6.95 billion (MAD), as of October 22, 2025 | Bladi.net (relaying the 2026 budget bill) |
| What it covers | Budget. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Length | 59 km | project | Hespress FR (ADM statement) |
| Lanes | 3 lanes each way | project | Le360 |
| Wadis crossed | 7 | project | Le360 |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 6.5 bn | Budget | project (provisional) | May 9, 2025 | Hespress FR (ADM statement) |
| MAD 6.95 bn | Budget | project, in the 2026 budget bill | October 22, 2025 | Bladi.net (relaying the 2026 budget bill) |
| MAD 653 M | Contract value | lot 1, Casablanca bypass-Oued El Maleh | May 7, 2025 | Le360 |
| MAD 628 M | Contract value | lot 2, Oued El Maleh-Oued Nfifikh | May 7, 2025 | Le360 |
| MAD 988 M | Contract value | lot 3, Oued Nfifikh-Oued Elghbar | May 7, 2025 | Le360 |
| MAD 1.13 bn | Contract value | lot 4, Oued Elghbar-Oued Charrate | May 7, 2025 | Le360 |
| MAD 749 M | Contract value | lot 5, Oued Charrate-Oued Yquem | May 7, 2025 | Le360 |
| MAD 574 M | Contract value | lot 6, Oued Yquem-RP 4022 | May 7, 2025 | Le360 |
| MAD 126 M | Contract value | lot 7, Oued Hassar viaduct | May 7, 2025 | Le360 |
| MAD 130 M | Contract value | lot 8, viaducts on Oued Elghbar and Oued Mhasser | May 7, 2025 | Le360 |
| MAD 12.5 bn | Investment programme | State-ADM programme 2025-2032 (Rabat-Casablanca continental, Tit Mellil-Berrechid, Sidi Maarouf and Aïn Harrouda nodes) | May 10, 2026 | Bladi.net |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| ADM (Société Nationale des Autoroutes du Maroc) | Owner | project owner | Le360 |
| ADM Projet | Engineer | ADM's engineering subsidiary, presented the works launch | Bladi.net |
| Mojazine | Contractor, one lot | lot 1, MAD 653.4M | Le360 |
| El Hallaoui | Contractor, one lot | lots 2 and 3, MAD 627.6M and 988.2M | Le360 |
| SNTRO with China Railway No.4 Engineering Group | Contractor, one lot | lot 4, MAD 1.13bn | Le360 |
| China Road and Bridge Corporation with Aleq | Contractor, one lot | lots 5 and 6, MAD 749.2M and 574.1M | Le360 |
| Jet Contractors | Contractor, one lot | lot 7, Oued Hassar viaduct, MAD 126.3M | Le360 |
| Seprob | Contractor, one lot | lot 8, viaducts on Oued Elghbar and Oued Mhasser, MAD 129.7M | Le360 |
| Novec | Designer | execution studies, Casablanca-Benslimane section (one of two study lots) | LesEco.ma |
| CID | Designer | execution studies, Benslimane-Rabat section; also carried out the environmental impact study | LesEco.ma |
| LPEE | Other role | geotechnical and geophysical works, MAD 10.2M | LesEco.ma |
Milestones
| Date | Milestone | Source |
|---|---|---|
| December 2019 | Studies started (end of 2019) | Hespress FR (ADM statement) |
| December 2024 | Tenders launched | Hespress FR (ADM statement) |
| May 5, 2025 | ADM publishes the winners of eight of nine lots; the ninth is cancelled | Le360 |
| December 30, 2025 | Works reported as started, completion in 2028 (La Vie éco) | La Vie éco |
| April 29, 2026 | Works reported continuing | L'Economiste |
| 2028 (planned) | Completion planned (ADM, May 2025); Le360 says by 2029 | Hespress FR (ADM statement) |
About the project
A new 59 km motorway inland of the existing A1, from the Tamesna interchange on the Rabat bypass to Tit Mellil on Casablanca's southern ring, passing near the Grand Stade Hassan II. ADM awarded eight of its nine lots in May 2025, mostly to Moroccan firms, and works were reported under way in April 2026. It has three lanes per direction and crosses seven wadis on several viaducts. The budget is MAD 6.5 billion and completion is planned for 2028 or 2029.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Autoroute continentale Rabat-Casablanca: les entreprises marocaines raflent 75% du marché, Le360 (press), 7 May 2025. Consulted 20 Nov 2026.
- ADM : Les projets autoroutiers avancent à grands pas, 10,25 MMDH investis, Hespress FR (ADM statement) (press), 9 May 2025. Consulted 20 Nov 2026.
- Infrastructures : progression des travaux de l'autoroute continentale Rabat-Casablanca, L'Economiste (press), 29 Apr 2026. Consulted 20 Nov 2026.
- Autoroute Rabat-Casablanca : les travaux démarrent, Bladi.net (press), 15 Apr 2026. Consulted 20 Nov 2026.
- Autoroutes : Nador se branche au réseau national, La Vie éco (press), 30 Dec 2025. Consulted 20 Nov 2026.
- Autoroutes au Maroc : les prochains grands chantiers se précisent, Bladi.net (press), 10 May 2026. Consulted 20 Nov 2026.
- Maroc : de gigantesques projets d'infrastructures lancés pour 2026, Bladi.net (relaying the 2026 budget bill) (press), 22 Oct 2025. Consulted 20 Nov 2026.
- Grand Stade Hassan II : la première brique bientôt posée, LesEco.ma (press), 2 May 2025. Consulted 23 Nov 2026.