Research record, fact-checked

Rabat-Casablanca continental motorway

Location
Tamesna (Rabat bypass) to Tit Mellil (Casablanca), Rabat-Salé-Kénitra / Casablanca-Settat, Morocco. See it on the map, in 3D
Stage
Under construction, as of April 29, 2026 (L'Economiste). Eight of nine lots were awarded in May 2025; La Vie éco reported in December 2025 that works had started, and L'Economiste reported on 29 April 2026 that they were continuing.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerADM (Société Nationale des Autoroutes du Maroc)
TypeHighways
Headline amountMAD 6.95 billion (MAD), as of October 22, 2025Bladi.net (relaying the 2026 budget bill)
What it coversBudget.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length59 kmprojectHespress FR (ADM statement)
Lanes3 lanes each wayprojectLe360
Wadis crossed7projectLe360
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 6.5 bnBudgetproject (provisional)May 9, 2025Hespress FR (ADM statement)
MAD 6.95 bnBudgetproject, in the 2026 budget billOctober 22, 2025Bladi.net (relaying the 2026 budget bill)
MAD 653 MContract valuelot 1, Casablanca bypass-Oued El MalehMay 7, 2025Le360
MAD 628 MContract valuelot 2, Oued El Maleh-Oued NfifikhMay 7, 2025Le360
MAD 988 MContract valuelot 3, Oued Nfifikh-Oued ElghbarMay 7, 2025Le360
MAD 1.13 bnContract valuelot 4, Oued Elghbar-Oued CharrateMay 7, 2025Le360
MAD 749 MContract valuelot 5, Oued Charrate-Oued YquemMay 7, 2025Le360
MAD 574 MContract valuelot 6, Oued Yquem-RP 4022May 7, 2025Le360
MAD 126 MContract valuelot 7, Oued Hassar viaductMay 7, 2025Le360
MAD 130 MContract valuelot 8, viaducts on Oued Elghbar and Oued MhasserMay 7, 2025Le360
MAD 12.5 bnInvestment programmeState-ADM programme 2025-2032 (Rabat-Casablanca continental, Tit Mellil-Berrechid, Sidi Maarouf and Aïn Harrouda nodes)May 10, 2026Bladi.net
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ADM (Société Nationale des Autoroutes du Maroc)Ownerproject ownerLe360
ADM ProjetEngineerADM's engineering subsidiary, presented the works launchBladi.net
MojazineContractor, one lotlot 1, MAD 653.4MLe360
El HallaouiContractor, one lotlots 2 and 3, MAD 627.6M and 988.2MLe360
SNTRO with China Railway No.4 Engineering GroupContractor, one lotlot 4, MAD 1.13bnLe360
China Road and Bridge Corporation with AleqContractor, one lotlots 5 and 6, MAD 749.2M and 574.1MLe360
Jet ContractorsContractor, one lotlot 7, Oued Hassar viaduct, MAD 126.3MLe360
SeprobContractor, one lotlot 8, viaducts on Oued Elghbar and Oued Mhasser, MAD 129.7MLe360
NovecDesignerexecution studies, Casablanca-Benslimane section (one of two study lots)LesEco.ma
CIDDesignerexecution studies, Benslimane-Rabat section; also carried out the environmental impact studyLesEco.ma
LPEEOther rolegeotechnical and geophysical works, MAD 10.2MLesEco.ma
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
December 2019Studies started (end of 2019)Hespress FR (ADM statement)
December 2024Tenders launchedHespress FR (ADM statement)
May 5, 2025ADM publishes the winners of eight of nine lots; the ninth is cancelledLe360
December 30, 2025Works reported as started, completion in 2028 (La Vie éco)La Vie éco
April 29, 2026Works reported continuingL'Economiste
2028 (planned)Completion planned (ADM, May 2025); Le360 says by 2029Hespress FR (ADM statement)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A new 59 km motorway inland of the existing A1, from the Tamesna interchange on the Rabat bypass to Tit Mellil on Casablanca's southern ring, passing near the Grand Stade Hassan II. ADM awarded eight of its nine lots in May 2025, mostly to Moroccan firms, and works were reported under way in April 2026. It has three lanes per direction and crosses seven wadis on several viaducts. The budget is MAD 6.5 billion and completion is planned for 2028 or 2029.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.