Research record, fact-checked
Ibn Sina University Hospital, Rabat
- Location
- Rabat, Rabat-Salé-Kénitra, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of June 2026 (Le360 (from the PLF 2027 regional investment note)). The 2027 finance bill's regional investment note puts the works at 90% at 30 June 2026, with opening planned in 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Health and Social Protection | |
| Type | Hospitals | |
| Headline amount | MAD 7.31 billion (MAD), as of October 2026 | Le360 (from the PLF 2027 regional investment note) |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Beds | 1,044 beds | hospital | TelQuel |
| Beds architect | 1,033 beds | architect's figure | AIA Life Designers |
| Tower floors | 33 floors above ground | hospitalisation tower, plus two lower levels | TelQuel |
| Tower height | 140 m | hospitalisation tower | AIA Life Designers |
| Medical block floors | 5 floors | medical and technical block, plus three lower levels | TelQuel |
| Cardiology tower floors | 11 floors | tower for the national league against cardiovascular disease, plus three lower levels | TelQuel |
| Floor area | 190,000 m2 | covered area | TelQuel |
| Site area | 11.4 ha | site | TelQuel |
| Park area | 6.5 ha | landscaped park | AIA Life Designers |
| Parking spaces | 1,300 spaces | car park | TelQuel |
| Operating rooms | 53 rooms | architect's figure | AIA Life Designers |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 7.31 bn | Total project cost | project (PLF 2027 note) | October 2026 | Le360 (from the PLF 2027 regional investment note) |
| MAD 6.53 bn | Total project cost | project (PLF 2025 note) | October 2024 | Le360 |
| MAD 6 bn | Total project cost | project at launch | May 2022 | TelQuel |
| €350 M | Budget | construction cost excl. taxes (architect) | April 2025 | AIA Life Designers |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Health and Social Protection | Owner | AIA Life Designers | |
| ANEP (Agence Nationale des Équipements Publics) | Other role | its director accompanied the minister's site inspection (delegated project manager; role not stated explicitly) | Aujourd'hui le Maroc |
| AIA Life Designers | Architect | with AW Mountassir | AIA Life Designers |
| AW Mountassir (AWMountassir) | Architect | AIA Life Designers | |
| AIA Ingénierie, TPFI (structure), A2MO, 8'18 | Engineer | engineering and eco-design | AIA Life Designers |
| SGTM-TGCC | General contractor | construction contract (structure), MAD 1.55bn | Barlamane |
| Jet Contractors | Contractor, one lot | fit-out (agencement) lot, won in 2024 | Challenge |
Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 5, 2022 | King Mohammed VI launches construction (48-month schedule) | TelQuel |
| October 2024 | Works about 28% complete | Le360 |
| 2026 (planned) | Opening planned in 2026 | Le360 (from the PLF 2027 regional investment note) |
| June 30, 2026 | Works 90% complete | Le360 (from the PLF 2027 regional investment note) |
About the project
The new Ibn Sina university hospital in Rabat replaces the 1954 hospital on the same 11.4 ha site. It has 1,044 beds in a 33-storey hospitalisation tower about 140 m high, a five-storey medical and technical block, an 11-storey cardiology tower, conference and training centres and a residence. The architects are AIA Life Designers and AW Mountassir. The King launched the works in May 2022; they were 90% complete at the end of June 2026, for a cost now put at MAD 7.31 billion.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Hôpitaux: les taux d'avancement de 32 projets, région par région, Le360 (from the PLF 2027 regional investment note) (press), 24 Oct 2026. Consulted 20 Nov 2026.
- Rabat: voici où en sont les travaux de construction du nouvel hôpital Ibn Sina, Le360 (press), 23 Oct 2024. Consulted 20 Nov 2026.
- Mohammed VI lance les travaux de construction du nouveau CHU Ibn Sina de Rabat, TelQuel (press), 6 May 2022. Consulted 20 Nov 2026.
- IBN SINA Hospital, Rabat - Morocco, AIA Life Designers (company), 3 Apr 2025. Consulted 20 Nov 2026.
- Santé: Les travaux de construction du nouveau CHU Ibn Sina progressent à un bon rythme, Aujourd'hui le Maroc (press), 17 Apr 2023. Consulted 20 Nov 2026.
- Rabat : La construction du nouvel hôpital Ibn Sina coûtera 1,55 MMDH, Barlamane (press), 17 Nov 2021. Consulted 23 Nov 2026.
- Jet Contractors : Mohamed Adil Rtabi, de jeune promoteur à leader du BTP alliant architecture innovante et énergie verte, Challenge (press), 26 Jan 2025. Consulted 23 Nov 2026.