Research record, fact-checked

Ibn Sina University Hospital, Rabat

Location
Rabat, Rabat-Salé-Kénitra, Morocco. See it on the map, in 3D
Stage
Under construction, as of June 2026 (Le360 (from the PLF 2027 regional investment note)). The 2027 finance bill's regional investment note puts the works at 90% at 30 June 2026, with opening planned in 2026.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Health and Social Protection
TypeHospitals
Headline amountMAD 7.31 billion (MAD), as of October 2026Le360 (from the PLF 2027 regional investment note)
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Beds1,044 bedshospitalTelQuel
Beds architect1,033 bedsarchitect's figureAIA Life Designers
Tower floors33 floors above groundhospitalisation tower, plus two lower levelsTelQuel
Tower height140 mhospitalisation towerAIA Life Designers
Medical block floors5 floorsmedical and technical block, plus three lower levelsTelQuel
Cardiology tower floors11 floorstower for the national league against cardiovascular disease, plus three lower levelsTelQuel
Floor area190,000 m2covered areaTelQuel
Site area11.4 hasiteTelQuel
Park area6.5 halandscaped parkAIA Life Designers
Parking spaces1,300 spacescar parkTelQuel
Operating rooms53 roomsarchitect's figureAIA Life Designers
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 7.31 bnTotal project costproject (PLF 2027 note)October 2026Le360 (from the PLF 2027 regional investment note)
MAD 6.53 bnTotal project costproject (PLF 2025 note)October 2024Le360
MAD 6 bnTotal project costproject at launchMay 2022TelQuel
€350 MBudgetconstruction cost excl. taxes (architect)April 2025AIA Life Designers
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Health and Social ProtectionOwnerAIA Life Designers
ANEP (Agence Nationale des Équipements Publics)Other roleits director accompanied the minister's site inspection (delegated project manager; role not stated explicitly)Aujourd'hui le Maroc
AIA Life DesignersArchitectwith AW MountassirAIA Life Designers
AW Mountassir (AWMountassir)ArchitectAIA Life Designers
AIA Ingénierie, TPFI (structure), A2MO, 8'18Engineerengineering and eco-designAIA Life Designers
SGTM-TGCCGeneral contractorconstruction contract (structure), MAD 1.55bnBarlamane
Jet ContractorsContractor, one lotfit-out (agencement) lot, won in 2024Challenge
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
May 5, 2022King Mohammed VI launches construction (48-month schedule)TelQuel
October 2024Works about 28% completeLe360
2026 (planned)Opening planned in 2026Le360 (from the PLF 2027 regional investment note)
June 30, 2026Works 90% completeLe360 (from the PLF 2027 regional investment note)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The new Ibn Sina university hospital in Rabat replaces the 1954 hospital on the same 11.4 ha site. It has 1,044 beds in a 33-storey hospitalisation tower about 140 m high, a five-storey medical and technical block, an 11-storey cardiology tower, conference and training centres and a residence. The architects are AIA Life Designers and AW Mountassir. The King launched the works in May 2022; they were 90% complete at the end of June 2026, for a cost now put at MAD 7.31 billion.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources

See it on the map. How the map is made.