Research record, fact-checked

Rabat-Salé airport: new terminal

Location
Salé (Rabat-Salé airport), Rabat-Salé-Kénitra, Morocco. See it on the map, in 3D
Stage
Under construction, as of March 2026 (Bladi.net). Bladi reported on 7 Mar 2026 that the terminal was ready but not yet open.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerONDA
TypeAirports
Headline amountEUR 171 million (EUR), as of October 2018African Development Bank
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Terminal floor area69,000 m2new terminalMCG24
Passengers a year5,000,000 passengers a yearairport after openingMCG24
Jet bridges6 bridgesnew terminalBladi.net
Car park spaces1,300 spacescar parkBladi.net
Aircraft stands23 standstarget in 2018 appraisal (17 in 2017)African Development Bank
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
€171 MTotal project costPEMARS, excl. taxes and duties (2018 appraisal)October 2018African Development Bank
€75 MLoanAfDBOctober 2018African Development Bank
€18 MLoanAFDOctober 2018African Development Bank
€128 MBudgetcomponent A: new terminal construction (2018 appraisal)October 2018African Development Bank
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
ONDAOwnerco-finances EUR 78.49MAfrican Development Bank
African Development BankLenderEUR 75MAfrican Development Bank
Agence Française de DéveloppementLenderEUR 17.51MAfrican Development Bank
SinohydroGeneral contractorwithdrew from the works consortium (2022); other members not foundMCG24
Menasteel IndustryGeneral contractormember of the Sinohydro, Menasteel Industry and Systherm grouping awarded tender 123/18/AOI, MAD 973,652,449.42 excl. VAT, MAD 1,168,382,939.30 incl. VAT, 27 monthsAfrican Development Bank
SysthermGeneral contractormember of the Sinohydro, Menasteel Industry and Systherm grouping awarded tender 123/18/AOI, MAD 1,168,382,939.30 incl. VATAfrican Development Bank
TGCC-Jet Contractors-Inter TridimBidderlosing bid, MAD 1,256,648,563.58African Development Bank
SGTMBidderlosing bid, MAD 1,326,089,148.68African Development Bank
Companies and public bodies named by a source, each with its role

Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
October 2018AfDB appraisal of PEMARSAfrican Development Bank
December 19, 2018First stone laidBladi.net (citing Hespress)
2022Sinohydro leaves the works consortium; delaysMCG24
April 10, 2026Transport minister says the terminal is 99% completeBladi.net
July 23, 2026Works reported finished; opening date not announcedBladi.net (citing Hespress)
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A new passenger terminal of about 69,000 m2 at Rabat-Salé airport, raising capacity from 1.5 to 5 million passengers a year, with six jet bridges and a 1,300-space car park. ONDA laid the first stone in December 2018, with loans from the African Development Bank and the French Development Agency. Works were delayed after Sinohydro left the contractor group in 2022. They were reported finished in July 2026; no opening date had been announced then.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.