Ratba dam
- Location
- Commune of Oudka, Taounate province, Fès-Meknès, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of October 2026 (Le360 (reporting the 2027 finance bill)). The 2027 finance bill documents, reported on 26 October 2026, give 56% physical progress and 52.5% financial progress. Works began in March 2022.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water | |
| Type | Dams and hydro | |
| Headline amount | MAD 4.5 billion (MAD), as of June 2025 | Le360 |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
| Field | Value | Scope | Source |
|---|---|---|---|
| Height | 98.4 m | dam | Le360 (citing the ministry's Maa Dialna platform) |
| Crest length | 1,340 m | dam | Le360 (citing the ministry's Maa Dialna platform) |
| Fill volume | 22 million m3 | dam | Le360 |
| Concrete face area | 26 ha | dam | Le360 |
| Concrete volume | 500,000 m3 | project | Le360 |
| Reservoir | 1,009 million m3 | project | Le360 (citing the ministry's Maa Dialna platform) |
| Reservoir | 1,900 million m3 | project | Le360 |
| Reservoir area | 2,678 ha | project | Le360 (citing the ministry's Maa Dialna platform) |
| Reservoir | 1,009 million m3 | project | Le360 (reporting the 2027 finance bill) |
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 3.27 bn | Budget | project | October 2026 | Le360 (reporting the 2027 finance bill) |
| MAD 4.37 bn | Budget | project | September 2026 | Le360 |
| MAD 4.5 bn | Total project cost | project | June 2025 | Le360 |
| MAD 4 bn | Budget | project | December 2024 | Le360 (citing the ministry's Maa Dialna platform) |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water | Owner | Figures released by the ministry | Le360 |
| SGTM (Société Générale des Travaux du Maroc) | General contractor | Its works director was quoted on site in September 2024 | Le360 |
| STAM | General contractor | dam works in a grouping with SGTM | STAM |
| Novec | Designer | execution notes and plans, technical assistance, for the DAH (Direction des Aménagements Hydrauliques) | Novec |
Milestones
| Date | Milestone | Source |
|---|---|---|
| March 2022 | Works begin | Le360 |
| September 21, 2024 | 27% overall progress; river diversion works 96% | Le360 |
| December 16, 2024 | 32% progress | Le360 (citing the ministry's Maa Dialna platform) |
| June 29, 2025 | 38% progress; about 6 million m3 of fill placed | Le360 |
| September 19, 2026 | 55% progress | Le360 |
| October 26, 2026 | 56% physical, 52.5% financial (2027 finance bill) | Le360 (reporting the 2027 finance bill) |
| December 2028 (planned) | Ready for impoundment by end 2028 (2025 statement) | Le360 |
| 2030 (planned) | Completion planned (ministry, September 2026) | Le360 |
About the project
A rockfill dam with a concrete face, about 98 m high and 1,340 m long, under construction on the Oued Aoulaï in the commune of Oudka, Taounate province, built by SGTM. Its reservoir of about 1,009 million m3 is for drinking water, irrigation, flood control and hydropower. Works began in March 2022 and were 56% complete in October 2026, with completion planned in 2030.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Sept barrages dépassent 80% de réalisation: le point sur les grands réservoirs en chantier, Le360 (press), 19 Sep 2026. Consulted 20 Nov 2026.
- Un milliard de m³ en chantier: le barrage Ratba franchit le cap des 38% de réalisation, en avance sur les délais impartis, Le360 (press), 29 Jun 2025. Consulted 20 Nov 2026.
- Province de Taounate: voici où en sont les travaux de construction du barrage Ratba, Le360 (citing the ministry's Maa Dialna platform) (press), 17 Dec 2024. Consulted 20 Nov 2026.
- Province de Taounate: les travaux de construction du barrage Ratba vont bon train, Le360 (press), 21 Sep 2024. Consulted 20 Nov 2026.
- PLF 2027: barrages, dessalement, irrigation... Les projets programmés région par région, Le360 (reporting the 2027 finance bill) (press), 26 Oct 2026. Consulted 20 Nov 2026.
- Trois grands Barrages sont en cours de construction par STAM, STAM (company). Consulted 23 Nov 2026.
- Barrage RATBA, Novec (company). Consulted 23 Nov 2026.