Research record, fact-checked
RN16 doubling, Touima to Nador West Med port
- Location
- Touima (Taouima) to the Nador West Med port, Nador province, Oriental, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of May 10, 2025 (Le360). The provincial director of Equipment said in May 2025 that works were more than 95% complete.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water (Direction provinciale de Nador) | |
| Type | Highways | |
| Headline amount | MAD 450 million (MAD), as of May 10, 2025 | Le360 |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 450 M | Total project cost | project | May 10, 2025 | Le360 |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water (Direction provinciale de Nador) | Owner | Le360 |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 10, 2025 | More than 95% complete | Le360 |
About the project
The doubling of national road RN16 over 32.3 km between Touima and the Nador West Med port, for MAD 450 million. Works added a 7.5 m carriageway, 68 drainage structures, two bridges over the Oued Oumassine and 17 rebuilt junctions. They were more than 95% complete in May 2025.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Infrastructures: le dédoublement de la route reliant Touima au port de Nador West Med pratiquement achevé, Le360 (press), 10 May 2025. Consulted 20 Nov 2026.
- Maroc - Projet autoroutier Guercif-Nador - Rapport d'évaluation de projet, African Development Bank (lender), 2023. Consulted 20 Nov 2026.