Tamri dam

Location
Agadir Ida-Outanane prefecture, 62 km north of Agadir, Souss-Massa, Morocco. See it on the map, in 3D
Stage
Under construction, as of September 2026 (Le360). Le360 gave 39.5% progress on 19 September 2026; another Le360 roundup gave 88%.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Equipment and Water
TypeDams and hydro
Headline amountMAD 2.7 billion (MAD), as of September 2024Le360
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Height75 mdam (total height)Le360
Crest length460 mdamLe360
Reservoir204 million m3projectLe360
Annual inflow63 million m3 a yearprojectLe360
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 2.3 bnBudgetprojectOctober 2026Le360 (reporting the 2027 finance bill)
MAD 2.7 bnTotal project costprojectSeptember 2024Le360
MAD 3.27 bnBudgetprojectSeptember 2026Le360
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and WaterOwnerFigures released by the ministryLe360
SomagecGeneral contractorcivil worksAujourd'hui le Maroc
CIDDesignerexecution studiesAujourd'hui le Maroc
LPEESupervisionworks controlAujourd'hui le Maroc
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
August 2022Works launchedLe360
September 29, 202452% progressLe360
March 18, 2026Close to 90% progressAgrimaroc
May 2026 (planned)Completion announced for May 2026 instead of 2029 (April 2026 report); not confirmed by a later completion statementLe360
September 19, 202639.5% in the ministry figures (conflicts with the March 2026 report)Le360
October 26, 202694% physical, 79.1% financial (2027 finance bill)Le360 (reporting the 2027 finance bill)
2029 (planned)Delivery planned in 2029 (ministry figures, September 2026); the original deadlineLe360
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

A dam 75 m high and 460 m long, 62 km north of Agadir, with a reservoir of 204 million m3 to supply drinking water to Greater Agadir, irrigate nearby land and recharge the aquifer. Works began in August 2022 and the 2027 finance bill put physical progress at 94% in October 2026.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.

Sources