Research record, fact-checked
Targa Ou Madi dam
- Location
- On the Oued Zobzit, about 74 km from Guercif (Jerada province in the ministry's list), Oriental, Morocco. See it on the map, in 3D
- Stage
- Under construction, as of September 2026 (Le360). Le360 reports 90% progress on 19 Sept 2026.
- Status
- Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 20 Nov 2026; an editor has not yet reviewed it.
- Research as of
Who, what, how much
| Field | Value | Source |
|---|---|---|
| Owner | Ministry of Equipment and Water (Direction des Aménagements Hydrauliques, DAH) | |
| Type | Dams and hydro | |
| Headline amount | MAD 1.849 billion (MAD), as of September 2026 | Le360 |
| What it covers | Total project cost. |
The works in figures
Each figure as its source states it, with its scope. Where two sources disagree, both are listed.
Cost, contracts and financing
A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| MAD 1.85 bn | Total project cost | project | September 2026 | Le360 |
Companies and their roles
| Company | Role | Note | Source |
|---|---|---|---|
| Ministry of Equipment and Water (Direction des Aménagements Hydrauliques, DAH) | Owner | DAH named as client by NOVEC | NOVEC |
| NOVEC | Engineer | Execution notes and drawings, technical assistance, site monitoring, execution geology, as-built documents, dam monitoring (auscultation) | NOVEC |
| Bioui Travaux | General contractor | dam construction contract awarded 1 April 2022, MAD 867.87M | Challenge |
| SBTX | General contractor | named as the builder in August 2024; possibly the same company as Bioui Travaux (see that entry) | Le360 |
| Houar | Bidder | losing bidder, 2022 tender won by Bioui Travaux | Challenge |
| SGTM | Bidder | losing bidder, 2022 tender won by Bioui Travaux | Challenge |
Sgtm is a client of Mirage Metrics. This page describes the project from public sources and says nothing about that work.
Milestones
| Date | Milestone | Source |
|---|---|---|
| July 31, 2026 | 90% complete, preparing for impoundment | Le360 |
| September 19, 2026 | 90% (ministry figures) | Le360 |
| 2027 (planned) | Delivery planned | Le360 |
About the project
A concrete-faced rockfill dam 116 m high with a 584 m crest on the Oued Zobzit, about 74 km from Guercif in the Oriental region. Its 287 million m3 reservoir will supply drinking water to Guercif and nearby towns, irrigate land and feed a future hydropower plant. The works were 90% complete in mid-2026, with delivery planned in 2027.
The site in 3D
The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.
Sources
- Sept barrages dépassent 80% de réalisation: le point sur les grands réservoirs en chantier, Le360 (press), 19 Sep 2026. Consulted 20 Nov 2026.
- Guercif: achevé à 90%, le barrage Targa Ou Madi se prépare à sa mise en eau, Le360 (press), 31 Jul 2026. Consulted 20 Nov 2026.
- Barrage Targa ouMadi, NOVEC (company). Consulted 20 Nov 2026.
- Bioui Travaux construira le barrage Targa Ou Madi dans la province de Guercif, Challenge (press), 1 Apr 2022. Consulted 23 Nov 2026.
- Province de Guercif: le chantier du barrage Targa Ou Madi à un taux de réalisation de 52%, Le360 (press), 11 Aug 2024. Consulted 23 Nov 2026.
- Sept barrages dépassent 80% de réalisation: le point sur les grands réservoirs en chantier, Le360 (press), 19 Sep 2026. Consulted 23 Nov 2026.