Tétouan-Chefchaouen expressway (RN2)

Location
Tétouan to Chefchaouen, Tanger-Tétouan-Al Hoceïma, Morocco. See it on the map, in 3D
Stage
Under construction, as of March 2026 (Le360). Le360, citing the ministry, lists the 53 km Tétouan-Chefchaouen expressway among the projects started in 2025.
Status
Research record, fact-checked: compiled from the sources below (the owner, the ministry, the companies, the lenders and the press), each fact checked against its source on 23 Nov 2026; an editor has not yet reviewed it.
Research as of

Who, what, how much

Sourced facts of the project
FieldValueSource
OwnerMinistry of Equipment and Water
TypeHighways
Headline amountMAD 900 million (MAD), as of January 2019Yabiladi (with MAP)
What it coversTotal project cost.
Sourced facts of the project

The works in figures

Each figure as its source states it, with its scope. Where two sources disagree, both are listed.

Physical figures, as their sources describe them
FieldValueScopeSource
Length53 kmexpressway (2025 project)Le360
LengthAbout 49 km2016-2020 dualling programmeYabiladi (with MAP)
Roundabouts4phase 3 (2019)Yabiladi (with MAP)
Physical figures, as their sources describe them

Cost, contracts and financing

A total project cost, a budget, one contract, a loan and a national programme are different objects: each is listed with what it covers, in the currency its source gives, never converted or added to another.

Amounts, each with its kind and scope
AmountWhat it isScopeAs ofSource
MAD 900 MTotal project cost2016-2020 dualling programme, about 49 kmJanuary 2019Yabiladi (with MAP)
MAD 237 MBudgetphase 3, 10.7 kmJanuary 2019Yabiladi (with MAP)
MAD 96 MBudgetphase 2, Ben Karrich to Zinat, 5.3 kmJanuary 2019Yabiladi (with MAP)
Amounts, each with its kind and scope

Companies and their roles

Companies and public bodies named by a source, each with its role
CompanyRoleNoteSource
Ministry of Equipment and WaterOwnerLe360
Companies and public bodies named by a source, each with its role

Milestones

Dated milestones, at the precision of their source; a planned date is marked as such
DateMilestoneSource
January 19, 2019Phase 1 finished, phase 2 at 75%, phase 3 (10.7 km) launchedYabiladi (with MAP)
2025Expressway listed by the ministry among the projects started in 2025Le360
Dated milestones, at the precision of their source; a planned date is marked as such

About the project

The upgrade of the RN2 national road between Tétouan and Chefchaouen to an expressway, for the Ministry of Equipment and Water. The ministry gives 53 km and counts it among the projects started in 2025. Earlier phases of dualling on the same road were built between 2016 and 2020.

The site in 3D

The site's 3D model is drawn to scale from OpenStreetMap: the works as mapped and the land, roads, water and buildings around them, with the structure drawn from its published figures and those figures on its card, each with its source. What no map or source gives is drawn as typical and listed under the model as illustrative. Open the site in 3D.