Filter Blanket, Geotextile unit price, Alabama

Low bidders on ALDOT contracts carried a median of $5.00 per SY for item 610D003, filter blanket, geotextile, over the 24 months to 28 AUG 2026, across 119 low bids. Half of all 418 bids fell between $4.13 and $7.50.

Owner
Alabama DOT
Item
610D003
Unit
SY
Latest letting
28 AUG 2026
$5.00Low bidder's median, per SY
$5.50Median of all bids, per SY
119Contracts in the window

By year of letting

Filter Blanket, Geotextile, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20227171$5.50196$5.54
20237272$5.85191$5.78
20246363$4.79220$5.00
20256666$5.20226$5.56
20262121$5.0079$5.21
Filter Blanket, Geotextile, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Filter Blanket, Geotextile, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
030113$6.1251$6.46
05028$5.0034$4.67
02026$5.0530$5.91
09018$7.2224$5.81
07018$5.1020$4.63
09024$6.4720$5.48
06015$5.3118$6.60
01055$6.5017$5.46
08043$7.5016$5.61
01043$4.0016$5.75
07024$4.5115$4.87
03023$12.0013$12.00
Filter Blanket, Geotextile, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Filter Blanket, Geotextile, ALDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
10 to 22029$6.00
228 to 60030$5.54
628 to 1,89730$5.29
1,985 to 56,43530$4.13
Filter Blanket, Geotextile, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Filter Blanket, Geotextile
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 2026202608280110402765$7.00$6.374VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
28 AUG 202620260828027070150$5.00$5.003LEWIS INCORPORATED..ALDOT
28 AUG 2026202608280300202126$5.50$6.218ROGERS GROUP, INC.ALDOT
31 JUL 2026202607310010301709$5.00$10.006IKAROS, LLCALDOT
31 JUL 20262026073101704024,337$4.27$3.884ALABAMA GRADING & EXCAVATION, LLC.ALDOT
26 JUN 2026202606260350902900$7.83$5.245WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 202620260529001060323,564$3.12$3.123APAC-ALABAMA, INC.ALDOT
29 MAY 2026202605290230301552$10.64$10.324WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
24 APR 2026202604240070604144$6.63$7.155S. A. GRAHAM COMPANY, INC.ALDOT
24 APR 2026202604240190502150$6.00$4.992IKAROS, LLCALDOT
24 APR 2026202604240440604455$3.16$3.753WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 MAR 202620260327001060614,679$2.75$2.912NEWELL & BUSH, INC.ALDOT
27 MAR 2026202603270280404521$6.36$6.033APAC-ALABAMA, INC.ALDOT
27 MAR 2026202603270440606230$5.00$4.872EAST ALABAMA PAVING COMPANY, INC.ALDOT
27 FEB 2026202602270040405150$10.00$8.654TEMPLE J ELECTRIC, LLCALDOT
Latest ALDOT contracts carrying Filter Blanket, Geotextile

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way