North American transit and bridge projects, on one map
Mirage Metrics maps 39 transit, bridge and tunnel projects in Canada and the United States, from planning to recent openings. For each one you can see who owns it, how it is delivered, which consortium builds it, what budget was announced, where it stands and what is dated next. Every fact comes from the owner, the procurement agency, a government or the companies themselves, and links to its source on the project's page.
- Published
- Updated
- Reading time
- Reference
- Written by
- Jules Toussaint
Public facts only, as the owners and companies published them, with no forecast and no judgement of any project. Last updated November 10, 2026. The data is free to reuse under CC BY 4.0.
Explore the projects
All 39 projects
This list holds the same projects as the explorer above, as text: 24 in Canada and 15 in the United States. Each name opens the project's page, with its contracts, its teams, its dated milestones and the source of every fact.
| Project | Where | Type | Stage | Owner | Delivery | Next milestone |
|---|---|---|---|---|---|---|
| Broadway Subway | Vancouver, British Columbia | Transit | Construction | Province of British Columbia, Transportation Investment Corporation | design-build-finance | 2027: Scheduled to open for passenger service in fall 2027 |
| Calgary Green Line LRT (Phase 1) | Calgary, Alberta | Transit | Construction | City of Calgary | multiple construction contracts (City-delivered) | |
| Eglinton Crosstown LRT (Line 5 Eglinton) | Toronto, Ontario | Transit | Completed | Metrolinx, Infrastructure Ontario | P3 (DBFM) | |
| Eglinton Crosstown West Extension | Toronto and Mississauga, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | mixed | March 2027: Stations, rail and systems development phase completed (anticipated in fiscal 2026-27) |
| Finch West LRT (Line 6 Finch West) | Toronto, Ontario | Transit | Completed | Metrolinx, Infrastructure Ontario | P3 (DBFM) | |
| Fraser River Tunnel (George Massey Tunnel replacement) | Richmond and Delta, British Columbia | Tunnel | Procurement | Province of British Columbia | several procurement packages | 2026: Environmental Assessment Office review expected to conclude before the end of 2026 |
| GO Expansion On-Corridor Works | Greater Toronto and Hamilton Area, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | progressive contracts | March 2027: First GO trains fitted with ETCS Level 2 equipment (planned in fiscal 2026-27) |
| Gordie Howe International Bridge | Windsor, Ontario, Canada, and Detroit, Michigan, United States | Bridge | Completed | Windsor-Detroit Bridge Authority | P3 (DBFOM) | |
| Hamilton LRT | Hamilton, Ontario | Transit | Development phase | Metrolinx | alliance | March 2027: Utility relocation enabling works completed (expected by the end of fiscal 2026-27) |
| Hazel McCallion Line (Hurontario LRT) | Mississauga and Brampton, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | P3 (DBFOM) | March 2027: Systems installation from Gateway Terminal to Cooksville, vehicle burn-in and system site integration tests completed (expected in fiscal 2026-27) |
| Île-aux-Tourtes Bridge reconstruction | Vaudreuil-Dorion and Senneville, Québec | Bridge | Construction | Ministère des Transports et de la Mobilité durable du Québec | design-build-finance | 2026: First structure scheduled to open in late 2026, with five lanes managed according to peak traffic |
| Montréal Metro Blue Line extension | Montréal, Québec | Transit | Construction | Société de transport de Montréal | ||
| New Île d'Orléans Bridge | Québec City and Île d'Orléans, Québec | Bridge | Construction | Ministère des Transports et de la Mobilité durable du Québec | design-build | |
| Ontario Line | Toronto, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | mixed | March 2027: Second pair of tunnel boring machines, for the tunnels under Pape Avenue, delivered and assembled (planned in fiscal 2026-27) |
| Ottawa O-Train Stage 2 | Ottawa, Ontario | Transit | Construction | City of Ottawa | P3 (DBF and DBFM) | 2027: West extension (Lines 1 and 3) handover to the City anticipated in Q2 2027, then preparation for passenger service in Q3 |
| Pattullo Bridge replacement (stal̕əw̓asəm Bridge) | New Westminster and Surrey, British Columbia | Bridge | Construction | Province of British Columbia, Transportation Investment Corporation | design-build | |
| QEW Garden City Skyway Bridge Twinning | St. Catharines and Niagara-on-the-Lake, Ontario | Bridge | Development phase | Ontario Ministry of Transportation, Infrastructure Ontario | progressive design-build | 2027: Construction start |
| Réseau express métropolitain (REM) | Greater Montréal, Québec | Transit | Construction | CDPQ Infra | EPC and RSSOM contracts | 2027: Airport branch to Montréal-Trudeau International Airport scheduled to open |
| Scarborough Subway Extension | Toronto, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | mixed | |
| Surrey Langley SkyTrain | Surrey and Langley, British Columbia | Transit | Construction | Province of British Columbia, Transportation Investment Corporation | mixed | |
| TramCité (Québec City tramway) | Québec City, Québec | Transit | Development phase | Gouvernement du Québec, CDPQ Infra | co-development (target price) | 2027: Target price and schedule set at the end of the planning phase |
| TRAMGO (Gatineau-Ottawa tramway) | Gatineau, Québec, and Ottawa, Ontario | Transit | Planning | Mobilité Infra Québec | November 30, 2026: Mobilité Infra Québec submits its final recommendations | |
| Valley Line West LRT | Edmonton, Alberta | Transit | Construction | City of Edmonton | design, build and partially finance | 2028: Construction anticipated to be complete, followed by testing and commissioning before opening |
| Yonge North Subway Extension | Toronto, Markham, Vaughan and Richmond Hill, Ontario | Transit | Construction | Metrolinx, Infrastructure Ontario | mixed | March 2027: Stations, rail and systems alliance partners selected and development phase begun (anticipated in fiscal 2026-27) |
| Project | Where | Type | Stage | Owner | Delivery | Next milestone |
|---|---|---|---|---|---|---|
| BART Silicon Valley Phase II | San José and Santa Clara, California | Transit | Construction | Santa Clara Valley Transportation Authority | design-build | |
| Brent Spence Bridge Corridor | Covington, Kentucky, and Cincinnati, Ohio | Bridge | Construction | Kentucky Transportation Cabinet, Ohio Department of Transportation | design-build | |
| CTA Red Line Extension | Chicago, Illinois | Transit | Development phase | Chicago Transit Authority | design-build | |
| East San Fernando Valley Light Rail Transit | Van Nuys Boulevard, San Fernando Valley, Los Angeles County, California | Transit | Construction | Los Angeles County Metropolitan Transportation Authority | ||
| Frederick Douglass Tunnel Program | Baltimore, Maryland | Tunnel | Construction | Amtrak | multiple contracts (tunnel by construction manager at-risk) | |
| Hampton Roads Bridge-Tunnel Expansion | Hampton and Norfolk, Virginia | Tunnel | Construction | Virginia Department of Transportation | design-build | |
| Hudson Tunnel Project | Under the Hudson River, between New Jersey and Manhattan, New York | Tunnel | Construction | Gateway Development Commission | ||
| I-10 Calcasieu River Bridge | Lake Charles, Louisiana | Bridge | Development phase | State of Louisiana | P3 (design-build with 50 years of operations and maintenance) | |
| Interstate Bridge Replacement Program | Vancouver, Washington, and Portland, Oregon | Bridge | Procurement | Oregon Department of Transportation, Washington State Department of Transportation | progressive design-build (bridge) | 2027: Progressive design-builder selected (mid-2027), with construction to start in 2028 |
| LA Metro D Line Subway Extension | Los Angeles, California | Transit | Construction | Los Angeles County Metropolitan Transportation Authority | ||
| Portal North Bridge | Hackensack River, New Jersey | Bridge | Construction | NJ TRANSIT, Amtrak | competitive bid (invitation for bid) | |
| Purple Line (Maryland) | Bethesda to New Carrollton, Montgomery and Prince George's counties, Maryland | Transit | Construction | Maryland Transit Administration | P3 | 2027: Opening for service, planned for winter 2027 (announcement of March 2024) |
| Second Avenue Subway Phase 2 | East Harlem, Manhattan, New York City, New York | Transit | Construction | Metropolitan Transportation Authority | multiple contracts | 2027: Tunnel boring begins |
| SR 400 Express Lanes | Fulton and Forsyth counties, metro Atlanta, Georgia | Highway | Construction | Georgia Department of Transportation, State Road and Tollway Authority | P3 | |
| West Seattle Link Extension | Seattle, Washington | Transit | Planning | Sound Transit |
Largest budgets, companies on several projects, next milestones
The tables below read the same data three ways. Budgets are compared within one currency only, and as each owner stated them (a total project cost, a capital budget or a contract value, as the basis column says). The budget lists therefore rank announcements, not final costs.
| Project | Budget | Basis | As of |
|---|---|---|---|
| Ontario Line | C$29.8 billion | Metrolinx current baseline less exclusions, in year-of-expenditure dollars; includes 30-year financing, lifecycle, operations and maintenance of the RSSOM contract and omits progressive-contract scope not yet in its implementation phase, so Metrolinx notes it is not the full project cost | June 30, 2026 |
| Scarborough Subway Extension | C$10.2 billion | Metrolinx current baseline less exclusions, in year-of-expenditure dollars | June 30, 2026 |
| Eglinton Crosstown LRT (Line 5 Eglinton) | C$9.1 billion | DBFM contract value including inflation (stated by Infrastructure Ontario as $8.25 billion, or $9.1 billion including inflation) | November 2015 |
| Fraser River Tunnel (George Massey Tunnel replacement) | C$8.5 billion | updated total project budget (federal contribution of up to $3 billion in capital costs) | July 2026 |
| Réseau express métropolitain (REM) | C$8.3 billion | total construction cost | 2026 |
| TRAMGO (Gatineau-Ottawa tramway) | C$8 billion | order-of-magnitude investment for a route of about 24 km, from an independent estimate | June 2026 |
| Montréal Metro Blue Line extension | C$7.6 billion | total cost, Québec and partner contributions, in the Plan québécois des infrastructures 2026-2036 | March 2026 |
| Calgary Green Line LRT (Phase 1) | C$6.2 billion | Phase 1 funding commitments from the City of Calgary, the Province of Alberta and the Government of Canada |
| Project | Budget | Basis | As of |
|---|---|---|---|
| Hudson Tunnel Project | US$16 billion | total commitment needed to complete the project | July 2024 |
| SR 400 Express Lanes | US$10.8 billion | approximate project value | April 2026 |
| Second Avenue Subway Phase 2 | US$7 billion | project budget | August 2025 |
| Frederick Douglass Tunnel Program | US$6 billion | approximate total program cost | February 2024 |
| Interstate Bridge Replacement Program | US$5.7 billion | available funding (state contributions, federal grants and future tolling) backing the first construction phase | August 2026 |
| CTA Red Line Extension | US$5.3 billion | overall project budget, including financing expenses | August 2024 |
| Hampton Roads Bridge-Tunnel Expansion | US$3.9 billion | total project cost | November 2026 |
| I-10 Calcasieu River Bridge | US$2.3 billion | total project value | August 2024 |
| Company | Projects | Where |
|---|---|---|
| Aecon Concessions | 5 | Eglinton Crosstown LRT (Line 5 Eglinton), Eglinton Crosstown West Extension, Finch West LRT (Line 6 Finch West), GO Expansion On-Corridor Works, Yonge North Subway Extension |
| Aecon Infrastructure Management Inc. | 5 | Eglinton Crosstown LRT (Line 5 Eglinton), Eglinton Crosstown West Extension, GO Expansion On-Corridor Works, Scarborough Subway Extension, Yonge North Subway Extension |
| Dragados Canada Inc. | 5 | Eglinton Crosstown LRT (Line 5 Eglinton), Eglinton Crosstown West Extension, Finch West LRT (Line 6 Finch West), Réseau express métropolitain (REM), Surrey Langley SkyTrain |
| Acciona Infrastructure Canada Inc. | 4 | Broadway Subway, Eglinton Crosstown West Extension, Ontario Line, Surrey Langley SkyTrain |
| Fomento de Construcciones y Contratas Canada Ltd. | 4 | GO Expansion On-Corridor Works, Ontario Line, Scarborough Subway Extension, Yonge North Subway Extension |
| ACS Infrastructure Canada Inc. | 3 | Eglinton Crosstown LRT (Line 5 Eglinton), Finch West LRT (Line 6 Finch West), Gordie Howe International Bridge |
| EXP Services Inc. | 3 | Eglinton Crosstown West Extension, Hazel McCallion Line (Hurontario LRT), Yonge North Subway Extension |
| Ghella Canada Ltd. | 3 | Broadway Subway, Eglinton Crosstown West Extension, Yonge North Subway Extension |
| WSP Canada Inc. | 3 | Eglinton Crosstown West Extension, GO Expansion On-Corridor Works, Ontario Line |
| ACCIONA | 2 | I-10 Calcasieu River Bridge, SR 400 Express Lanes |
| Aecon | 2 | GO Expansion On-Corridor Works, Gordie Howe International Bridge |
| Aecon O&M | 2 | Finch West LRT (Line 6 Finch West), GO Expansion On-Corridor Works |
| Date | Project | Milestone |
|---|---|---|
| November 30, 2026 | TRAMGO (Gatineau-Ottawa tramway) | Mobilité Infra Québec submits its final recommendations |
| January 2027 | QEW Garden City Skyway Bridge Twinning | Design phase planned to end |
About this map
The map covers the transit (subway, light rail, automated light metro, commuter rail), bridge and tunnel projects, and the major highway structures, that a large heavy civil contractor or a consortium would bid. It includes projects in planning, in procurement, in a development phase or under construction on November 10, 2026, and the ones opened since 2024. It is a working list, not a census. A project is added once its owner has published enough to describe it, and the dataset says what was left out and why.
- Owners and delivery models are named as the owner names them: P3 (DBFM), progressive design-build, alliance, design-build, design-bid-build.
- Teams and roles are the ones the award announcement gives (builder, designer, systems, operations and maintenance, equity), member by member.
- Each budget gives the amount, currency, basis and date of the owner's latest statement. Two figures for one project are not mixed.
- Milestones are dated only as precisely as the source dates them: a year, a month or a day.
Mirage Metrics builds AI agents for heavy civil estimating and preconstruction: quantities measured from each design package and tied to their drawing, changes between packages, and bid documents checked against each other. This map is published as a reference for the people who bid and build these projects, and it says nothing about any work by Mirage Metrics. Where a project's builder is one of the companies Mirage Metrics names among its clients (Skyway Bridging Partners), the project's page says so and nothing more. For the vocabulary used here, see the guides on project delivery methods, AACE estimate classes, P3 project agreements and why estimates grow between design stages.
To report an error, write to mehdi@miragemetrics.com with a public source. Corrections follow the editorial policy.
The dataset
The dataset has one row per project. Each row gives the project's name and place, type and stage, owners, delivery model, the announced budget with its basis and date, the length where an owner gives one, every contract with its team and members, the next dated milestone, the coordinates used on the map, the page on this site and the source links. The file is regenerated from the same records as these pages at each update.
Creative Commons Attribution 4.0: credit Mirage Metrics and link this page.
Questions readers ask
The facts on this map come from the owners, the procurement agencies, the governments and the companies themselves: project pages, procurement notices, award releases, budget documents and the consortium members' own announcements. Every fact on a project's page links to the document it comes from and gives that document's date. A fact found only in the press is left out.
The map is kept current project by project: each project carries the date it was last checked, and the newest is November 10, 2026. A project is re-checked when its owner announces a shortlist, an award, a financial close or an opening, and its date moves with it. Budgets are shown as the owner stated them, with the date of that statement, not as a forecast.
Yes, you can reuse the data: the whole dataset is a CSV file under the Creative Commons Attribution 4.0 licence. You can chart it and publish it, with a credit to Mirage Metrics and a link to this page.
The map describes these projects from public sources and says nothing about any work by Mirage Metrics on them. Where a project's builder is a company Mirage Metrics names among its clients, the project's page says so and nothing more. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams, and it publishes the map as a reference, not as a list of deployments.
To report an error or a missing project, write to mehdi@miragemetrics.com with the project, the fact and a public source for the correction. A verified correction is made on the project's page and its date is updated, as the editorial policy describes.