AACE estimate classes for road, rail and transit work: Class 5 to Class 1, accuracy ranges and estimate growth

AACE International classifies a cost estimate by the maturity of the project definition behind it. The scale runs from Class 5 (0% to 2% of full definition, concept screening) to Class 1 (65% to 100%, check estimate or bid). For roads, railroads and transit, its Recommended Practice 98R-18 gives each class an expected accuracy range. For Class 5, the range runs from -20% to -50% on the low side and +30% to +100% on the high side. For Class 1, it narrows to -3% to -10% and +3% to +15%. These ranges hold at about 80% confidence, once a contingency set at a 50% probability has been added, for a given scope. The range describes the estimate: it is not a contingency to add. 98R-18 ties a 30% design review to Class 3, while AACE's 2026 tunneling practice reports that it is most often read as Class 4. Either way, the deliverables decide the class. Mirage Metrics wrote this guide for the estimators who prepare these estimates on transit, bridge and highway projects.

Published
Updated
Reading time
14 min
Written by
Jules Toussaint

AACE's recommended practices are copyright. The ranges and matrices here are restated from 98R-18 (rev. August 2020), from the sample pages AACE publishes of 18R-97, 56R-08 (rev. August 2020) and 142R-26 (August 2026), and from AACE's PGD 01 (rev. August 2022). The class descriptions are paraphrased.

Who wrote this, and why. Mirage Metrics builds AI agents that read construction documents. From Class 3 down, AACE's methods move from cost per length to unit costs on measured quantities. That takeoff is where an agent helps. It structures the quantities from the plan set and keeps each one tied to its sheet, while the estimator prices, sets the contingency and decides the class. Mirage reads plan sets drawn in metric or imperial units, and documents in English or French. Mirage publishes no estimate accuracy figures. Its published takeoff proofs are John Cockerill, 80 to 90% less time on piping takeoff and a bill of materials ten times faster, and OCBM, 3 agents in production and 100% of quantities tied to a source drawing. See the takeoff and estimating workflow.

The five classes on a road, rail or transit project

What sets an estimate's class is how far the project's definition has gone. The maturity of the project definition deliverables is the only primary characteristic of a class. End use, method and accuracy are secondary, and they follow from it. The percentages are only indicative, because "it is the maturity of the defining deliverables that is the determinant, not the percent" (98R-18, section 3). The table below reads each class as 98R-18 describes it for road and rail, alongside what a transit or bridge estimating team actually has in hand.

AACE estimate classes for road, rail and transit work under 98R-18: maturity, deliverables, method, range, quantities and takeoff automation. Compiled by Mirage Metrics, November 2026
ClassDefinition and typical reviewWhat the project hasMethodAccuracy range (98R-18)Quantities that existTakeoff automation adds, and does not
Class 50% to 2%; planning, concept screeningCapacity or load factor, general concept, routing alternatives on large-scale mapsCost per length, parametric models, judgment or analogyL: -20% to -50%; H: +30% to +100%Lengths of each alternative routeLittle to measure; the unit rates come from past projects and are the estimator's call
Class 41% to 15%; feasibility, alternatives analysisPreliminary road or rail design and geometry, routing corridors, preliminary structure and system features, topographic mappingAdjusted cost per length, approximate unit or assembly costs for major structures and systemsL: -15% to -30%; H: +20% to +50%Alignment lengths, structure counts and sizes per alternativeThe same measurements on every alternative, on the same rules; not the choice between them
Class 310% to 40%; budget authorization; many owners call for a 30% design reviewCompleted road, rail and structure concept design, route confirmed by survey, right-of-way holders identified, EIS preparedSemi-detailed unit costs, assembly-level line items, detailed quantity surveyingL: -10% to -20%; H: +10% to +30%Measured quantities by assembly from the concept plansMeasured quantities, each tied to its sheet; not the unit rates, the contingency or the class
Class 230% to 75%; control or bid; many call for a 60% design reviewDetailed design well advanced, most right-of-way obtained, permits obtainedDetailed unit costs with forced detailed takeoff, often tens of thousands of line itemsL: -5% to -15%; H: +5% to +20%Line-item quantities, with forced detail where the design is missingLine-item takeoff at that scale and what changed between packages; not the forced-detail assumptions
Class 165% to 100%; check estimate or bid; some call for a 90% reviewAll maturity-matrix deliverables complete or nearly soDetailed unit costs on actual design quantitiesL: -3% to -10%; H: +3% to +15%Full design quantities, package by packageA full takeoff checked against the bid schedule; not the price
AACE estimate classes for road, rail and transit work under 98R-18: maturity, deliverables, method, range, quantities and takeoff automation. Compiled by Mirage Metrics, November 2026

Source: 98R-18: Table 1 (maturity, end use, method, range), Tables 2a to 2e (deliverables, reviews, methods), Table 3 (maturity matrix). The last two columns are Mirage Metrics' reading for takeoff.

98R-18's maturity matrix shows where bridge and transit deliverables sit at each class (98R-18, Table 3). Major structure drawings for bridges and viaducts are started or preliminary at Class 4, and complete, at concept level, at Class 3. Geometric layout (alignment, profile, cross section) is preliminary or complete at Class 3. Roadway or track discipline drawings, and signaling, telecommunication and electrification drawings, are only preliminary at Class 3 and complete at Class 1. Geotechnical and hydrology studies are preliminary at Class 4 and defined from Class 3.

98R-18 expected accuracy ranges by estimate class, from -50% to +100%Class 5Class 4Class 3Class 2Class 1-50%-25%0%+25%+50%+75%+100%
The chart shows expected accuracy ranges for road and rail estimates, drawn by Mirage Metrics from 98R-18 Table 1. The filled bar runs between the narrow bounds, and the outline between the wide bounds. The ranges hold at about 80% confidence, after contingency, for a given scope.

The range is a probability, not a contingency rule

A range tells you how far actual cost may fall from the estimate, which is not the same thing as a contingency. AACE states each range as the typical variation of actual cost from the estimate at an 80% confidence interval, after a contingency set "typically to achieve a 50% probability of project cost overrun versus underrun", for a given scope. A specific project can fall outside it. The range for a given estimate "should always be determined through risk analysis of the specific project and should never be pre-determined" (98R-18, section 3). AACE's guidance document adds that range values cannot be quoted without quantitative risk analysis (PGD 01). So adding 30% because an estimate is Class 3 confuses the range with a contingency.

Where takeoff automation changes the work

Up to Class 4, the estimate rests on cost per length and factored costs, so the work is finding comparable costs, not measuring. From Class 3, 98R-18's methods call for detailed quantity surveying and unit cost line items. At Class 2 there are often tens of thousands of them, with forced detail where the design is missing. That measuring is what an agent can take over. The rates, the contingency and the judgment of what the deliverables support stay with the estimator (see the quantity takeoff guide).

30%, 60%, 90% and IFC: which class?

Here is how the familiar design review milestones line up with the classes. 98R-18 describes Class 3 as the stage where "many call for a 30% design review". It ties Class 2 to a 60% review, and Class 1, for some, to a 90% review. It also warns that a percent design review may not match the deliverables. An estimate at a 30% review that lacks some Class 3 deliverables is "Class 3 with Exceptions", with the missing deliverables listed (98R-18, sections 4 and 5).

AACE's tunneling practice, published in August 2026, reads the same milestones differently. Where AACE classes are applied, it says, 30/60/90 reviews are "most commonly associated with Class 4/3/2", and one reference equates them with Class 3/2/1. Because there is no universal standard for those reviews, they are "an unreliable basis for stage or class delineation" (142R-26, section 3). For a tunnel, geotechnical studies cap the class, so the estimate cannot be more advanced than they support (142R-26, section 2). An issued-for-construction (IFC) set and the bid, with every package designed, are Class 1 territory. By Class 1, 98R-18 notes, all the work is usually tendered.

98R-18 leaves out the parts that drive a transit or bridge program's risk: major long-span bridges and viaducts, major tunnels, and major buildings such as rail stations. Each is a sub-project with its own class. A program is usually rated by its least defined major element, "on the principle that a system is only as strong as its weakest link" (98R-18, section 2). Stations go to 56R-08, and tunnels now to 142R-26. AACE's guide to its classification practices (rev. 2022) lists no practice for long-span bridges (PGD 01). To see at which class each delivery method fixes the price, read the project delivery methods guide.

98R-18 against 18R-97 and 56R-08

Each industry has its own AACE practice, and the ranges do not always match. 18R-97, AACE's first industry practice (process plants), gives the same five ranges as 98R-18. 56R-08, for buildings, is narrower at every class. The generic practice, 17R-97, sets out the principles and a generic matrix, and each industry practice adds its own maturity matrix and ranges (PGD 01). So a search for "AACE 18R-97" on a road or rail project lands on the right numbers but the wrong deliverables. 98R-18's maturity matrix is the one written for routes, structures and systems.

Expected accuracy ranges by class in three AACE practices, revision of August 7, 2020. Compiled by Mirage Metrics, November 2026
98R-18 road and rail18R-97 process56R-08 building and general construction
Class 5L -20% to -50%, H +30% to +100%L -20% to -50%, H +30% to +100%L -20% to -30%, H +30% to +50%
Class 4L -15% to -30%, H +20% to +50%L -15% to -30%, H +20% to +50%L -10% to -20%, H +20% to +30%
Class 3L -10% to -20%, H +10% to +30%L -10% to -20%, H +10% to +30%L -5% to -15%, H +10% to +20%
Class 2L -5% to -15%, H +5% to +20%L -5% to -15%, H +5% to +20%L -5% to -10%, H +5% to +15%
Class 1L -3% to -10%, H +3% to +15%L -3% to -10%, H +3% to +15%L -3% to -5%, H +3% to +10%
Class 5 methodCost per length, parametric, judgment or analogyCapacity factored, parametric, judgment or analogyArea factoring, parametric, judgment or analogy
CoversRoads, highways, railroads, transit rail; not major long-span bridges, major tunnels or stationsProcess plants; 98R-18 sends substations hereBuildings, stations included, and repetitive site and civil work
Expected accuracy ranges by class in three AACE practices, revision of August 7, 2020. Compiled by Mirage Metrics, November 2026

Source: 98R-18, Table 1 and section 2; 18R-97, Table 1; 56R-08, Table 1; scope of 56R-08 from PGD 01.

Canada: Class D, C, B and A

Canada's federal government uses its own estimate terms. The Treasury Board distinguishes an indicative estimate, "an order-of-magnitude estimate that is not sufficiently reliable to warrant Treasury Board approval as a cost objective", from a substantive one. A substantive estimate is "an estimate of high quality and reliability", based on detailed specifications (TBS glossary). For building projects, Public Services and Procurement Canada (PSPC) defines four classes by the documents available and the design allowance each may carry (PSPC definitions, as reproduced by the RAIC).

PSPC estimate classes and the nearest 56R-08 class by end use. Compiled by Mirage Metrics, November 2026
PSPC classBased onFormatDesign allowance, at mostNearest 56R-08 class by end use
Class D (indicative)Statement of requirements, outline of potential solutions or functional programElemental analysis20%Class 5 (functional area, concept screening)
Class CSchematic or conceptual design, or a comprehensive list of requirementsMeasured quantities, elemental analysis15%Class 4 (schematic design, concept study)
Class B (substantive)Design development drawings and outline specifications, preliminary design of all major systemsMeasured quantities, elemental analysis10%Class 3 (design development, budget authorization)
Class A (pre-tender)Completed construction drawings and specifications before tenderFully measured quantities, elemental and trade formats5%Class 1 (check estimate or pre-bid)
PSPC estimate classes and the nearest 56R-08 class by end use. Compiled by Mirage Metrics, November 2026

The last column is a reading of 56R-08's end-use terms, not an official mapping. The two systems also measure different things. A design allowance is money carried in the estimate for design still to come. An AACE range, by contrast, is a statement about how far actual cost may fall from the estimate.

US references: GAO and FHWA, and where FTA sits

In the US, GAO's Cost Estimating and Assessment Guide (GAO-20-195G, March 2020) is the federal best-practice reference for the process itself, from the technical baseline and work breakdown structure to sensitivity and risk analysis, documentation and updates. It is about how an estimate is built, whatever its class.

For a federal-aid highway project of $500 million or more, 23 U.S.C. 106(h) requires a project management plan and an annual financial plan. FHWA expects at least one Cost Estimate Review, "an unbiased risk based probabilistic review", within 12 months before the Initial Financial Plan, whose cost should reflect the 70th percentile, in year-of-expenditure dollars (FHWA financial plan guidance). A P70 figure (70th percentile) is a different statement from an AACE range around a P50 (50th percentile) estimate. Check which one a number is before you compare it.

For transit, 98R-18 makes two observations. The Federal Transit Administration (FTA) does not make its national decision at the Class 5 regional-planning gate. And the distinction between New Starts and Small Starts can imply different accuracy expectations (98R-18, sections 3 and 4). For the cost format FTA asks for, see the FTA standard cost categories guide.

Why estimates grow between classes, and what overrun studies measure

An estimate that rises from Class 4 to the bid has not necessarily missed, because growth has more than one source. AACE's ranges hold for a given scope and "explicitly exclude scope change" (98R-18, section 9; PGD 01). Scope added later is therefore growth that no range covered. Prices move too. FHWA asks for major-project costs in year-of-expenditure dollars, so escalation sits inside the figure, and 98R-18 lists escalation among the deliverables to define by Class 3 (Table 3). What is left is definition, which the class range describes.

The baseline you measure from decides the headline. In all the national systems 98R-18 compares, the first estimate reported to the public is the Class 4 one. Given its range, that confuses overrun discussions, and measuring overruns from the Class 3 estimate "would be a better basis" (98R-18, section 4). The best-known study took 258 transport projects worth $90 billion. It measured in fixed prices, from the estimate at the decision to build. Costs were underestimated in almost 9 projects in 10, and actual costs averaged 28% above estimate: 44.7% for rail, 33.8% for fixed links such as bridges and tunnels and 20.4% for roads (Flyvbjerg, Holm and Buhl, 2002). The class of that decision estimate varies between systems. Norway funds at Class 3, while other systems wait for tender prices at Class 2 (98R-18, section 4).

Why costs are underestimated is disputed. 98R-18 records the view that politicized decisions breed "strategic misrepresentation", and also research that has not supported it. Its own ranges assume a base estimate checked against empirical cost metrics, and a contingency from empirically valid risk quantification. For weak project systems and complex projects, the research it cites puts the high range at two to three times Table 1 (98R-18, section 3).

Illustrative example, invented figures: one project, two baselines

A light rail extension is announced on a Class 4 estimate of $250 million, contingency included. At its wide bounds, 98R-18's Class 4 range puts the 80% interval between $175 million (-30%) and $375 million (+50%). At its narrow bounds, the interval runs between $212.5 million (-15%) and $300 million (+20%). After the 30% design review, a Class 3 estimate gives $320 million. The project is bid and built for $340 million, with no change of scope.

Measured against the announcement, the final cost is 36% over ($340 million divided by $250 million). That sits inside the wide Class 4 band and outside the narrow one. Measured against the Class 3 estimate, it is 6.25% over ($340 million divided by $320 million), under even the narrow Class 3 high bound of +10% ($352 million). The project and the cost are the same, yet the result reads as a 36% overrun or as a result inside its budget range, depending on the baseline.

What the estimating team controls is the record, and it has two parts. The first is a basis of estimate that states the scope, the methods, the deliverables used, the assumptions and exclusions (98R-18, section 7). The second is a set of quantities that trace to the drawing revision they were measured from. With both, growth between classes can be split into design, scope and price (see plan revision comparison).

Limits of estimate classes

Five limits are worth keeping in mind before you rely on a class.

  • Percent design is not the class. The deliverables set the class (98R-18, section 4), and the 30/60/90 milestones have no universal standard (142R-26).
  • A class is not a quality specification. In AACE's words, "Class alone is not a valid contract specification for estimating services". A contract has to define the estimating requirements, processes and methods (PGD 01).
  • The range is not a contingency. It comes from the project's risk analysis and is never pre-determined (98R-18, section 3).
  • 98R-18 leaves out the big pieces. Long-span bridges, major tunnels and stations carry their own class, and the program usually takes the weakest one (98R-18, section 2).
  • Long-range plans are not Class 5. An estimate made decades ahead, whose scope will not be updated, is Unclassified or "Class 10", with no accuracy range (98R-18, section 9).

Questions readers ask

  • The AACE estimate classes are five classes, from Class 5 to Class 1, set by the maturity of the project definition deliverables behind an estimate. Class 5 rests on 0% to 2% of full definition, and Class 1 on 65% to 100%. End use, method and accuracy follow from that maturity. For road, rail and transit work, the industry practice is AACE's 98R-18. 18R-97 covers the process industries, and 56R-08 covers buildings and general construction.

  • A Class 3 estimate is the estimate that supports full budget authorization or funding and becomes the first control estimate. Under 98R-18, it rests on 10% to 40% of full project definition, a completed concept design for road, rail and structures, and semi-detailed unit costs at assembly level. Many owners call for a 30% design review at this class. Its expected range is -10% to -20% on the low side and +10% to +30% on the high side.

  • Under 98R-18, a Class 5 estimate's range is -20% to -50% on the low side and +30% to +100% on the high side, and a Class 4 estimate's is -15% to -30% and +20% to +50%. AACE states these at about 80% confidence, after a contingency set at a 50% probability of overrun, for a given scope. The range for a specific project comes from its risk analysis, not from the table.

  • A 30% design is not automatically a Class 3 estimate. 98R-18 notes that many owners call for a 30% design review at Class 3, but the class is set by the deliverables. An estimate at a 30% review that lacks some of them is a Class 3 with exceptions. AACE's 2026 tunneling practice reports that 30/60/90 reviews are most commonly read as Class 4/3/2, and it calls them an unreliable basis for class.

  • By end use, Canada's Class D, C, B and A estimates sit closest to AACE Classes 5, 4, 3 and 1, but their percentages measure something different. PSPC defines its classes for building projects by the documents available and the design allowance the estimate may carry. Class D rests on a statement of requirements (20%), Class C on schematic design (15%), Class B on design development (10%) and Class A on completed drawings before tender (5%). The allowance is money in the estimate, not an accuracy range.

Sources and scope

Checked on . All sources were read on 9 November 2026. AACE's recommended practices are copyright: the tables restate their published values and the text paraphrases them; check the latest revision at web.aacei.org before relying on a value.

This guide explains cost estimating practice for educational purposes. It does not replace the AACE recommended practices, an owner's own estimating manual or a qualified cost engineer's judgment.

Show us how your estimators take off design packages

Leave your work email, then pick a time for a 30-minute call on the design packages your estimators take off by hand, and at which class. You leave with a written plan: what an agent could prepare and what stays with your team. No commitment.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy