FTA Standard Cost Categories (SCC): a guide for transit estimators
FTA's Standard Cost Categories (SCC) are the format in which every Capital Investment Grants project reports its capital cost. There are ten categories, from 10 Guideway and Track Elements to 100 Finance Charges, with 57 numbered lines under eight of them. FTA introduced them in 2005 and requires grant sponsors to estimate in its SCC workbook, now revision 27 of April 2026. Each line carries a quantity, a base-year cost without contingency, its allocated contingency and a year-of-expenditure total, while unallocated contingency sits alone in category 90. On risk, FTA's oversight procedure sets contingency at the 65th percentile of its cost risk model. It calls prudent a total contingency that falls from 40% of the estimate at 15% design to 20% before bid. This guide by Mirage Metrics lists every line with the quantities and drawings that feed it on a light rail or subway estimate, and shows how to keep a takeoff mapped to the same lines from 30% to 90% design.
- Published
- Updated
- Reading time
- 12 min
- Written by
- Jules Toussaint
Built from FTA's own workbook, pages and oversight procedure, read on 9 November 2026 from archived copies because FTA's website refuses automated requests, and from 49 U.S.C. 5309. Not FTA guidance and not legal advice.
Who wrote this, and why. Mirage Metrics builds AI agents that read construction documents: plan sets drawn in metric or imperial units, and documents in English or French. Mirage has no published deployment on an FTA-funded project, so this page is reference material built from FTA's own documents. Its nearest published proofs are quantity work: at OCBM, three agents in production and 100% of quantities tied to a source drawing, and at John Cockerill, 80 to 90% less time on piping takeoff.
Why FTA requires the SCC, and on which projects
FTA implemented the Standard Cost Categories in 2005 "to establish a consistent format for the reporting, estimating, and managing of capital costs", and the cost data gathered that way became its Capital Cost Database (FTA, Standard Cost Categories). The workbook is project-based, not grant-based, which means it follows one project through every grant that funds it.
The requirement attaches to the Capital Investment Grants (CIG) program of 49 U.S.C. 5309, whose subsection (a) defines the project types. New Starts are new fixed guideway projects or extensions. Small Starts are projects seeking less than $150 million of CIG funds with a total estimated net capital cost under $400 million. Core Capacity projects raise the capacity of an existing fixed guideway corridor by at least 10 percent. A New Starts project in development has two years to complete the work needed for a rating (5309(d)). It then enters engineering, and a New Starts or Core Capacity project ends in a full funding grant agreement, or FFGA (5309(k)(2)). FTA publishes separate New Starts, Small Starts and Core Capacity workbooks (FTA).
FTA wants a "reasonably firm and reliable" estimate at three decision points: Entry to Engineering (for New Starts and Core Capacity), grant award and construction. Its Project Management Oversight Contractors review that estimate, and FTA states that CIG sponsors "must use" the SCC workbook (FTA, Cost Estimation).
The workbook, revision 27
Your estimate reaches FTA through one file, so it helps to know its sheets before you map a takeoff to it. The current New Starts file, SCC-New-Starts-May-2026.xlsx, carries "Rev.27, April, 2026" on its definitions and inflation sheets (SCC workbook; page updated 15 April 2026, FTA). It holds fifteen sheets: the SCC list and definitions, a crosswalk to the scopes and activity line items of FTA's grants system (TrAMS), Build Main, Inflation, the project description, the FFGA schedule and cost attachments (Schedule FFGA A4, FFGA A3T1 to A3A), annualized costs for the current and horizon years, and fund sources by category and by year.
Build Main is where the estimate lands. For every line it asks for the quantity, base-year dollars without contingency, base-year allocated contingency, the base-year total and unit cost, the line's share of construction cost and of total project cost, and the year-of-expenditure total, all in thousands. It then builds the construction subtotal (10 to 50), the subtotals 10 to 80 and 10 to 90, and the total project cost (10 to 100). It reports contingency as a share of the base, plus cost per mile. FTA locks the green cells and accepts data only in the white ones, and it asks sponsors not to add worksheets without speaking to its staff.
The categories assume design-bid-build. On a design-build project, FTA asks for construction costs in 10 to 50 and for design, administration and testing in 80, separated "to the best of your ability" (SCC Definitions, note).
Categories 10 to 100, line by line
The table gives every category and line, so you can check where an item belongs before you price it. The first three columns are FTA's. The last two show where the quantities usually come from on a light rail or subway estimate, and they are an illustration, not an FTA rule.
| Category | Lines | Unit FTA counts | Takeoff quantities that feed it (illustrative) | Drawings they come from (illustrative) |
|---|---|---|---|---|
| 10 Guideway and track elements | 10.01 to 10.03 at-grade (exclusive, semi-exclusive, mixed traffic); 10.04 aerial; 10.05 built-up fill; 10.06 cut and cover; 10.07 tunnel; 10.08 retained cut or fill; 10.09 to 10.12 track (direct fixation, embedded, ballasted, special); 10.13 vibration and noise dampening | Route miles of guideway, whatever its width | Guideway length by type; piers, caissons and deck for aerial; excavation, walls and backfill for cut and cover; tunnel length by method; track length by type; turnouts; dampened track | Plan and profile, typical sections, structural and tunnel drawings, track and special trackwork plans |
| 20 Stations, stops, terminals, intermodal | 20.01 at-grade; 20.02 aerial; 20.03 underground; 20.04 other (intermodal, ferry, trolley); 20.05 joint development; 20.06 parking structure; 20.07 elevators, escalators | Number of stations; a pair of inbound and outbound platforms is one | Station structure, enclosures and finishes; HVAC, ventilation shafts, station power, lighting, public address, fire, security and access control; elevator and escalator counts | Station architectural, structural, mechanical and electrical sets |
| 30 Support facilities | 30.01 administration; 30.02 light maintenance; 30.03 heavy maintenance; 30.04 storage or maintenance of way; 30.05 yard and yard track | None stated | Building areas, shop equipment, fueling and charging equipment, yard track and turnouts | Maintenance facility and yard drawings |
| 40 Sitework and special conditions | 40.01 demolition, clearing, earthwork; 40.02 utilities; 40.03 hazardous materials; 40.04 environmental mitigation; 40.05 retaining and sound walls; 40.06 pedestrian, bike, landscaping; 40.07 roads and parking; 40.08 temporary facilities and indirect costs | None stated | Earthwork volumes, utility relocations by type, contaminated soil, wall areas, paving, sidewalks, lighting, signage, fencing; mobilization and phasing | Civil, utility, environmental, landscape, traffic and staging drawings |
| 50 Systems | 50.01 train control and signals; 50.02 traffic signals and crossing protection; 50.03 traction power substations; 50.04 catenary and third rail; 50.05 communications; 50.06 fare collection; 50.07 central control | None stated | Signal equipment and cable, substations, overhead contact or third rail length, communications and passenger information devices, fare machines | Signal, traction power, overhead contact, communications and fare collection drawings |
| 60 Right-of-way, land, existing improvements | 60.01 purchase or lease of real estate; 60.02 relocation of households and businesses | None stated | Parcels, surface and subsurface easements, relocations | Right-of-way plans |
| 70 Vehicles | 70.01 light rail; 70.02 heavy rail; 70.03 commuter rail; 70.04 bus; 70.05 other; 70.06 non-revenue; 70.07 spare parts | Number of vehicles | Fleet by type, spares | Fleet plan, not drawings |
| 80 Professional services | 80.01 project development; 80.02 engineering; 80.03 project management; 80.04 construction administration; 80.05 insurance; 80.06 legal, permits, fees; 80.07 surveys, testing, inspection; 80.08 start-up | Applies to categories 10 to 50 | Design, management, inspection and start-up effort | Contracts and staffing plans |
| 90 Unallocated contingency | No lines | Project reserve | Risk register | |
| 100 Finance charges | No lines | Year-of-expenditure dollars | Debt costs to the later of completion or the end of the funding commitment | Financial plan |
Three rules in the definitions cut across the table. Categories 10 to 50 each include "all construction materials and labor regardless of whom is performing the work". Rough grading and excavation follow the guideway, station or facility they serve. Category 80 covers professional services for 10 to 50 only, so services for real estate and vehicles go in 60 and 70.
Base-year and year-of-expenditure dollars
The workbook counts money in two kinds of dollars, and you need to know which one each number is in. Base-year dollars are constant dollars of the year the sponsor states at the top of Build Main and the Inflation sheet, beside the year revenue operations begin. The Inflation sheet spreads each category's base-year cost across the years in which it will be spent. It applies an inflation rate for each year and the compounded factor, then returns year-of-expenditure (YOE) dollars by category and year (Inflation sheet).
This has two consequences for an estimator. First, unit prices belong in base-year dollars. Escalation is applied once, in the Inflation sheet, so a rate already escalated in the takeoff ends up escalated twice. Second, finance charges (100) are computed by year in YOE dollars from the financial plan. They count only charges paid before the later of project completion and the end of the funding commitment.
Allocated and unallocated contingency, and FTA's P65 rule
The workbook keeps the two contingencies apart. Allocated contingency is entered beside each line's base cost on Build Main. Category 90 holds unallocated contingency and project reserves, and the sheet reports allocated, unallocated and total contingency as shares of the base cost without contingency (Build Main and Definitions).
FTA's Oversight Procedure 40 sets how its oversight contractors test those numbers. Risk workshops are typically held before Entry to Engineering or before the grant agreement (Appendix G). The cost risk model starts from the SCC costs without allocated contingency. It leaves out category 90, which it would duplicate, and category 100 (Appendix I). Since July 2018 FTA has used the 65th percentile (P65) of that model to set contingency, and sponsors must provide cash funding at P65. The recommended contingency is the P65 cost less the stripped and adjusted base estimate (6.4.2). Schedule contingency is generally 125% of the remaining critical path, at least 25% (6.4.1) (OP 40, October 2023).
| Nominal stage | Minimum contingency |
|---|---|
| 15% design | 40% |
| 30% design | 33% |
| 60% design | 26% |
| 95% design (before bid) | 20% |
| 100% design (after bid, construction start) | 13% |
| 20% of construction complete | 9% |
| 50% of construction complete | 7% |
| Revenue service date | 1% |
The levels come from FTA's historic, mostly design-bid-build projects. FTA allows straight-line interpolation between stages, and it asks analysts to adjust the levels when construction is contracted before design is complete, as in design-build.
Illustrative example, invented figures: one project's minimum contingency at three submissions, in $ millions
| Submission | Estimate without contingency | Minimum contingency | Contingency | Estimate with contingency |
|---|---|---|---|---|
| 30% design | 700.0 | 33% | 231.0 | 931.0 |
| 60% design | 760.0 | 26% | 197.6 | 957.6 |
| 90% design | 790.0 | 20.9% (interpolated) | 164.8 | 954.8 |
Between 30% and 90% the base estimate grows by $90.0 million (12.9%) while the minimum contingency falls by $66.2 million. The 90% figure interpolates between 26% at 60% design and 20% at 95%: 26 minus 6 times 30/35 gives 20.86%. A base that grows faster than contingency draws down is the signal FTA's drawdown curve is built to catch.
From takeoff to SCC lines, and in sync from 30% to 90%
Map each takeoff item to exactly one SCC line by a stable item number, and keep that map from one design submission to the next. Then, when the 60% quantities arrive, you can explain every change on a line as scope, quantity, price or a move between lines, which is what an oversight review asks. For the items that sit between two categories, FTA's own definitions settle the call:
- Track at stations and yards. Station track goes in 10 and yard track in 30.05. Any other track at a support facility also goes in 10.
- Shared structures. A support facility sharing a structure with a station may be carried with the station, with a note.
- Indirect costs. Allocate them among 10 to 50 where possible. Otherwise, 40.08 takes mobilization, phasing, weather, temporary works, supervision, general conditions, overhead and profit.
- Insurance. Contractor's general liability and builder's risk go in 10 to 50, not in 80. Professional liability goes in 80.05.
- Systems against stations. Station public address and customer information sit in 20, while passenger information systems at stations and on vehicles go in 50.05. Decide once which items each covers, and write it down.
- Costs outside the workbook. Planning and environmental work done before FTA approved entry into project development is left out.
Where an AI agent helps, and where a person decides
An agent can read each submission's drawings, keep every quantity tied to its sheet, apply the map, and list what moved on each line between 30%, 60% and 90% (see plan revision comparison and the quantity takeoff guide). A person decides the boundary calls above, the unit prices, the allocated contingency on each line and the risk assumptions. For how estimate accuracy changes with design maturity, see the AACE estimate classes guide.
The Capital Cost Database
The same categories let you compare an estimate with projects already built. FTA's October 2026 update holds as-built costs for 77 federally funded projects in five modes: bus rapid transit, commuter rail, light rail, heavy rail and trolley. Costs are tracked in the SCC and validated, and the file comes as an Access database and a CSV. Keep FTA's own warning in mind: the database is for conceptual, order-of-magnitude estimates and for comparing an estimate with history, not for preparing a detailed estimate (FTA, Capital Cost Database).
Limits
- Not FTA guidance. FTA's workbook, reporting instructions and the project's oversight contractor govern a submission. This page explains them.
- Revisions move. The workbook is at revision 27, so check the revision FTA posts before each submission. The Small Starts and Core Capacity workbooks are not compared here.
- Archived reading. FTA's website refused automated requests on 9 November 2026, so its pages were read from Wayback Machine copies dated in the sources.
- Illustrative mapping. The takeoff and drawing columns describe common practice, not an FTA requirement.
- No template here. FTA asks sponsors not to alter its workbook, so a separate takeoff map belongs in the estimating system, not in a copy of FTA's file.
Questions readers ask
The FTA Standard Cost Categories are the format FTA requires for the capital cost of a Capital Investment Grants project: ten categories, from 10 Guideway and Track Elements to 100 Finance Charges, with 57 numbered lines under eight of them. FTA introduced them in 2005 so that costs are reported, estimated and managed the same way on every project. Sponsors enter them in FTA's SCC workbook, currently revision 27 of April 2026.
Allocated contingency is entered line by line beside each base-year cost on the Build Main worksheet, while unallocated contingency, including project reserves, sits alone in category 90. FTA's minimum contingency levels in Oversight Procedure 40 apply to the two together.
FTA's Oversight Procedure 40 calls a contingency of 33% prudent at nominal 30% design and 26% at 60% design (Appendix N), measured against the current estimate at completion without contingency. The level falls to 20% before bid. Since July 2018 FTA has set contingency at the 65th percentile of its cost risk model and requires sponsors to provide cash funding at that level.
The FTA Capital Cost Database holds the as-built costs of 77 federally funded bus rapid transit, commuter rail, light rail, heavy rail and trolley projects, tracked in the Standard Cost Categories and validated. FTA published its October 2026 update as an Access database and a CSV file. It says the database is for conceptual, order-of-magnitude estimates and historical comparison, not for detailed estimates.
Station tracks go in category 10, Guideway and Track Elements, not in category 20. FTA's definitions put guideway and track associated with stations in 10, and track associated with a yard in 30.05 Yard and Yard Track. Category 20 holds the station structure, finishes, building systems and vertical circulation.
Sources and scope
Checked on . Every source was read on 9 November 2026. FTA's website refused automated requests that day, so its pages, the workbook and OP 40 were read from the Wayback Machine copies named in the labels. The worked example is invented.
- FTA, New Starts SCC Workbook, SCC-New-Starts-May-2026.xlsx, Rev. 27, April 2026 (Wayback Machine copy of 12 August 2026): SCC Definitions sheet: categories 10 to 100, the 57 lines, units, inclusion rules, the design-build note, pre-PD costs excluded, category 100; Build Main columns, subtotals and contingency ratios; Inflation sheet; FFGA attachment, annualized cost, fund source and TrAMS crosswalk sheets; locked cells
- FTA, New Starts SCC Workbook page, last updated 15 April 2026 (Wayback Machine copy of 26 August 2026): worksheets for reporting the capital costs and schedules of proposed projects; the current file
- FTA, Standard Cost Categories for Capital Projects (Wayback Machine copy of 20 October 2026): SCC implemented in 2005 for a consistent format for reporting, estimating and managing capital costs; data behind the Capital Cost Database; project-based, not grant-based; separate New Starts, Small Starts and Core Capacity workbooks
- FTA, Cost Estimation for FTA Funded Transit Projects (Wayback Machine copy of 13 July 2026): reliable estimate at Entry to Engineering, grant award and construction; PMOC review; CIG sponsors must use the SCC workbook; project management plan
- FTA, Oversight Procedure 40, Risk and Contingency Review, October 2023, posted November 2024 (Wayback Machine copy of 23 August 2026): 6.4.1 schedule contingency, 125 percent of the remaining critical path; 6.4.2 P65 since July 2018, cash funding at P65, contingency as the P65 cost less the stripped and adjusted base estimate; Appendix G workshop timing; Appendix I risk model starts from SCC costs without allocated contingency, excludes 90 and 100; Appendix N minimum contingency by stage
- FTA, Capital Cost Database, October 2026 update, page last updated 13 October 2026 (Wayback Machine copy of 20 October 2026): as-built costs of 77 federally funded projects in five modes, tracked in the SCC and validated; for conceptual estimates and historical comparison, not detailed estimates
- 49 U.S.C. 5309, Fixed guideway capital investment grants (Cornell LII, read 9 November 2026): (a) definitions of core capacity improvement, new fixed guideway capital and small start projects; (d) project development within 2 years, engineering; (h) small starts; (k)(2) full funding grant agreements
This guide explains FTA's public cost reporting format for educational purposes. It is not FTA guidance or legal advice; the current workbook, FTA's instructions and the grant agreement govern each project.