Ottawa O-Train Stage 2

The second stage of Ottawa's O-Train extends two lines. The Trillium Line extension to Limebank, with an airport link, opened as Lines 2 and 4 in January 2025. The Confederation Line extensions run east to Trim and west to Algonquin and Moodie. The east extension reached substantial completion in March 2026, and the City expects the west extension's handover in Q2 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#ottawa-o-train-stage-2.

At a glance

Ottawa O-Train Stage 2 at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerCity of Ottawa
LocationOttawa, Ontario, Canada
TypeTransit, light rail
Delivery modelP3 (DBF and DBFM)
StageConstruction
Next milestone2027: West extension (Lines 1 and 3) handover to the City anticipated in Q2 2027, then preparation for passenger service in Q3OC Transpo
Ottawa O-Train Stage 2 at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Ottawa O-Train Stage 2: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Confederation Line extensions, east and westdesign-build-financeEast West ConnectorsKiewit (joint venture lead (60%)), VINCI (joint venture partner (40%))awardedApril 2019VINCI
Trillium Line extension (Lines 2 and 4)design, construct, supply, test, commission, finance and maintaincompletedCity of Ottawa
Ottawa O-Train Stage 2: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Ottawa O-Train Stage 2: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
April 30, 2019Design-build-finance contract for the Confederation Line extensions awarded to East West ConnectorsVINCI
January 6, 2025Trillium Line extension, delivered by AtkinsRéalis, opens as O-Train Lines 2 and 4, including the airport linkAtkinsRéalis
March 5, 2026Line 1 East extension, Blair to Trim, reaches substantial completionOC Transpo
Ottawa O-Train Stage 2: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy