Ottawa O-Train Stage 2
The second stage of Ottawa's O-Train extends two lines. The Trillium Line extension to Limebank, with an airport link, opened as Lines 2 and 4 in January 2025. The Confederation Line extensions run east to Trim and west to Algonquin and Moodie. The east extension reached substantial completion in March 2026, and the City expects the west extension's handover in Q2 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#ottawa-o-train-stage-2.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | City of Ottawa | |
| Location | Ottawa, Ontario, Canada | |
| Type | Transit, light rail | |
| Delivery model | P3 (DBF and DBFM) | |
| Stage | Construction | |
| Next milestone | 2027: West extension (Lines 1 and 3) handover to the City anticipated in Q2 2027, then preparation for passenger service in Q3 | OC Transpo |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Confederation Line extensions, east and west | design-build-finance | East West Connectors | Kiewit (joint venture lead (60%)), VINCI (joint venture partner (40%)) | awarded | April 2019 | VINCI |
| Trillium Line extension (Lines 2 and 4) | design, construct, supply, test, commission, finance and maintain | completed | City of Ottawa |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 30, 2019 | Design-build-finance contract for the Confederation Line extensions awarded to East West Connectors | VINCI |
| January 6, 2025 | Trillium Line extension, delivered by AtkinsRéalis, opens as O-Train Lines 2 and 4, including the airport link | AtkinsRéalis |
| March 5, 2026 | Line 1 East extension, Blair to Trim, reaches substantial completion | OC Transpo |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Sources and scope
Checked on .
- VINCI, VINCI wins contract to build extension to Confederation Line in Ottawa (April 30, 2019)
- City of Ottawa, Stage 2 Trillium Line Extension Project Agreement summary
- AtkinsRéalis, AtkinsRéalis celebrates the launch of a new era of green transit in the capital region (January 6, 2025)
- OC Transpo, Stage 2 O-Train Line East Extension Achieves Substantial Completion (March 5, 2026)
- OC Transpo, O-Train West