Pattullo Bridge replacement (stal̕əw̓asəm Bridge)
A four-lane, single-tower cable-stayed bridge of 1,235 metres now crosses the Fraser River between New Westminster and Surrey. Named stal̕əw̓asəm (Riverview), it was built by Fraser Crossing Partners under a design-build contract within a $1.637 billion project. All four lanes opened on February 14, 2026. Deconstruction of the old Pattullo Bridge is under way and is expected to take about two years. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#pattullo-bridge-replacement.
At a glance
| Field | Value | Source |
|---|---|---|
| Owners | Province of British Columbia, Transportation Investment Corporation | |
| Location | New Westminster and Surrey, British Columbia, Canada | |
| Type | Bridge, cable-stayed bridge | |
| Delivery model | design-build | |
| Budget announced | C$1.6 billion, project budget | Government of British Columbia |
| Length | 1.235 km | Government of British Columbia |
| Stage | Construction |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Design-build contract | design-build | Fraser Crossing Partners | awarded | Government of British Columbia |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 14, 2026 | All four lanes of the stal̕əw̓asəm (Riverview) Bridge open to traffic | Government of British Columbia |
| February 21, 2026 | Deconstruction of the Pattullo Bridge begins (about two years) | Government of British Columbia |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.