Pattullo Bridge replacement (stal̕əw̓asəm Bridge)

A four-lane, single-tower cable-stayed bridge of 1,235 metres now crosses the Fraser River between New Westminster and Surrey. Named stal̕əw̓asəm (Riverview), it was built by Fraser Crossing Partners under a design-build contract within a $1.637 billion project. All four lanes opened on February 14, 2026. Deconstruction of the old Pattullo Bridge is under way and is expected to take about two years. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#pattullo-bridge-replacement.

At a glance

Pattullo Bridge replacement (stal̕əw̓asəm Bridge) at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersProvince of British Columbia, Transportation Investment Corporation
LocationNew Westminster and Surrey, British Columbia, Canada
TypeBridge, cable-stayed bridge
Delivery modeldesign-build
Budget announcedC$1.6 billion, project budgetGovernment of British Columbia
Length1.235 kmGovernment of British Columbia
StageConstruction
Pattullo Bridge replacement (stal̕əw̓asəm Bridge) at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Pattullo Bridge replacement (stal̕əw̓asəm Bridge): contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Design-build contractdesign-buildFraser Crossing PartnersawardedGovernment of British Columbia
Pattullo Bridge replacement (stal̕əw̓asəm Bridge): contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Pattullo Bridge replacement (stal̕əw̓asəm Bridge): dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
February 14, 2026All four lanes of the stal̕əw̓asəm (Riverview) Bridge open to trafficGovernment of British Columbia
February 21, 2026Deconstruction of the Pattullo Bridge begins (about two years)Government of British Columbia
Pattullo Bridge replacement (stal̕əw̓asəm Bridge): dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy