Fraser River Tunnel (George Massey Tunnel replacement)
An eight-lane, toll-free immersed-tube tunnel will replace the George Massey Tunnel under the Fraser River on Highway 99. In 2026 the Province split the remaining work into several procurement packages and put the updated budget at $8.5 billion, with federal funding of up to $3 billion. It expects major construction from 2027 and completion in September 2031. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#fraser-river-tunnel.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | Province of British Columbia | |
| Location | Richmond and Delta, British Columbia, Canada | |
| Type | Tunnel, immersed-tube tunnel | |
| Delivery model | several procurement packages | |
| Budget announced | C$8.5 billion, updated total project budget (federal contribution of up to $3 billion in capital costs), as of July 2026 | Government of British Columbia |
| Stage | Procurement | |
| Next milestone | 2026: Environmental Assessment Office review expected to conclude before the end of 2026 | Government of British Columbia |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Design and Early Works Agreement | design and early works | Cross Fraser Partnership | completed | September 2024 | Government of British Columbia | |
| First two work packages | in procurement | June 16, 2026 | Government of British Columbia |
Milestones
| Date | Milestone | Source |
|---|---|---|
| September 2024 | Design and early works agreement with Cross Fraser Partnership | Government of British Columbia |
| January 2026 | Early construction work begins (tree clearing, utility relocations) | Government of British Columbia |
| June 15, 2026 | Revised procurement approach: remaining work divided into several packages | Government of British Columbia |
| June 16, 2026 | Requests for qualifications posted for the first two work packages | Government of British Columbia |
| 2027 | Proponents for the first two packages selected (expected by early 2027); major construction anticipated to begin | Government of British Columbia |
| September 2031 | Estimated completion | Government of British Columbia |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Estimating a project like this one?
Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.