Second Avenue Subway Phase 2
An extension of the Q train, about 1.5 miles long, from 96 Street to 125 Street in East Harlem, with three new accessible stations at 106, 116 and 125 Streets. It reuses a tunnel segment built in the 1970s between 110 and 120 Streets. The MTA Board approved the $1.972 billion tunneling contract with Connect Plus Partners (Halmar International and FCC Construction) in August 2025. The third contract, for the 106 Street Station structural shell, was awarded in April 2026. The project budget is $6.99 billion, and revenue service is planned for September 2032. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Updated
- Reading time
- 3 min
- Written by
- Mirage Metrics
Last checked November 10, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#second-avenue-subway-phase-2.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | Metropolitan Transportation Authority | |
| Location | East Harlem, Manhattan, New York City, New York, United States | |
| Type | Transit, subway | |
| Delivery model | multiple contracts | |
| Budget announced | US$7 billion, project budget, as of August 2025 | Office of the Governor of New York |
| Stage | Construction | |
| Next milestone | 2027: Tunnel boring begins | Office of the Governor of New York |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Contract 1: utility relocation, 105 Street to 110 Street | awarded | January 2024 | Office of the Governor of New York | |||
| Contract 2: tunneling from 116 Street to 125 Street and excavation for the future 125 Street Station | Connect Plus Partners | Halmar International (joint venture member), FCC Construction (joint venture member) | awarded | September 2025 | Office of the Governor of New York | |
| Contract 3: excavation and structural shell of 106 Street Station, tunnel connections, ancillary buildings and entrances | awarded | April 2026 | Office of the Governor of New York |
Milestones
| Date | Milestone | Source |
|---|---|---|
| January 2024 | Contract 1 (utility relocation) awarded | Office of the Governor of New York |
| August 2025 | MTA Board approves the $1.972 billion tunneling contract with Connect Plus Partners | Office of the Governor of New York |
| April 2026 | Contract 3 (106 Street Station structural shell) awarded | Office of the Governor of New York |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.