Second Avenue Subway Phase 2

An extension of the Q train, about 1.5 miles long, from 96 Street to 125 Street in East Harlem, with three new accessible stations at 106, 116 and 125 Streets. It reuses a tunnel segment built in the 1970s between 110 and 120 Streets. The MTA Board approved the $1.972 billion tunneling contract with Connect Plus Partners (Halmar International and FCC Construction) in August 2025. The third contract, for the 106 Street Station structural shell, was awarded in April 2026. The project budget is $6.99 billion, and revenue service is planned for September 2032. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Updated
Reading time
3 min
Written by
Mirage Metrics

Last checked November 10, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#second-avenue-subway-phase-2.

At a glance

Second Avenue Subway Phase 2 at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerMetropolitan Transportation Authority
LocationEast Harlem, Manhattan, New York City, New York, United States
TypeTransit, subway
Delivery modelmultiple contracts
Budget announcedUS$7 billion, project budget, as of August 2025Office of the Governor of New York
StageConstruction
Next milestone2027: Tunnel boring beginsOffice of the Governor of New York
Second Avenue Subway Phase 2 at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Second Avenue Subway Phase 2: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Contract 1: utility relocation, 105 Street to 110 StreetawardedJanuary 2024Office of the Governor of New York
Contract 2: tunneling from 116 Street to 125 Street and excavation for the future 125 Street StationConnect Plus PartnersHalmar International (joint venture member), FCC Construction (joint venture member)awardedSeptember 2025Office of the Governor of New York
Contract 3: excavation and structural shell of 106 Street Station, tunnel connections, ancillary buildings and entrancesawardedApril 2026Office of the Governor of New York
Second Avenue Subway Phase 2: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Second Avenue Subway Phase 2: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
January 2024Contract 1 (utility relocation) awardedOffice of the Governor of New York
August 2025MTA Board approves the $1.972 billion tunneling contract with Connect Plus PartnersOffice of the Governor of New York
April 2026Contract 3 (106 Street Station structural shell) awardedOffice of the Governor of New York
Second Avenue Subway Phase 2: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy