Montréal Metro Blue Line extension
An extension of Montréal's metro Blue Line nearly 6 kilometres east from Saint-Michel station to Anjou, with five new stations, owned by the STM. The main tunnel and underground structures contract was signed with Mobilité Bleu Horizon (Pomerleau, EBC and Spie batignolles) in 2024, and Québec's 2026-2036 infrastructure plan puts the total cost at $7.58 billion. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#montreal-metro-blue-line-extension.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | Société de transport de Montréal | |
| Location | Montréal, Québec, Canada | |
| Type | Transit, subway | |
| Budget announced | C$7.6 billion, total cost, Québec and partner contributions, in the Plan québécois des infrastructures 2026-2036, as of March 2026 | Gouvernement du Québec |
| Length | 6 km | Pomerleau |
| Stage | Construction |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Train control system (CBTC), with maintenance | Ground Transportation Systems Canada inc. | awarded | February 2024 | STM | ||
| Main contract: tunnel and excavation of underground structures | Mobilité Bleu Horizon | Pomerleau (equal partner), EBC (equal partner), Spie batignolles (equal partner) | awarded | August 2024 | Pomerleau |
Milestones
| Date | Milestone | Source |
|---|---|---|
| February 2024 | Train control system contract awarded to Ground Transportation Systems Canada inc. ($217,173,941 in total) | STM |
| August 23, 2024 | Mobilité Bleu Horizon signs the main tunnel and underground structures contract | Pomerleau |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Sources and scope
Checked on .
- Gouvernement du Québec, Plan québécois des infrastructures 2026-2036 (Budget de dépenses 2026-2027, vol. 6) (March 2026)
- Pomerleau, Mobilité Bleu Horizon consortium undertakes Montréal's metro Blue Line extension project (August 23, 2024)
- STM, Le contrat entourant le système de contrôle des trains est adjugé (February 2024)
Estimating a project like this one?
Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.