Ontario Line

A 15.6-kilometre, 15-station subway from Exhibition station to Don Valley station on the Eglinton Crosstown, built through four main contracts procured by Metrolinx and Infrastructure Ontario. All four are under contract, and tunnelling under downtown Toronto began in 2026. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
4 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#ontario-line.

At a glance

Ontario Line at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersMetrolinx, Infrastructure Ontario
LocationToronto, Ontario, Canada
TypeTransit, subway
Delivery modelmixed
Budget announcedC$29.8 billion, Metrolinx current baseline less exclusions, in year-of-expenditure dollars; includes 30-year financing, lifecycle, operations and maintenance of the RSSOM contract and omits progressive-contract scope not yet in its implementation phase, so Metrolinx notes it is not the full project cost, as of June 30, 2026Metrolinx
Length15.6 kmMetrolinx
StageConstruction
Next milestoneMarch 2027: Second pair of tunnel boring machines, for the tunnels under Pape Avenue, delivered and assembled (planned in fiscal 2026-27)Metrolinx
Ontario Line at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Ontario Line: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Southern Civil, Stations and Tunneldesign, build and financeOntario Transit GroupFerrovial Construction Canada Inc. (applicant lead, construction team), VINCI Construction Grands Projets (applicant lead), Janin Atlas Inc. (construction team), AECOM Canada Ltd. (design team), COWI North America Ltd. (design team), GHD Limited (design team), SENER Group (design team), Agentis Capital (financial advisor)awardedNovember 9, 2022Infrastructure Ontario
Rolling Stock, Systems, Operations and Maintenance (RSSOM)P3 (design, build, finance, operate and maintain, 30-year term)Connect 6ixPlenary Americas (applicant lead), Hitachi Rail (applicant lead, design team, construction team, operations, maintenance and rehabilitation team), Webuild Group (applicant lead, construction team), Transdev Canada Inc. (applicant lead, operations, maintenance and rehabilitation team), IBI Group Professional Services (Canada) Inc. (design team), NGE Contracting Inc. (construction team), National Bank Financial Inc. (financial advisor), Sumitomo Mitsui Banking Corporation (financial advisor)awardedNovember 17, 2022Infrastructure Ontario
Pape Tunnel and Underground Stations ($4.32 billion target price agreement)progressive design-buildPape North ConnectWebuild Civil Work Inc., Fomento de Construcciones y Contratas Canada Ltd., Arcadis Professional Services (Canada) Inc., AECOM Canada Ltd.awardedAugust 2026Infrastructure Ontario
Elevated Guideway and Stationsprogressive design-buildTrillium Guideway PartnersAcciona Infrastructure Canada Inc. (applicant lead, construction team), Amico Major Projects Inc. (applicant lead, construction team), WSP Canada Inc. (design team)awardedFebruary 20, 2024Infrastructure Ontario
Ontario Line: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Ontario Line: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
November 9, 2022Southern Civil, Stations and Tunnel contract awarded to Ontario Transit Group ($6 billion, of which $5.5 billion capital)Infrastructure Ontario
November 17, 2022RSSOM contract awarded to Connect 6ix ($9 billion, of which $2.3 billion capital, 30-year term)Infrastructure Ontario
January 2024Pape Tunnel and Underground Stations: Pape North Connect selected as development partnerInfrastructure Ontario
February 20, 2024Elevated Guideway and Stations: development and master construction agreement signed with Trillium Guideway PartnersInfrastructure Ontario
April 2026First tunnel boring machine launched at Exhibition station, starting tunnelling on the southern section (late April 2026)Metrolinx
August 1, 2026Pape Tunnel and Underground Stations: target price achieved with Pape North ConnectMetrolinx
Ontario Line: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy