Yonge North Subway Extension

An extension of TTC Line 1 about 7.4 kilometres north from Finch station to Richmond Hill, with five new stations. The $1.4 billion advance tunnel contract was awarded in August 2025, and proposals for the stations, rail and systems alliance closed in August 2026. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
3 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#yonge-north-subway-extension.

At a glance

Yonge North Subway Extension at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersMetrolinx, Infrastructure Ontario
LocationToronto, Markham, Vaughan and Richmond Hill, Ontario, Canada
TypeTransit, subway
Delivery modelmixed
Budget announcedC$5.7 billion, Metrolinx current baseline less exclusions, in year-of-expenditure dollars; omits large contracts awaiting procurement or award, so Metrolinx notes it is not the full project cost, as of June 30, 2026Metrolinx
Length7.4 kmMetrolinx
StageConstruction
Next milestoneMarch 2027: Stations, rail and systems alliance partners selected and development phase begun (anticipated in fiscal 2026-27)Metrolinx
Yonge North Subway Extension at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Yonge North Subway Extension: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Advance Tunneldesign-build-finance (P3)North End ConnectorsAecon Infrastructure Management Inc. (applicant lead, construction), Fomento de Construcciones y Contratas Canada Ltd. (applicant lead, construction, financial advisor), Ghella Canada Ltd. (applicant lead, construction), EXP Services Inc. (design), TYPSA Inc. (design), National Bank Financial (financial advisor), Aecon Concessions (financial advisor), Ghella Investments & Partnerships SpA (financial advisor)awardedAugust 6, 2025Infrastructure Ontario
Stations, Rail and Systemsprogressive alliancein procurementInfrastructure Ontario
Yonge North Subway Extension: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Yonge North Subway Extension: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
August 6, 2025$1.4 billion fixed-price advance tunnel contract awarded to North End ConnectorsInfrastructure Ontario
October 16, 2025Stations, Rail and Systems: request for qualifications issuedInfrastructure Ontario
May 28, 2026Stations, Rail and Systems: request for proposals issuedInfrastructure Ontario
August 28, 2026Stations, Rail and Systems: request for proposals closedInfrastructure Ontario
Yonge North Subway Extension: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy