A 19-kilometre light rail line with 25 stations and stops across midtown Toronto, from Mount Dennis station to Kennedy station, built and maintained under a DBFM contract with Crosslinx Transit Solutions. It reached substantial completion in December 2025 and opened as TTC Line 5 Eglinton in February 2026. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
3 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#eglinton-crosstown-lrt.

At a glance

Eglinton Crosstown LRT (Line 5 Eglinton) at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersMetrolinx, Infrastructure Ontario
LocationToronto, Ontario, Canada
TypeTransit, light rail
Delivery modelP3 (DBFM)
Budget announcedC$9.1 billion, DBFM contract value including inflation (stated by Infrastructure Ontario as $8.25 billion, or $9.1 billion including inflation), as of November 2015Infrastructure Ontario
Length19 kmMetrolinx
StageCompleted
Eglinton Crosstown LRT (Line 5 Eglinton) at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Eglinton Crosstown LRT (Line 5 Eglinton): contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Eglinton Crosstown LRT project agreementDBFM (design, build, finance and maintain)Crosslinx Transit SolutionsACS Infrastructure Canada Inc. (developer, maintenance and rehabilitation), Aecon Concessions (developer), EllisDon Capital Inc. (developer), SNC-Lavalin Capital Inc. (developer), Aecon Infrastructure Management Inc. (design and construction), Dragados Canada Inc. (design and construction), EllisDon Civil Ltd. (design and construction), SNC-Lavalin Constructors (Pacific) Inc. (design and construction), SNC-Lavalin Inc. (design and construction), IBI Group Inc. (design and construction), NORR Limited (design and construction), Adamson Associates Architects (design and construction), Urban Strategies Inc. (design and construction), Dialog Ontario Inc. (design and construction), Sereca Fire Consulting Ltd. (design and construction), Thurber Engineering Ltd. (design and construction), Dr G Sauer & Partners (design and construction), Daoust Lestage Inc. (design and construction), SNC-Lavalin Operations & Maintenance Inc. (maintenance and rehabilitation), EllisDon Facilities Services Inc. (maintenance and rehabilitation), Aecon Buildings (maintenance and rehabilitation), Bombardier Transportation Canada Inc. (maintenance and rehabilitation), National Bank Financial (financial advisor), Bank of Nova Scotia (financial advisor)completedNovember 3, 2015Infrastructure Ontario
Eglinton Crosstown LRT (Line 5 Eglinton): contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Eglinton Crosstown LRT (Line 5 Eglinton): dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
January 22, 2013Request for qualifications issuedInfrastructure Ontario
June 9, 2015Crosslinx Transit Solutions selected as preferred proponentInfrastructure Ontario
November 3, 2015DBFM contract awarded to Crosslinx Transit SolutionsInfrastructure Ontario
March 3, 2016Construction beginsInfrastructure Ontario
December 5, 2025Substantial completionInfrastructure Ontario
February 8, 2026Line 5 Eglinton opens to riders, operated by the TTCTTC
Eglinton Crosstown LRT (Line 5 Eglinton): dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy