Eglinton Crosstown West Extension
A 9.2-kilometre westward extension of Line 5 Eglinton from Mount Dennis station to Renforth Drive in Mississauga, with seven stations. The twin main tunnels reached substantial completion in June 2025, and the stations, rail and systems contract entered its development phase in August 2025. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 3 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#eglinton-crosstown-west-extension.
At a glance
| Field | Value | Source |
|---|---|---|
| Owners | Metrolinx, Infrastructure Ontario | |
| Location | Toronto and Mississauga, Ontario, Canada | |
| Type | Transit, light rail | |
| Delivery model | mixed | |
| Budget announced | C$4 billion, Metrolinx current baseline less exclusions, in year-of-expenditure dollars; omits progressive-contract scope not yet in its implementation phase, so Metrolinx notes it is not the full project cost, as of June 30, 2026 | Metrolinx |
| Length | 9.2 km | Infrastructure Ontario |
| Stage | Construction | |
| Next milestone | March 2027: Stations, rail and systems development phase completed (anticipated in fiscal 2026-27) | Metrolinx |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Advance Tunnel | P3 (design, build and finance) | West End Connectors | Aecon Infrastructure Management Inc. (developer, construction), Dragados Canada Inc. (developer, construction), Ghella Canada Ltd. (developer, construction), TYPSA Inc. (design), EXP Services Inc. (design), ACS Infrastructure Canada (financial), Aecon Concessions (financial), Scotiabank Capital (financial), Ghella Investments & Partnerships (financial) | completed | May 20, 2021 | Infrastructure Ontario |
| Elevated Guideway | design-build | Aecon Infrastructure Management Inc. | awarded | December 15, 2023 | Metrolinx | |
| Advance Tunnel 2 | P3 (design, build and finance) | STRABAG Inc. (developer, construction, financial advisor), WSP Canada Inc. (design), Dr. G. Sauer & Partners Corporation (design) | awarded | February 16, 2024 | Infrastructure Ontario | |
| Stations, Rail and Systems | progressive design-build | Trillium Rail Partners | Amico Major Projects Inc. (applicant lead, construction), Alberici Constructors, Ltd. (applicant lead, construction), Acciona Infrastructure Canada Inc. (applicant lead, construction), WSP Canada Inc. (design team) | awarded | August 2025 | Infrastructure Ontario |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 20, 2021 | $729.2 million fixed-price advance tunnel contract awarded to West End Connectors | Infrastructure Ontario |
| December 15, 2023 | Elevated guideway design and build contract awarded to Aecon Infrastructure Management Inc. | Metrolinx |
| February 16, 2024 | $255 million fixed-price Advance Tunnel 2 contract awarded to STRABAG Inc. | Infrastructure Ontario |
| June 30, 2025 | Advance tunnel contract reaches substantial completion (two 6.3-kilometre tunnels, Scarlett Road to Renforth Drive) | Infrastructure Ontario |
| August 2025 | Stations, rail and systems development and master construction agreement signed with Trillium Rail Partners | Infrastructure Ontario |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
- Yonge North Subway Extension
- Eglinton Crosstown LRT (Line 5 Eglinton)
- GO Expansion On-Corridor Works
- Ontario Line
- Finch West LRT (Line 6 Finch West)
- Broadway Subway
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Sources and scope
Checked on .
- Infrastructure Ontario, Substantial Completion Reached for Eglinton Crosstown West Extension Advance Tunnel Contract (June 30, 2025)
- Infrastructure Ontario, Contract Awarded for Eglinton Crosstown West Extension Advance Tunnel Project (May 20, 2021)
- Infrastructure Ontario, Contract Awarded for Eglinton Crosstown West Extension Advance Tunnel 2 (February 16, 2024)
- Metrolinx, Contract awarded for Eglinton Crosstown West Extension guideway (December 15, 2023)
- Infrastructure Ontario, Agreement Signed for Eglinton Crosstown West Extension Stations, Rail and Systems (August 28, 2025)
- Metrolinx, 2026-27 Business Plan (section 7.4)
- Metrolinx, CPG (Rapid Transit) State of the Network, FY 2026/27 Q1 (Board of Directors, item 8.2) (September 10, 2026)