Finch West LRT (Line 6 Finch West)
An 11-kilometre light rail line along Finch Avenue West between Finch West station on Line 1 and Humber Polytechnic's North Campus, built and maintained under a $2.5 billion DBFM contract with Mosaic Transit Group. Construction ended in November 2025 and the line opened as TTC Line 6 Finch West on December 7, 2025. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#finch-west-lrt.
At a glance
| Field | Value | Source |
|---|---|---|
| Owners | Metrolinx, Infrastructure Ontario | |
| Location | Toronto, Ontario, Canada | |
| Type | Transit, light rail | |
| Delivery model | P3 (DBFM) | |
| Budget announced | C$2.5 billion, DBFM contract value, as of May 2018 | Infrastructure Ontario |
| Length | 11 km | Infrastructure Ontario |
| Stage | Completed |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Finch West LRT project agreement | DBFM (design, build, finance and maintain) | Mosaic Transit Group | ACS Infrastructure Canada Inc. (lead, maintenance), Aecon Concessions (lead), CRH Canada Group Inc. (lead), Aecon Infrastructure and Management Inc. (construction), Dragados Canada Inc. (construction), Dufferin Construction Company (construction), Arup Canada Inc. (design), Dillon Consulting Limited (design), DPM Energy Inc. (design), DTAH (design), Perkins + Will Canada Inc. (design), Sener SES Canada Inc. (design), Aecon O&M (maintenance), RBC Dominion Securities Inc. (financial advisor) | completed | May 7, 2018 | Infrastructure Ontario |
Milestones
| Date | Milestone | Source |
|---|---|---|
| September 8, 2015 | Request for qualifications issued | Infrastructure Ontario |
| April 12, 2018 | Mosaic Transit Group selected as preferred proponent | Infrastructure Ontario |
| May 7, 2018 | Contract awarded and financial close; construction starts | Infrastructure Ontario |
| November 12, 2025 | Construction ends | Infrastructure Ontario |
| December 7, 2025 | Line 6 Finch West opens to customers, operated by the TTC | TTC |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
- Eglinton Crosstown LRT (Line 5 Eglinton)
- Eglinton Crosstown West Extension
- GO Expansion On-Corridor Works
- Yonge North Subway Extension
- Gordie Howe International Bridge
- Réseau express métropolitain (REM)
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.