Finch West LRT (Line 6 Finch West)

An 11-kilometre light rail line along Finch Avenue West between Finch West station on Line 1 and Humber Polytechnic's North Campus, built and maintained under a $2.5 billion DBFM contract with Mosaic Transit Group. Construction ended in November 2025 and the line opened as TTC Line 6 Finch West on December 7, 2025. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#finch-west-lrt.

At a glance

Finch West LRT (Line 6 Finch West) at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersMetrolinx, Infrastructure Ontario
LocationToronto, Ontario, Canada
TypeTransit, light rail
Delivery modelP3 (DBFM)
Budget announcedC$2.5 billion, DBFM contract value, as of May 2018Infrastructure Ontario
Length11 kmInfrastructure Ontario
StageCompleted
Finch West LRT (Line 6 Finch West) at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Finch West LRT (Line 6 Finch West): contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Finch West LRT project agreementDBFM (design, build, finance and maintain)Mosaic Transit GroupACS Infrastructure Canada Inc. (lead, maintenance), Aecon Concessions (lead), CRH Canada Group Inc. (lead), Aecon Infrastructure and Management Inc. (construction), Dragados Canada Inc. (construction), Dufferin Construction Company (construction), Arup Canada Inc. (design), Dillon Consulting Limited (design), DPM Energy Inc. (design), DTAH (design), Perkins + Will Canada Inc. (design), Sener SES Canada Inc. (design), Aecon O&M (maintenance), RBC Dominion Securities Inc. (financial advisor)completedMay 7, 2018Infrastructure Ontario
Finch West LRT (Line 6 Finch West): contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Finch West LRT (Line 6 Finch West): dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
September 8, 2015Request for qualifications issuedInfrastructure Ontario
April 12, 2018Mosaic Transit Group selected as preferred proponentInfrastructure Ontario
May 7, 2018Contract awarded and financial close; construction startsInfrastructure Ontario
November 12, 2025Construction endsInfrastructure Ontario
December 7, 2025Line 6 Finch West opens to customers, operated by the TTCTTC
Finch West LRT (Line 6 Finch West): dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy