Réseau express métropolitain (REM)

A 67-kilometre automated light metro with 26 stations across Greater Montréal, owned by CDPQ Infra and built under an EPC contract with NouvLR, with rolling stock, systems and operations by Pulsar. Three branches opened between July 2023 and May 2026, and the airport branch is scheduled for 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#reseau-express-metropolitain.

At a glance

Réseau express métropolitain (REM) at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerCDPQ Infra
LocationGreater Montréal, Québec, Canada
TypeTransit, automated light metro
Delivery modelEPC and RSSOM contracts
Budget announcedC$8.3 billion, total construction cost, as of 2026CDPQ Infra
Length67 kmCDPQ Infra
StageConstruction
Next milestone2027: Airport branch to Montréal-Trudeau International Airport scheduled to openCDPQ Infra
Réseau express métropolitain (REM) at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Réseau express métropolitain (REM): contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Infrastructure engineering, procurement and construction (EPC)engineering, procurement and constructionNouvLRSNC Lavalin Grands Projets Inc. (member), Dragados Canada Inc. (member), Groupe Aecon Québec Ltée (member), Pomerleau Inc. (member), EBC Inc. (member), SNC Lavalin Inc. (participant), Aecom Consultants Inc. (participant)awardedFebruary 8, 2018CDPQ Infra
Rolling stock, systems, operation and maintenance (RSSOM)rolling stock, systems, operation and maintenanceGroupe des Partenaires pour la Mobilité des Montréalais (now Pulsar)Alstom Transport Canada Inc. (member), SNC-Lavalin O&M Inc. (member)awardedFebruary 8, 2018CDPQ Infra
Réseau express métropolitain (REM): contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Réseau express métropolitain (REM): dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
February 8, 2018Winning consortia announced: NouvLR for the EPC contract, PMM for rolling stock, systems, operation and maintenanceCDPQ Infra
July 2023South Shore branch opens, Brossard to Gare CentraleCDPQ Infra
November 2025Deux-Montagnes branch opens, Gare Centrale to Deux-MontagnesCDPQ Infra
May 2026Anse-à-l'Orme branch opens, Bois-Franc to Anse-à-l'OrmeCDPQ Infra
Réseau express métropolitain (REM): dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy