Scarborough Subway Extension

A 7.8-kilometre, three-stop extension of TTC Line 2 from Kennedy station to Sheppard Avenue East, delivered as an advance tunnel contract and a progressive design-build stations, rail and systems contract. Tunnelling began in January 2023 and had passed 75% by June 2026, with major station construction under way since 2025. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#scarborough-subway-extension.

At a glance

Scarborough Subway Extension at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnersMetrolinx, Infrastructure Ontario
LocationToronto, Ontario, Canada
TypeTransit, subway
Delivery modelmixed
Budget announcedC$10.2 billion, Metrolinx current baseline less exclusions, in year-of-expenditure dollars, as of June 30, 2026Metrolinx
Length7.8 kmMetrolinx
StageConstruction
Scarborough Subway Extension at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Scarborough Subway Extension: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Advance TunnelStrabagawardedMay 2021Metrolinx
Stations, Rail and Systemsprogressive design-buildScarborough Transit ConnectAecon Infrastructure Management Inc. (applicant lead, construction team), Fomento de Construcciones y Contratas Canada Ltd. (applicant lead, construction team), Sener (design team)awardedJanuary 28, 2025Infrastructure Ontario
Scarborough Subway Extension: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Scarborough Subway Extension: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
May 2021Advance tunnel contract finalized with StrabagMetrolinx
November 2022Scarborough Transit Connect selected for the stations, rail and systems development phaseInfrastructure Ontario
January 2023Tunnelling beginsMetrolinx
January 28, 2025$5.7 billion target price agreement signed for stations, rail and systemsInfrastructure Ontario
September 2025Major construction begins at Scarborough Centre stationMetrolinx
June 30, 2026Tunnel excavation passes 75% (5,229 metres) as the tunnel boring machine advances toward the extraction shaftMetrolinx
Scarborough Subway Extension: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy