Scarborough Subway Extension
A 7.8-kilometre, three-stop extension of TTC Line 2 from Kennedy station to Sheppard Avenue East, delivered as an advance tunnel contract and a progressive design-build stations, rail and systems contract. Tunnelling began in January 2023 and had passed 75% by June 2026, with major station construction under way since 2025. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#scarborough-subway-extension.
At a glance
| Field | Value | Source |
|---|---|---|
| Owners | Metrolinx, Infrastructure Ontario | |
| Location | Toronto, Ontario, Canada | |
| Type | Transit, subway | |
| Delivery model | mixed | |
| Budget announced | C$10.2 billion, Metrolinx current baseline less exclusions, in year-of-expenditure dollars, as of June 30, 2026 | Metrolinx |
| Length | 7.8 km | Metrolinx |
| Stage | Construction |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| Advance Tunnel | Strabag | awarded | May 2021 | Metrolinx | ||
| Stations, Rail and Systems | progressive design-build | Scarborough Transit Connect | Aecon Infrastructure Management Inc. (applicant lead, construction team), Fomento de Construcciones y Contratas Canada Ltd. (applicant lead, construction team), Sener (design team) | awarded | January 28, 2025 | Infrastructure Ontario |
Milestones
| Date | Milestone | Source |
|---|---|---|
| May 2021 | Advance tunnel contract finalized with Strabag | Metrolinx |
| November 2022 | Scarborough Transit Connect selected for the stations, rail and systems development phase | Infrastructure Ontario |
| January 2023 | Tunnelling begins | Metrolinx |
| January 28, 2025 | $5.7 billion target price agreement signed for stations, rail and systems | Infrastructure Ontario |
| September 2025 | Major construction begins at Scarborough Centre station | Metrolinx |
| June 30, 2026 | Tunnel excavation passes 75% (5,229 metres) as the tunnel boring machine advances toward the extraction shaft | Metrolinx |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
- GO Expansion On-Corridor Works
- Yonge North Subway Extension
- Eglinton Crosstown LRT (Line 5 Eglinton)
- Eglinton Crosstown West Extension
- Ontario Line
- Finch West LRT (Line 6 Finch West)
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Sources and scope
Checked on .
- Metrolinx, Scarborough Subway Extension project page
- Metrolinx, Tunnel contract finalized for Scarborough Subway Extension (May 25, 2021)
- Infrastructure Ontario, Contract Awarded for the Scarborough Subway Extension Stations, Rail and Systems Project (January 28, 2025)
- Metrolinx, CPG (Rapid Transit) State of the Network, FY 2026/27 Q1 (Board of Directors, item 8.2) (September 10, 2026)
Estimating a project like this one?
Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.