Purple Line (Maryland)

A 16-mile light rail line with 21 stations between Bethesda and New Carrollton, in Montgomery and Prince George's counties, with connections to Metrorail, Amtrak, MARC and bus networks. The Maryland Transit Administration is delivering it as a public-private partnership with Purple Line Transit Partners. The owner's site showed construction 92% complete when read in November 2026, and the opening date announced in March 2024 is winter 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#purple-line-maryland.

At a glance

Purple Line (Maryland) at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerMaryland Transit Administration
LocationBethesda to New Carrollton, Montgomery and Prince George's counties, Maryland, United States
TypeTransit, light rail
Delivery modelP3
Length25.7 kmMaryland Transit Administration
StageConstruction
Next milestone2027: Opening for service, planned for winter 2027 (announcement of March 2024)Maryland Transit Administration and Purple Line Transit Partners announce updated opening date for light rail line
Purple Line (Maryland) at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Purple Line (Maryland): contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Purple Line public-private partnershipP3Purple Line Transit PartnersawardedMaryland Transit Administration and Purple Line Transit Partners announce updated opening date for light rail line
Purple Line (Maryland): contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Purple Line (Maryland): dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
March 1, 2024MTA and Purple Line Transit Partners announce an updated opening date of winter 2027Maryland Transit Administration and Purple Line Transit Partners announce updated opening date for light rail line
Purple Line (Maryland): dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy