Hudson Tunnel Project

A new two-track rail tunnel under the Hudson River between New Jersey and Manhattan, followed by the full rehabilitation of the existing North River Tunnel, giving four modern tracks between New York and New Jersey on the Northeast Corridor. The Gateway Development Commission secured the $16 billion commitment in July 2024. Construction started in November 2023, with the new tunnel expected in service by 2035 and the rehabilitation complete by 2038. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#hudson-tunnel-project.

At a glance

Hudson Tunnel Project at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerGateway Development Commission
LocationUnder the Hudson River, between New Jersey and Manhattan, New York, United States
TypeTunnel, two-track rail tunnel and rehabilitation of the existing tunnel
Budget announcedUS$16 billion, total commitment needed to complete the project, as of July 2024Gateway Development Commission
StageConstruction
Hudson Tunnel Project at a glance. Compiled by Mirage Metrics, November 2026

Milestones

Hudson Tunnel Project: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
October 2022Gateway Development Commission assumes NEPA sponsorshipHudson Tunnel Project
November 2023Construction starts on both sides of the Hudson RiverGateway Development Commission
July 8, 2024Full Funding Grant Agreement signed with the FTA for $6.88 billion; $4.06 billion in RRIF loans closedGateway Development Commission
Hudson Tunnel Project: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy