Île-aux-Tourtes Bridge reconstruction
A new Autoroute 40 bridge between Vaudreuil-Dorion and Senneville, on the island of Montréal, is being built north of the 1965 bridge under a design-build-finance contract. It consists of two structures, with three lanes in each direction. The Québec government puts the total cost at $2.3 billion. The first structure is scheduled to open in late 2026 and the second in 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#ile-aux-tourtes-bridge.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | Ministère des Transports et de la Mobilité durable du Québec | |
| Location | Vaudreuil-Dorion and Senneville, Québec, Canada | |
| Type | Bridge, highway bridge (two structures) | |
| Delivery model | design-build-finance | |
| Budget announced | C$2.3 billion, total project cost, financed entirely by the Québec government, as of October 2026 | Gouvernement du Québec |
| Stage | Construction | |
| Next milestone | 2026: First structure scheduled to open in late 2026, with five lanes managed according to peak traffic | Gouvernement du Québec |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| New Île-aux-Tourtes bridge (design, construction and financing) | design-build-finance | Groupe Nouveau Pont Île-Aux-Tourtes Inc. | awarded | 2023 | CDPQ |
Milestones
| Date | Milestone | Source |
|---|---|---|
| June 12, 2023 | Groupe Nouveau Pont Île-Aux-Tourtes closes its financing ($400 million credit facility and $380.2 million in senior secured bonds) | CDPQ |
| December 11, 2023 | Start of construction of the new bridge announced | Gouvernement du Québec |
| 2026 | First structure scheduled to open in late 2026, with five lanes managed according to peak traffic | Gouvernement du Québec |
| 2027 | Second structure scheduled to open, giving three lanes in each direction at all times | Gouvernement du Québec |
| 2029 | Deconstruction of the existing bridge scheduled for completion (final work in 2030) | Gouvernement du Québec |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
Projects that share an owner or a team member with this one:
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.