Île-aux-Tourtes Bridge reconstruction

A new Autoroute 40 bridge between Vaudreuil-Dorion and Senneville, on the island of Montréal, is being built north of the 1965 bridge under a design-build-finance contract. It consists of two structures, with three lanes in each direction. The Québec government puts the total cost at $2.3 billion. The first structure is scheduled to open in late 2026 and the second in 2027. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#ile-aux-tourtes-bridge.

At a glance

Île-aux-Tourtes Bridge reconstruction at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerMinistère des Transports et de la Mobilité durable du Québec
LocationVaudreuil-Dorion and Senneville, Québec, Canada
TypeBridge, highway bridge (two structures)
Delivery modeldesign-build-finance
Budget announcedC$2.3 billion, total project cost, financed entirely by the Québec government, as of October 2026Gouvernement du Québec
StageConstruction
Next milestone2026: First structure scheduled to open in late 2026, with five lanes managed according to peak trafficGouvernement du Québec
Île-aux-Tourtes Bridge reconstruction at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Île-aux-Tourtes Bridge reconstruction: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
New Île-aux-Tourtes bridge (design, construction and financing)design-build-financeGroupe Nouveau Pont Île-Aux-Tourtes Inc.awarded2023CDPQ
Île-aux-Tourtes Bridge reconstruction: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Île-aux-Tourtes Bridge reconstruction: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
June 12, 2023Groupe Nouveau Pont Île-Aux-Tourtes closes its financing ($400 million credit facility and $380.2 million in senior secured bonds)CDPQ
December 11, 2023Start of construction of the new bridge announcedGouvernement du Québec
2026First structure scheduled to open in late 2026, with five lanes managed according to peak trafficGouvernement du Québec
2027Second structure scheduled to open, giving three lanes in each direction at all timesGouvernement du Québec
2029Deconstruction of the existing bridge scheduled for completion (final work in 2030)Gouvernement du Québec
Île-aux-Tourtes Bridge reconstruction: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy