BART Silicon Valley Phase II
A six-mile, four-station extension of BART from Berryessa/North San José through downtown San José to Santa Clara, with three underground stations, one ground-level station and a maintenance facility. The Santa Clara Valley Transportation Authority is delivering it. Early works began in spring 2024 and major tunneling and construction in spring 2025, with completion estimated for 2036. Compiled by Mirage Metrics from the owner's and the companies' own publications.
- Published
- Updated
- Reading time
- 2 min
- Written by
- Mirage Metrics
Last checked November 10, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#bart-silicon-valley-phase-ii.
At a glance
| Field | Value | Source |
|---|---|---|
| Owner | Santa Clara Valley Transportation Authority | |
| Location | San José and Santa Clara, California, United States | |
| Type | Transit, rapid transit rail | |
| Delivery model | design-build | |
| Length | 9.7 km | Santa Clara Valley Transportation Authority |
| Stage | Construction |
Contracts and teams
Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.
| Contract | Delivery | Team | Members and roles | Status | Date | Source |
|---|---|---|---|---|---|---|
| General engineering consultant | Mott MacDonald/PGH Wong | awarded | January 2019 | Santa Clara Valley Transportation Authority | ||
| Contract Package 2: tunnel and trackwork (amended and restated agreement) | Kiewit Shea Traylor Joint Venture | awarded | Traylor Construction Group |
Milestones
| Date | Milestone | Source |
|---|---|---|
| April 5, 2018 | VTA Board approval | Santa Clara Valley Transportation Authority |
| April 26, 2018 | BART Board approval | Santa Clara Valley Transportation Authority |
| June 4, 2018 | Federal Record of Decision | Santa Clara Valley Transportation Authority |
| 2024 | Early works begin (spring 2024) | Santa Clara Valley Transportation Authority |
| 2025 | Major tunneling and construction begin (spring 2025) | Santa Clara Valley Transportation Authority |
Mirage Metrics and this project
This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.
If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.
Estimating a project like this one?
Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.