Hamilton LRT

A 14-kilometre, 17-stop light rail line across Hamilton from McMaster University to Eastgate Square. Its first major contract, the Package 1 civils and utilities works, went to the Hamilton Transit Alliance led by Aecon Infrastructure on April 30, 2026, opening an 18 to 24-month development phase. Compiled by Mirage Metrics from the owner's and the companies' own publications.

Published
Reading time
2 min
Written by
Mirage Metrics

Last checked November 9, 2026. Every fact below links to its source. You can also find the project on the map at /infrastructure-map#hamilton-lrt.

At a glance

Hamilton LRT at a glance. Compiled by Mirage Metrics, November 2026
FieldValueSource
OwnerMetrolinx
LocationHamilton, Ontario, Canada
TypeTransit, light rail
Delivery modelalliance
Budget announcedC$959 million, Metrolinx current baseline less exclusions, in year-of-expenditure dollars; omits progressive-contract scope not yet in its implementation phase and contracts awaiting procurement or award, so Metrolinx notes it is not the full project cost, as of June 30, 2026Metrolinx
Length14 kmMetrolinx
StageDevelopment phase
Next milestoneMarch 2027: Utility relocation enabling works completed (expected by the end of fiscal 2026-27)Metrolinx
Hamilton LRT at a glance. Compiled by Mirage Metrics, November 2026

Contracts and teams

Each contract is listed as the owner or the team announced it, with the members and the role the announcement gives each one.

Hamilton LRT: contracts and teams. Compiled by Mirage Metrics, November 2026
ContractDeliveryTeamMembers and rolesStatusDateSource
Package 1: Civils and Utilitiesalliance (development phase, then implementation)Hamilton Transit AllianceAecon Infrastructure (lead), Hatch (designer), Egis (designer), Systra (designer)awardedApril 30, 2026Metrolinx
Hamilton LRT: contracts and teams. Compiled by Mirage Metrics, November 2026

Milestones

Hamilton LRT: dated milestones. Compiled by Mirage Metrics, November 2026
DateMilestoneSource
April 30, 2026Hamilton Transit Alliance awarded the Package 1 Civils and Utilities contract; 18 to 24-month development phase beginsMetrolinx
Hamilton LRT: dated milestones. Compiled by Mirage Metrics, November 2026

Mirage Metrics and this project

This page describes the project from public sources only and says nothing about any work by Mirage Metrics. Mirage Metrics builds AI agents for heavy civil estimating and preconstruction teams. The agents measure quantities from each design package and tie them to their drawing, track what moves between packages, and check bid documents against each other. See AI for heavy civil estimating and the infrastructure map.

Projects that share an owner or a team member with this one:

If something on this page is wrong or missing, write to mehdi@miragemetrics.com with a public source.

Estimating a project like this one?

Mirage builds AI agents that measure quantities from each design package, track what moves between packages and check a bid's documents against each other, with every quantity tied to its drawing.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy