Polyethylene unit price, Alabama

Low bidders on ALDOT contracts carried a median of $3.99 per SY for item 665E000, polyethylene, over the 24 months to 28 AUG 2026, across 74 low bids. Half of all 258 bids fell between $2.71 and $5.31.

Owner
Alabama DOT
Item
665E000
Unit
SY
Latest letting
28 AUG 2026
$3.99Low bidder's median, per SY
$3.94Median of all bids, per SY
74Contracts in the window

By year of letting

Polyethylene, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20223737$2.79105$2.88
20234040$3.41107$3.55
20244141$4.50150$4.47
20253434$3.73119$3.76
20262020$3.1565$4.00
Polyethylene, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Polyethylene, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
030111$3.4945$4.27
05027$3.1528$4.00
09024$2.5621$2.63
09015$3.8718$3.25
02043$1.0012$3.10
07023$3.1810$3.95
01053$3.109$4.50
03053$4.589$4.30
05043$4.748$4.75
Polyethylene, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Polyethylene, ALDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
25 to 50018$3.19
500 to 50019$3.97
500 to 1,00018$3.65
1,000 to 5,50019$4.50
Polyethylene, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Polyethylene
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 2026202608280110402500$4.20$3.604VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
31 JUL 2026202607310010301500$3.29$5.206IKAROS, LLCALDOT
31 JUL 2026202607310170402500$88.00$3.984ALABAMA GRADING & EXCAVATION, LLC.ALDOT
31 JUL 20262026073102509021,000$2.50$2.816ARRINGTON CURB & EXCAVATION, INC.ALDOT
26 JUN 2026202606260350902500$2.63$2.865WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
29 MAY 2026202605290230301500$4.07$3.714WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
24 APR 2026202604240190502500$3.00$2.832IKAROS, LLCALDOT
24 APR 2026202604240410204500$1.00$2.223ROGERS GROUP, INC.ALDOT
27 MAR 2026202603270010606500$4.02$4.412NEWELL & BUSH, INC.ALDOT
27 MAR 2026202603270280404100$5.00$5.003APAC-ALABAMA, INC.ALDOT
27 MAR 20262026032703807041,000$2.35$2.353WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
27 FEB 2026202602270010301500$1.00$5.005GILLESPIE CONSTRUCTION, LLCALDOT
27 FEB 202620260227038050425$4.74$4.743DUNN CONSTRUCTION COMPANY, INC.ALDOT
27 FEB 2026202602270390705200$2.98$1.942WIREGRASS CONSTRUCTION COMPANY, INC.ALDOT
30 JAN 2026202601300030504500$4.80$4.803MCINNIS CONSTRUCTION, LLCALDOT
Latest ALDOT contracts carrying Polyethylene

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy