Solid Sodding unit price, Alabama

Low bidders on ALDOT contracts carried a median of $10.02 per SY for item 654A000, solid sodding, over the 24 months to 28 AUG 2026, across 38 low bids. Half of all 127 bids fell between $8.60 and $13.00.

Owner
Alabama DOT
Item
654A000
Unit
SY
Latest letting
28 AUG 2026
$10.02Low bidder's median, per SY
$10.10Median of all bids, per SY
38Contracts in the window

By year of letting

Solid Sodding, ALDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20221717$9.0155$8.30
20232727$9.0067$10.07
20241616$7.1254$9.00
20251717$11.7251$10.57
20261313$10.0348$10.51
Solid Sodding, ALDOT: unit prices by year

Bid prices as published, not adjusted for inflation.

By district

Solid Sodding, ALDOT: unit prices by district, last 24 months
DistrictLow bidsLow-bid medianAll bidsMedian, all bids
03017$10.4526$10.72
01056$10.2926$11.59
03023$14.5013$14.50
04043$9.006$8.64
Solid Sodding, ALDOT: unit prices by district, last 24 months

Districts with at least three low bids, over the last 24 months.

By quantity

Solid Sodding, ALDOT: low bidder's median by quantity band
Quantity (SY)Low bidsLow-bid median
70 to 4259$14.66
526 to 2,20010$7.60
2,375 to 6,3109$9.61
6,553 to 33,91610$9.73
Solid Sodding, ALDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Latest contracts with this item

Latest ALDOT contracts carrying Solid Sodding
LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
28 AUG 20262026082801104024,880$11.00$10.784VULCAN MATERIALS ASPHALT AND CONSTRUCTION,ALDOT
31 JUL 20262026073100103019,906$12.00$10.516IKAROS, LLCALDOT
31 JUL 202620260731017040214,893$10.03$10.264ALABAMA GRADING & EXCAVATION, LLC.ALDOT
31 JUL 20262026073102201052,675$8.50$9.125LAMBERT CONTRACTING, LLCALDOT
26 JUN 2026202606260320606100$20.00$20.001EAST ALABAMA PAVING COMPANY, INC.ALDOT
24 APR 2026202604240320301300$9.76$11.063APAC-ALABAMA, INC.ALDOT
27 MAR 20262026032702804046,310$9.61$9.613APAC-ALABAMA, INC.ALDOT
27 FEB 2026202602270010301526$10.45$12.005GILLESPIE CONSTRUCTION, LLCALDOT
27 FEB 2026202602270070902120$16.31$15.122PL RUSSELL LLCALDOT
30 JAN 20262026013000101052,375$10.00$10.436ROGERS GROUP, INC.ALDOT
30 JAN 202620260130031040132,092$6.05$6.051GARY INGRAM GRADING & PAVING, INC.ALDOT
30 JAN 20262026013003604032,781$5.40$5.401EAST ALABAMA PAVING COMPANY, INC.ALDOT
30 JAN 2026202601300640105613$10.52$12.007ALABAMA GRADING & EXCAVATION, LLC.ALDOT
05 DEC 2025202512050590302378$24.00$15.505BULLS CONSTRUCTION GROUP, LLCALDOT
07 NOV 20252025110705303012,011$9.82$9.962MCINNIS CONSTRUCTION, LLCALDOT
Latest ALDOT contracts carrying Solid Sodding

Filter this item by your own quantity, district and period, or check your price against it, in the ALDOT explorer.

How these prices were read

ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ALDOT's own: this item is compared with ALDOT contracts only.
  • Prices are bid prices, not paid prices, and are not adjusted for inflation. Use them as a reference range, never as a quote.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy